Risk · cheat sheet

Expected value and decision trees

Multiplying each possible outcome's probability by its impact and adding them up, to compare choices under uncertainty. A decision tree draws the choices, chances and outcomes.

Common practice
5 steps
Used by Project Manager

What it is

Expected value is probability × impact, added up across the possible outcomes of a choice. A decision tree draws the choices (squares), the chances (circles) and the outcomes, so options can be compared.

When to use it

For decisions with uncertain outcomes and significant money at stake.

Why it works

It makes decisions under uncertainty clearer and easier to defend, especially when choosing whether to pay now to avoid a possible cost later.

Do

  • Probabilities are estimates; show what happens if they're wrong.

Don't

  • Treating guessed probabilities as precise.
  • Ignoring a catastrophic worst case because its expected value is small.

Step by step

  1. Draw the decision A square with a branch for each option.
  2. Add chance branches Possible outcomes for each option, with probabilities that add up to 100%.
  3. Put a cost or value on each outcome Including the option's own cost.
  4. Calculate Multiply probability × value and add per option.
  5. Compare and sense-check Lowest expected cost, but can we survive the worst case?
Also called: EMV, decision tree analysisPrint the blank template ↗

Worked example

The situation. Should we pay €40,000 for a structural survey?

  1. No survey: 30% chance of a €300,000 problem → expected €90,000.
  2. Survey: €40,000, with most of that risk found and handled early.

The result. The survey was approved in one meeting.

Expected value worksheet Print blank
OptionOutcomeProba­bilityCostExpected
No surveyProblem found mid-works30%€300,000€90,000
No surveyNo problem70%€0€0
SurveySurvey cost100%€40,000€40,000

Filled in for: Should we pay €40,000 for a structural survey?

OptionOutcomeProba­bilityCost or valueProba­bility × value

Copy this structure, or print the blank version and fill it in by hand.

Before you use it: check these

CheckIf it fails
Probabilities and impacts estimated from evidenceShow the result for a range of probabilities
Many similar decisions, or a risk you can affordFor a single risk that could sink the project, judge the worst case too

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

Is the survey worth €40,000?

From Day 17: Putting numbers on risk of the Project Manager story

Without a structural survey there's a 30% chance of finding problems mid-works, costing about €300,000. With the survey, most of that is found early; a 5% chance remains.

Expected cost of each option025,00050,00075,000100,000No / survey: €90,000€90,000NosurveySurvey: €55,000€55,000Survey

Step by step

  1. Expected value without the survey0.30 × €300,000= €90,000
  2. With the survey€40,000 + 0.05 × €300,000= €55,000
  3. Difference90,000 − 55,000= €35,000 in favour of the survey
OptionCertain costChance of problemsCost if they happenExpected cost
No survey030%30000090000
Survey400005%30000055000

How to read the result

On average the survey saves €35,000, and it removes most of the chance of a €300,000 shock in the middle of the works.

What it led to

Order the survey. The decision tree goes into the business case file.

Do it in a spreadsheet

Expected cost=B2+C2*D2
Try it yourself: At what chance of problems would the survey stop being worth it (with 5% remaining after it)?

When p × 300,000 = 40,000 + 15,000: p = 18%.

In the roles

How a Project Manager uses it

Skipping the €40,000 survey has a 30% chance of a €300,000 problem: expected cost €90,000. The survey is clearly worth it.

Questions people ask

Is the option with the best expected value always right?

Not if its worst case is something you can't survive.