Finance system replacement53 questions5 phases

Ledgerline: a Project Manager case study

A food wholesaler with 900 staff still runs its finances on a 20-year-old system that only two people understand. Month-end closing takes 12 days. The finance director wants a new system live before the next financial year. You run the project.

What this case study tests
Make or buyData migrationEarned value and forecastsParallel runs

You're the Project Manager. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Stakeholders
Andrea (Project Manager)You
Alfred (Finance Director)Sponsor
Aiko (Financial Controller)Senior user: the finance team
Aurelio (Vendor Project Manager)The software supplier
Anil (IT Architect)Data and integrations
Abby (Accounts Payable Lead)Pays 4,000 invoices a month
Austin (Internal Auditor)Controls and compliance
Adriana (Change and Training Lead)People and new ways of working
Ledgerline

Starting up

A system only two people understand

Question 1 of 53

Choose 1
Aiko (Financial Controller)
The new system costs €1.2M and saves about €300,000 a year for six years. Our company uses a discount rate of 8%.

Which statement is right?

Learn it on Day 3: Is it worth it?

Question 2 of 53

Choose 1
Alfred (Finance Director)
Buy the system our competitor uses and install it.

What do you do first?

Learn it on Day 1: A request lands on your desk

Question 3 of 53

Choose 2
Alfred (Finance Director)
Options: upgrade the old system, buy a new one, outsource finance, or do nothing.

Which two statements are true?

Learn it on Day 3: Is it worth it?

Question 4 of 53

Choose 1
Aiko (Financial Controller)
The benefit is “better finance”.

How do you make it measurable?

Learn it on Day 3: Is it worth it?

Question 5 of 53

True or false
Alfred (Finance Director)
€1.6M approved, and I keep €150,000 back.

True or false: the €150,000 is the sponsor's reserve for unknown problems.

Learn it on Day 4: The decision

Question 6 of 53

Choose 1
Alfred (Finance Director)
Charter, really? We all know what we're doing.

What does the charter prevent?

Learn it on Day 5: Who's in charge here?

Question 7 of 53

Choose 1
Austin (Internal Auditor)
Nobody asked internal audit. We must sign off the controls.

How do you treat audit?

Learn it on Day 6: Everyone who matters

Technique: Stakeholder map (power and interest)

Question 8 of 53

Choose 1
Abby (Accounts Payable Lead)
My team is three days a week on the project, two in normal work. My manager says only one.

What do you do?

Learn it on Day 7: Who does what

Technique: Negotiation

Question 9 of 53

Choose 1
Anil (IT Architect)
At the kick-off we found out the old data has 30,000 duplicate suppliers.

What happens to the assumption that data is clean?

Learn it on Day 9: The kick-off

Technique: Risk identification

Question 10 of 53

Choose 1
Alfred (Finance Director)
We also want a new warehouse system. There's budget for one project now.

How do you help leadership choose?

Learn it on Day 2: Not the only proposal

Technique: Value vs effort

Question 11 of 53

Choose 1
Alfred (Finance Director)
The company's digital programme also runs the new warehouse system, and both projects need Anil (IT Architect) at the same time.

How do you handle it?

Learn it on Day 7: Who does what

Question 12 of 53

Choose 1
Alfred (Finance Director)
Halfway through, costs have risen by 20%. Should we carry on?

What do you use to decide?

Learn it on Day 3: Is it worth it?
Ledgerline

Planning

Scope, data and a deadline

Question 13 of 53

Choose 1
Aiko (Financial Controller)
Finance wants 140 custom reports.

How do you handle it?

Learn it on Day 10: What exactly are we building?

Technique: MoSCoW

Question 14 of 53

Choose 1
Aurelio (Vendor Project Manager)
Data migration: best 6 weeks, likely 9, worst 18.

What does the spread tell you?

Learn it on Day 12: How long will it really take?

Technique: Three-point estimating

Question 15 of 53

Choose 1
Anil (IT Architect)
Go-live must be on 1 April, the start of the financial year.

Which activities need the closest watch?

Learn it on Day 12: How long will it really take?

Technique: Critical path

Question 16 of 53

Choose 2
Alfred (Finance Director)
Here's the total. Where's the money for surprises?

Which two statements are true?

Learn it on Day 14: What will it cost?

Question 17 of 53

Choose 1
Austin (Internal Auditor)
Risk: the system goes live without proper approval controls.

Which response fits?

Learn it on Day 16: What could go wrong?

Technique: Risk responses

Question 18 of 53

Choose 1
Aurelio (Vendor Project Manager)
Should the implementation be fixed price?

What's a sensible approach?

Learn it on Day 18: Buying what we need

Technique: Contract types

Question 19 of 53

Choose 1
Anil (IT Architect)
Should we build our own system instead? We have developers.

How do you decide?

Learn it on Day 18: Buying what we need

Technique: Make or buy

Question 20 of 53

Choose 1
Aiko (Financial Controller)
How do we test that the system is good enough?

What makes a good quality plan here?

Learn it on Day 19: Good enough, and who hears what

Technique: Acceptance criteria and Given/When/Then

Question 21 of 53

Choose 1
Alfred (Finance Director)
Can we go live in February instead?

How do you answer?

Learn it on Day 20: Signing off the plan

Technique: Schedule compression

Question 22 of 53

Choose 1
Aiko (Financial Controller)
How do we make sure all 140 reporting needs end up built and tested?

What do you set up?

Learn it on Day 11: From needs to tests

Technique: Requirements traceability

Question 23 of 53

Choose 1
Aurelio (Vendor Project Manager)
Our software plan and your data migration plan don't match. Some tasks appear in both, some in neither.

How do you align them?

Learn it on Day 10: What exactly are we building?
Ledgerline

Delivering

Configuration, data and people

Question 24 of 53

Choose 1
Aurelio (Vendor Project Manager)
Can we skip the security review of the integrations to save time?

What do you decide?

Learn it on Day 21: Breaking ground

Question 25 of 53

Choose 1
Adriana (Change and Training Lead)
The finance team is anxious and resisting the new system.

What helps most?

Learn it on Day 23: Building the team

Technique: Active listening

Question 26 of 53

Choose 1
Aurelio (Vendor Project Manager)
Bank integration wasn't in our scope. That's extra.

What do you do first?

Learn it on Day 25: When a supplier slips

Technique: Negotiation

Question 27 of 53

Choose 1
Aiko (Financial Controller)
Test cycle 1: 210 defects.

How do you prioritise?

Learn it on Day 26: Quality on site

Technique: Pareto chart

Question 28 of 53

Choose 1
Aiko (Financial Controller)
Why do VAT errors keep returning after fixes?

How do you find the cause?

Learn it on Day 26: Quality on site

Technique: 5 Whys

Question 29 of 53

Choose 1
Abby (Accounts Payable Lead)
Rumours say the new system will cut jobs in accounts payable.

What do you do?

Learn it on Day 28: The neighbours are angry

Technique: Stakeholder communication plan

Question 30 of 53

Choose 1
Anil (IT Architect)
One of the two old-system experts is retiring next month.

What do you do?

Learn it on Day 30: A key person leaves

Technique: Knowledge transfer

Question 31 of 53

True or false
Aiko (Financial Controller)
Can't the vendor just add a field for us? It's tiny.

True or false: small configuration changes can skip change control.

Learn it on Day 30: A key person leaves

Question 32 of 53

Choose 1
Aurelio (Vendor Project Manager)
Join our Sprint Review on Friday to see the new approval screens.

How do you take part?

Learn it on Day 22: Working with an agile supplier

Technique: Sprint Review (for stakeholders)

Question 33 of 53

Choose 1
Adriana (Change and Training Lead)
One of my trainers keeps missing deadlines for the training materials.

What do you do?

Learn it on Day 24: Leading, not just managing

Technique: Difficult conversations

Question 34 of 53

Choose 1
Aiko (Financial Controller)
Finance staff are used to the old system's workarounds and don't trust the new one.

How do you help them?

Learn it on Day 31: Getting people ready

Question 35 of 53

Choose 1
Aurelio (Vendor Project Manager)
The cut-over weekend means people working 14-hour shifts, then driving home at night.

What do you do?

Learn it on Day 27: The accident
Ledgerline

Keeping control

Three months to 1 April

Question 36 of 53

Choose 1
Alfred (Finance Director)
Planned value €900,000, earned value €810,000, actual cost €950,000.

What does this show?

Learn it on Day 32: Are we on track?

Technique: Earned value

Question 37 of 53

Choose 1
Aurelio (Vendor Project Manager)
Can we report the integrations as green? We're nearly there.

What do you report?

Learn it on Day 32: Are we on track?

Technique: RAG status

Question 38 of 53

Choose 1
Austin (Internal Auditor)
A new regulation requires an extra approval step for large payments.

What happens?

Learn it on Day 33: The change request

Technique: Impact analysis

Question 39 of 53

Choose 1
Anil (IT Architect)
Data migration will be four weeks late. Go-live on 1 April is at risk.

Your tolerance is two weeks. What do you do?

Learn it on Day 34: Out of tolerance

Technique: Management by exception

Question 40 of 53

Choose 1
Alfred (Finance Director)
AC €950,000, EV €810,000, budget €1.6M. What's the final cost if this continues?

Estimate at completion with CPI ≈ 0.85?

Learn it on Day 34: Out of tolerance

Question 41 of 53

Choose 1
Aiko (Financial Controller)
Can I accept the accounts payable module?

How is it accepted?

Learn it on Day 36: Is it done?

Technique: Acceptance criteria and Given/When/Then

Question 42 of 53

Choose 1
Aurelio (Vendor Project Manager)
We added a dashboard nobody asked for. No charge.

What do you do?

Learn it on Day 36: Is it done?

Question 43 of 53

Choose 1
Alfred (Finance Director)
How much contingency is left?

What do you check?

Learn it on Day 38: The risk review

Technique: Reserve analysis

Question 44 of 53

Choose 1
Aiko (Financial Controller)
Every test cycle finds 50 to 60 defects, always in the same areas.

How do you look at it?

Learn it on Day 37: Is the process working?

Technique: Cost of quality

Question 45 of 53

Choose 1
Alfred (Finance Director)
The board wants to know how likely 1 April really is.

How do you answer?

Learn it on Day 17: Putting numbers on risk

Technique: Schedule simulation

Ledgerline

Closing

Go-live and the first month-end

Question 46 of 53

Choose 1
Aiko (Financial Controller)
Should we run month-end in both systems first?

Why rehearse?

Learn it on Day 41: Are we ready to open?

Technique: Dress rehearsal

Question 47 of 53

Choose 1
Alfred (Finance Director)
Are we going live on 1 May?

How do you decide?

Learn it on Day 41: Are we ready to open?

Technique: Go or no-go review

Question 48 of 53

Choose 1
Abby (Accounts Payable Lead)
Day one: 200 invoices stuck in approval.

What helps most?

Learn it on Day 42: Opening day

Technique: Hypercare

Question 49 of 53

Choose 1
Aurelio (Vendor Project Manager)
Can we close our contract?

What must happen?

Learn it on Day 43: Closing the contracts

Question 50 of 53

Choose 2
Alfred (Finance Director)
What do we tell the next system project?

Which two things belong in the lessons report?

Learn it on Day 44: Letting the team go

Question 51 of 53

Choose 1
Alfred (Finance Director)
Can we just close the project with an email?

What does formal closure include?

Learn it on Day 44: Letting the team go

Question 52 of 53

Choose 1
Aiko (Financial Controller)
Six months later: month-end takes 7 days, not 5.

How do you report it?

Learn it on Day 46: Was it worth it?

Technique: Benefits tracking

Question 53 of 53

Choose 1
Aiko (Financial Controller)
After go-live, who fixes problems during the first month-end close?

What do you plan?

Learn it on Day 42: Opening day