Working with an agile supplier
The booking system is built in two-week Sprints by a team six hours ahead. How do you follow it, plan with it and report it alongside a building schedule?
Stage goal: Build, buy, hire and keep everyone working together.
Stakeholders
Alfonso (Software Vendor Project Manager) Abigail (Finance Business Partner) Ananya (Vendor Development Lead)
How the day goes
- 08:00Sprint Review with the vendor team
- 11:00Status report progress with Abigail (Finance)
- 15:00Working across time zones with Ananya (Vendor)
Situation 1 of 4
08:00 · Sprint Review with the vendor teamAlfonso (Software Vendor Project Manager)
Join our Sprint Review on Friday. We'll show what we built and ask what to do next.
How do you take part?
In agile work, Sprint Reviews are where stakeholders inspect real results and shape what comes next. Take part, and bring the users.
Situation 2 of 4
11:00 · Status report progress with Abigail (Finance)Abigail (Finance Business Partner)
Your status report shows earned value for the building. What do I put for the booking system, which has no fixed design?
How do you report agile progress?
In hybrid projects, measure each part in the way that fits it, and connect them through shared milestones and one report.
Situation 3 of 4
15:00 · Working across time zones with Ananya (Vendor)Ananya (Vendor Development Lead)
Our team starts six hours ahead of you. Questions sent at your 4 p.m. wait until our next morning, so we lose a day.
How do you fix it?
Distributed teams need agreed overlap time, clear contacts, written decisions and respect for different working norms.
Used here Working agreements Decision log
Situation 4 of 4
15:00 · Working across time zones with Ananya (Vendor)Ananya (Vendor Development Lead)
In my culture, saying no to a client is rude. So when you ask “Can you finish by Friday?”, my developers say yes, even when they can't.
How do you work with that?
Cultures differ in how directly people say no. Adjust how you ask, and make bad news safe to share.
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Concept
Hybrid in practice
- Agile parts deliver in short cycles; predictive parts follow a plan. They meet at shared milestones and in one governance.
- The project manager connects them rather than forcing one approach on both.
Common practice
Reviews and backlogs
- In agile work, stakeholders shape the next steps by trying working results at regular reviews.
- Needs and feedback go to whoever orders the backlog, not straight to the developers.
Where you will meet this: Sprint Review · Product Backlog (Scrum)
Common practice
Distributed teams
- Teams across locations and time zones need agreed overlap time, named contacts and written decisions.
- Respect different working norms, holidays and languages.
Where you will meet this: Virtual teams · cultural awareness
Common practice
Working across cultures
- Cultures differ in how directly people disagree, how they treat hierarchy and how they see deadlines. Neither way is wrong; misunderstandings come from assuming everyone works like you.
- Ask open questions, agree how problems will be raised, confirm decisions in writing, and make it safe to bring bad news.
Where you will meet this: Cultural awareness · IPMA culture and values
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 22 complete
4 situations today.
Your responsibility todayDelivering a hybrid project
Technique you usedSprint Review, agile progress reporting, distributed teams
Key points to remember
- In agile work, Sprint Reviews are where stakeholders inspect real results and shape what comes next. Take part, and bring the users.
- In hybrid projects, measure each part in the way that fits it, and connect them through shared milestones and one report.
- Distributed teams need agreed overlap time, clear contacts, written decisions and respect for different working norms.
- Cultures differ in how directly people say no. Adjust how you ask, and make bad news safe to share.