Organisation and impediments · cheat sheet

Dependency board

A shared, visible map of what each team needs from others, and when.

Common practice
5 steps
Used by Scrum Master, Project Manager

What it is

A visual board showing which teams or suppliers are waiting for which others, and when.

When to use it

As soon as two or more teams depend on each other.

Why it works

Dependencies between teams are where most delays hide. Seeing them early lets you plan handovers instead of discovering gaps.

Do

  • A three-week look-ahead is often enough to avoid most surprises.

Don't

  • Discovering dependencies at integration time.

Step by step

  1. List teams or suppliers Across the top or side.
  2. Add each dependency Who needs what from whom, by when.
  3. Draw the links Strings, lines or arrows.
  4. Review weekly In a short coordination meeting.
  5. Flag the at-risk ones And escalate early.
Also called: Program board, dependency mapPrint the blank template ↗

Worked example

The situation. A building contractor, IT team and equipment supplier on one site.

  1. Board shows IT needs cabling by week 12; equipment needs power by week 14.
  2. Cabling slips one week; IT is told the same day.

The result. No more finding out by accident.

Dependency list Print blank
Who needsWhatFrom whomBy whenStatus

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Scrum Master uses it

Basketly needs Arvid's help from Astrid (Payments Scrum Master)'s Payments team in Sprint 2. It sits on a shared board, agreed by both Product Owners.

How a Project Manager uses it

Aine (IT Lead) found out about finished cabling by chance. A weekly site coordination meeting with a 3-week look-ahead now shows which team is waiting for which.

Questions people ask

Isn't this what the schedule does?

The schedule holds it; the board makes it visible and discussed.