Quality · cheat sheet

Version control

Keeping one register of the current versions of key documents, drawings and settings, withdrawing old versions and making sure everyone uses the latest.

Common practice
6 steps
Used by Project Manager

What it is

Keeping one register of the current versions of key documents, drawings and settings, approving changes before new versions are issued, and withdrawing old versions.

When to use it

Whenever several people or suppliers work from the same documents.

Why it works

When several people or suppliers work from copies, someone will use an old one. Version control prevents costly mistakes and rework.

Do

  • Mark old printed copies “superseded” or remove them from site.

Don't

  • Versions emailed around with no register.
  • Old copies left on site.

Step by step

  1. List what's controlled Drawings, specifications, plans, system settings.
  2. Number versions and set statuses Draft, approved, withdrawn.
  3. Keep one register The single source everyone checks.
  4. Approve changes first Linked to change control.
  5. Withdraw old versions And confirm everyone has the latest.
  6. Audit occasionally Spot-check what's actually in use.
Also called: Configuration management, document controlPrint the blank template ↗

Worked example

The situation. A building site with five trades.

  1. Electricians used floor plan v6; latest was v8.
  2. A drawing register, checked at every site meeting, with each trade signing for the current version.

The result. No more work to wrong drawings.

Document and drawing register Print blank
DocumentVersionStatusIssuedCon­firmed by
Floor planv8Approved12 MayAll trades
Floor planv6Withdrawn2 April

Filled in for: A building site with five trades.

DocumentVersionStatusIssuedChanged becauseCon­firmed by

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

Electricians used floor plan version 6 instead of 8. A drawing register, checked at every site meeting, stops it happening again.

Questions people ask

Is this only for engineering?

No. Contracts, plans and system settings all benefit from version control.