Finance system replacement 53 questions 5 phases
Ledgerline: a Project Manager case study A food wholesaler with 900 staff still runs its finances on a 20-year-old system that only two people understand. Month-end closing takes 12 days. The finance director wants a new system live before the next financial year. You run the project.
What this case study tests
Make or buy Data migration Earned value and forecasts Parallel runs
You're the Project Manager. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Stakeholders
Andrea (Project Manager) You Alfred (Finance Director) Sponsor Aiko (Financial Controller) Senior user: the finance team Aurelio (Vendor Project Manager) The software supplier Anil (IT Architect) Data and integrations Abby (Accounts Payable Lead) Pays 4,000 invoices a month Austin (Internal Auditor) Controls and compliance Adriana (Change and Training Lead) People and new ways of working Ledgerline
Starting up A system only two people understand
Question 1 of 53 Choose 1
Aiko (Financial Controller) The new system costs €1.2M and saves about €300,000 a year for six years. Our company uses a discount rate of 8%.
Which statement is right? The net present value is €600,000: savings minus cost Incorrect. That adds euros from different years as if they were worth the same today.Payback in 4 years proves it's the best option Incorrect. Payback ignores the time value of money and everything after the payback year.At 8%, the net present value is about €187,000 Correct. Right. Money later is worth less, so discounted payback always comes later than simple payback.
Learn it on Day 3: Is it worth it?
Check answer
Question 2 of 53 Choose 1
Alfred (Finance Director) Buy the system our competitor uses and install it.
What do you do first? Clarify the need: faster close, less reliance on two Correct. Right. Then compare options against that.Buy it: it worked well for their finance team last year Incorrect. Their needs and processes may differ.Write a 300-page specification before anything Incorrect. Too much detail before the decision to proceed.
Learn it on Day 1: A request lands on your desk
Check answer
Question 3 of 53 Choose 2
Alfred (Finance Director) Options: upgrade the old system, buy a new one, outsource finance, or do nothing.
Which two statements are true? Licence cost is the only thing that matters Incorrect. Implementation, training and running costs often outweigh it.All options compared on the same criteria Correct. Correct.The finance director's favourite is assumed Incorrect. That's choosing first.Doing nothing is assessed honestly too Correct. Correct.
Learn it on Day 3: Is it worth it?
Check answer
Question 4 of 53 Choose 1
Aiko (Financial Controller) The benefit is “better finance”.
How do you make it measurable? “A modern, reliable finance system” Incorrect. That's the output, not the benefit.Leave it vague, to be safe if it slips Incorrect. Then nobody can tell if it worked.Month-end close from 12 days to 5 Correct. Right.
Learn it on Day 3: Is it worth it?
Check answer
Question 5 of 53 True or false
Alfred (Finance Director) €1.6M approved, and I keep €150,000 back.
True or false: the €150,000 is the sponsor's reserve for unknown problems. True Correct. Correct. Using it needs the sponsor's agreement.False Incorrect. It's held by the sponsor, not the project.
Learn it on Day 4: The decision
Check answer
Question 6 of 53 Choose 1
Alfred (Finance Director) Charter, really? We all know what we're doing.
What does the charter prevent? Arguments about scope, authority and limits Correct. Right. It also names you and your authority.Nothing much: it's mostly a formality for audit Incorrect. Unclear authority causes most early conflicts.All the risks that the project could face Incorrect. It doesn't remove risks; it sets the frame.
Learn it on Day 5: Who's in charge here?
Check answer
Question 7 of 53 Choose 1
Austin (Internal Auditor) Nobody asked internal audit. We must sign off the controls.
Question 8 of 53 Choose 1
Abby (Accounts Payable Lead) My team is three days a week on the project, two in normal work. My manager says only one.
What do you do? Ask Abby to work evenings to fit it all in Incorrect. Burns out a key person.Do the work without her team's input, to save time Incorrect. They know the processes best.Agree her time with her manager, in writing Correct. Right. Matrix organisations need agreed time.
Learn it on Day 7: Who does what Technique: Negotiation
Check answer
Question 9 of 53 Choose 1
Anil (IT Architect) At the kick-off we found out the old data has 30,000 duplicate suppliers.
What happens to the assumption that data is clean? It failed: it's now an issue with an owner Correct. Right. Record it in the RAID log.Ignore it: the new system will fix the data Incorrect. Bad data in, bad data out.Delay the kick-off until the data is clean Incorrect. The issue needs action, not delay.
Learn it on Day 9: The kick-off Technique: Risk identification
Check answer
Question 10 of 53 Choose 1
Alfred (Finance Director) We also want a new warehouse system. There's budget for one project now.
How do you help leadership choose? Do both projects, each with half of the money Incorrect. Two underfunded projects rarely succeed.Score both on the same criteria, then decide Correct. Right. Finance wins on urgency: the two experts may leave.Pick whichever project the CEO likes more, to be safe Incorrect. Use agreed criteria.
Learn it on Day 2: Not the only proposal Technique: Value vs effort
Check answer
Question 11 of 53 Choose 1
Alfred (Finance Director) The company's digital programme also runs the new warehouse system, and both projects need Anil (IT Architect) at the same time.
How do you handle it? Raise it with the programme board to share Anil Correct. Right. Shared people are a programme decision; hiding the clash just delays both projects.Take Anil first: your deadline matters most Incorrect. The other project's deadline matters too.Hire a contractor quietly, without telling anyone Incorrect. Unplanned spending breaks governance.
Learn it on Day 7: Who does what
Check answer
Question 12 of 53 Choose 1
Alfred (Finance Director) Halfway through, costs have risen by 20%. Should we carry on?
What do you use to decide? Carry on: we've already spent so much on it, so finish Incorrect. Money already spent shouldn't drive the decision.Update the business case and let the board decide Correct. Right. The business case is the test used at every stage, not just at the start.Stop the project immediately to limit the loss Incorrect. Higher costs may still be justified.
Learn it on Day 3: Is it worth it?
Check answer
Ledgerline
Planning Scope, data and a deadline
Question 13 of 53 Choose 1
Aiko (Financial Controller) Finance wants 140 custom reports.
Question 14 of 53 Choose 1
Aurelio (Vendor Project Manager) Data migration: best 6 weeks, likely 9, worst 18.
Question 15 of 53 Choose 1
Anil (IT Architect) Go-live must be on 1 April, the start of the financial year.
Question 16 of 53 Choose 2
Alfred (Finance Director) Here's the total. Where's the money for surprises?
Which two statements are true? Each estimator adds their own hidden buffer Incorrect. Hidden buffers make estimates unreliable; keep contingency visible.The sponsor holds a reserve for unknowns Correct. Correct.Reserves aren't needed for software work Incorrect. Software projects have plenty of risk.Contingency for known risks is in the baseline Correct. Correct.
Learn it on Day 14: What will it cost?
Check answer
Question 17 of 53 Choose 1
Austin (Internal Auditor) Risk: the system goes live without proper approval controls.
Which response fits? Reduce it: audit reviews the design and tests Correct. Right.Accept it: audit will sign off in the end Incorrect. Control failures can cost far more.Transfer it to the vendor in the contract Incorrect. Controls are the company's responsibility.
Learn it on Day 16: What could go wrong? Technique: Risk responses
Check answer
Question 18 of 53 Choose 1
Aurelio (Vendor Project Manager) Should the implementation be fixed price?
What's a sensible approach? Fixed price for everything, to be safe on cost Incorrect. Unclear work gets padded or disputed.Fixed price where defined, capped T&M elsewhere Correct. Right.Time and materials for all of it, with no cap Incorrect. All cost risk stays with the buyer.
Learn it on Day 18: Buying what we need Technique: Contract types
Check answer
Question 19 of 53 Choose 1
Anil (IT Architect) Should we build our own system instead? We have developers.
How do you decide? Build it: it'll fit the business perfectly, for years Incorrect. And someone must maintain it for 15 years.Buy the cheapest package on the market today Incorrect. Cheapest to buy isn't cheapest to own.Compare whole-life cost, risk, time and support Correct. Right.
Learn it on Day 18: Buying what we need Technique: Make or buy
Check answer
Question 20 of 53 Choose 1
Aiko (Financial Controller) How do we test that the system is good enough?
Question 21 of 53 Choose 1
Alfred (Finance Director) Can we go live in February instead?
Question 22 of 53 Choose 1
Aiko (Financial Controller) How do we make sure all 140 reporting needs end up built and tested?
Question 23 of 53 Choose 1
Aurelio (Vendor Project Manager) Our software plan and your data migration plan don't match. Some tasks appear in both, some in neither.
How do you align them? Keep two plans and compare them now and then Incorrect. Gaps slip through.Let the vendor own all of the planning Incorrect. The company's work would be missing.One work breakdown structure for both Correct. Right. One WBS shows the whole scope and stops gaps and duplicates.
Learn it on Day 10: What exactly are we building?
Check answer
Ledgerline
Delivering Configuration, data and people
Question 24 of 53 Choose 1
Aurelio (Vendor Project Manager) Can we skip the security review of the integrations to save time?
What do you decide? No: security and legal requirements stay Correct. Right.Yes, just this once, to hit the date Incorrect. Financial data breaches are serious.Let the vendor decide which checks to skip Incorrect. Security is the company's responsibility.
Learn it on Day 21: Breaking ground
Check answer
Question 25 of 53 Choose 1
Adriana (Change and Training Lead) The finance team is anxious and resisting the new system.
What helps most? Tell them it's decided, and they must adapt to it Incorrect. Resistance grows.Listen, involve them in testing, train early Correct. Right. People adopt what they help shape.Wait until go-live and deal with it then Incorrect. Too late to build confidence.
Learn it on Day 23: Building the team Technique: Active listening
Check answer
Question 26 of 53 Choose 1
Aurelio (Vendor Project Manager) Bank integration wasn't in our scope. That's extra.
What do you do first? Pay it: they did do the extra work for us Incorrect. Check first.Do it in-house quietly instead, to save money Incorrect. Hides a scope question.Check the SOW; if missing, it's a change Correct. Right. The SOW says “bank integrations”: included.
Learn it on Day 25: When a supplier slips Technique: Negotiation
Check answer
Question 27 of 53 Choose 1
Aiko (Financial Controller) Test cycle 1: 210 defects.
How do you prioritise? Group by cause, and fix the top three causes Correct. Right.Fix them in the order they were logged Incorrect. Wastes effort on symptoms.Postpone them all until after the go-live date Incorrect. They'll block go-live.
Learn it on Day 26: Quality on site Technique: Pareto chart
Check answer
Question 28 of 53 Choose 1
Aiko (Financial Controller) Why do VAT errors keep returning after fixes?
How do you find the cause? Blame the vendor and ask for a proper fix Incorrect. Find the cause first.Ask why until you reach the process Correct. Right. Fix the configuration process.Add more testers to catch these errors Incorrect. Treats the symptom.
Learn it on Day 26: Quality on site Technique: 5 Whys
Check answer
Question 29 of 53 Choose 1
Abby (Accounts Payable Lead) Rumours say the new system will cut jobs in accounts payable.
Question 30 of 53 Choose 1
Anil (IT Architect) One of the two old-system experts is retiring next month.
Question 31 of 53 True or false
Aiko (Financial Controller) Can't the vendor just add a field for us? It's tiny.
True or false: small configuration changes can skip change control. True Incorrect. Small changes add up and can affect testing and controls.False Correct. Correct. One route for changes.
Learn it on Day 30: A key person leaves
Check answer
Question 32 of 53 Choose 1
Aurelio (Vendor Project Manager) Join our Sprint Review on Friday to see the new approval screens.
Question 33 of 53 Choose 1
Adriana (Change and Training Lead) One of my trainers keeps missing deadlines for the training materials.
Question 34 of 53 Choose 1
Aiko (Financial Controller) Finance staff are used to the old system's workarounds and don't trust the new one.
How do you help them? Respect their careful culture: involve them in tests Correct. Right. Trust grows when people see the system work on their own data.Switch off the old system and let them adapt Incorrect. Forced switches create errors and resistance.Let IT handle the training, as they know the system Incorrect. Finance staff need training built around their own work.
Learn it on Day 31: Getting people ready
Check answer
Question 35 of 53 Choose 1
Aurelio (Vendor Project Manager) The cut-over weekend means people working 14-hour shifts, then driving home at night.
What do you do? Praise their dedication in front of the team Incorrect. Praise encourages unsafe overwork.Treat fatigue as a safety risk: limit shifts Correct. Right. Tired people make mistakes and have accidents; safety comes first.Pay overtime and carry on as planned Incorrect. Money doesn't remove the risk.
Learn it on Day 27: The accident
Check answer
Ledgerline
Keeping control Three months to 1 April
Question 36 of 53 Choose 1
Alfred (Finance Director) Planned value €900,000, earned value €810,000, actual cost €950,000.
Question 37 of 53 Choose 1
Aurelio (Vendor Project Manager) Can we report the integrations as green? We're nearly there.
What do you report? Green, to keep the board feeling confident Incorrect. “Nearly there” isn't a rule.The colour the rules give, with a plan Correct. Right.Nothing at all, until it's back on track Incorrect. Silence hides risks.
Learn it on Day 32: Are we on track? Technique: RAG status
Check answer
Question 38 of 53 Choose 1
Austin (Internal Auditor) A new regulation requires an extra approval step for large payments.
What happens? Ignore it until after the go-live date, then see Incorrect. Non-compliance isn't an option.Add it quietly to the configuration, as required Incorrect. Unassessed changes break plans.A change request, with its impact known Correct. Right.
Learn it on Day 33: The change request Technique: Impact analysis
Check answer
Question 39 of 53 Choose 1
Anil (IT Architect) Data migration will be four weeks late. Go-live on 1 April is at risk.
Question 40 of 53 Choose 1
Alfred (Finance Director) AC €950,000, EV €810,000, budget €1.6M. What's the final cost if this continues?
Estimate at completion with CPI ≈ 0.85? €1.6M, the original budget Incorrect. That's the budget, not the forecast.About €1.88M: €1.6M ÷ 0.85 Correct. Right. Beyond the baseline; the sponsor needs to know now.€950,000, the cost to date Incorrect. That's what's been spent so far.
Learn it on Day 34: Out of tolerance
Check answer
Question 41 of 53 Choose 1
Aiko (Financial Controller) Can I accept the accounts payable module?
Question 42 of 53 Choose 1
Aurelio (Vendor Project Manager) We added a dashboard nobody asked for. No charge.
What do you do? Check it against controls, and record it Correct. Right. Gold-plating is a change.Accept it: a free dashboard is a bonus for users Incorrect. It may affect testing and support.Demand its removal without looking at it Incorrect. Check first.
Learn it on Day 36: Is it done?
Check answer
Question 43 of 53 Choose 1
Alfred (Finance Director) How much contingency is left?
Question 44 of 53 Choose 1
Aiko (Financial Controller) Every test cycle finds 50 to 60 defects, always in the same areas.
How do you look at it? Add more testers at the very end of each cycle Incorrect. Treats the symptom.Accept it as normal for a project like this Incorrect. A steady stream points to a process problem.Chart defects, and compare fix vs prevent Correct. Right. Prevention halves the defects.
Learn it on Day 37: Is the process working? Technique: Cost of quality
Check answer
Question 45 of 53 Choose 1
Alfred (Finance Director) The board wants to know how likely 1 April really is.
Ledgerline
Closing Go-live and the first month-end
Question 46 of 53 Choose 1
Aiko (Financial Controller) Should we run month-end in both systems first?
Question 47 of 53 Choose 1
Alfred (Finance Director) Are we going live on 1 May?
Question 48 of 53 Choose 1
Abby (Accounts Payable Lead) Day one: 200 invoices stuck in approval.
What helps most? The hypercare team fixes routing the same day Correct. Right.Tell finance the system is theirs to sort now Incorrect. Day one needs close support.Switch back to the old system until it's fixed Incorrect. Only if the fallback criteria are met.
Learn it on Day 42: Opening day Technique: Hypercare
Check answer
Question 49 of 53 Choose 1
Aurelio (Vendor Project Manager) Can we close our contract?
What must happen? Pay the last invoice, and forget about the contract Incorrect. Warranties and support need to be clear.Acceptance, claims, payment, a closure letter Correct. Right.Keep the contract open forever, just in case Incorrect. Close it formally.
Learn it on Day 43: Closing the contracts
Check answer
Question 50 of 53 Choose 2
Alfred (Finance Director) What do we tell the next system project?
Which two things belong in the lessons report? The names of people who made mistakes Incorrect. Blame doesn't help.Check data quality before planning Correct. Correct. A concrete recommendation.Nothing: every project is different Incorrect. Patterns repeat.Involve audit from the very start Correct. Correct.
Learn it on Day 44: Letting the team go
Check answer
Question 51 of 53 Choose 1
Alfred (Finance Director) Can we just close the project with an email?
What does formal closure include? A closure report, signed off by the sponsor Correct. Right.An email to the sponsor is enough to close Incorrect. Nobody can see what was delivered against what was approved.Keep the project open until benefits arrive Incorrect. Benefits are tracked by the business after closure.
Learn it on Day 44: Letting the team go
Check answer
Question 52 of 53 Choose 1
Aiko (Financial Controller) Six months later: month-end takes 7 days, not 5.
How do you report it? Call it a failure: the 5-day target was missed Incorrect. The project delivered; benefits are partly realised.From 12 to 7 days: progress, causes, actions Correct. Right.Change the target to 7 days to match it Incorrect. That destroys trust.
Learn it on Day 46: Was it worth it? Technique: Benefits tracking
Check answer
Question 53 of 53 Choose 1
Aiko (Financial Controller) After go-live, who fixes problems during the first month-end close?
What do you plan? The project team stays on indefinitely Incorrect. Projects end; operations must own the system.The vendor's helpdesk alone, from day one Incorrect. The finance team needs closer support at first.A supported handover to operations Correct. Right. The first month-end is when problems show; support must be there.
Learn it on Day 42: Opening day
Check answer