The accident
A worker falls from a scaffold on site. He's hurt, but conscious. What happens in the next hour, the next day and the next week?
Stage goal: Build, buy, hire and keep everyone working together.
Team
Antonia (Quality and Compliance Lead)
Stakeholders
Arash (Contractor Project Manager) Atticus (Director of Community Health)
Techniques today 5 Whys Blameless review
Documents today Lessons log Incident report
How the day goes
- 10:15Call from Arash: an accident on site
- 13:00Reporting and investigation with Antonia (Compliance Lead)
- 16:00Telling people, starting with Atticus (Sponsor)
Situation 1 of 3
10:15 · Call from Arash: an accident on siteArash (Contractor Project Manager)
One of our workers fell from the scaffold. The ambulance is here. What do we do?
What comes first?
In an incident: people first, make the area safe, preserve evidence and report as required. The schedule comes later.
Used here Incident report
Situation 2 of 3
13:00 · Reporting and investigation with Antonia (Compliance Lead)Antonia (Quality and Compliance Lead)
The health and safety inspector will investigate. What do we do on our side?
How is the incident investigated?
Investigate incidents without blame, to find and fix what in the process allowed them, and cooperate with the authorities.
Situation 3 of 3
16:00 · Telling people, starting with Atticus (Sponsor)Atticus (Director of Community Health)sponsor
The local paper is asking. And will this delay the opening?
What do you do?
Report incidents honestly and quickly upwards, speak with one voice to the public, and record the lessons.
Used here Lessons log
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Concept
Incident response
- People first, make the area safe, preserve evidence, and report as the law requires.
- The schedule comes after safety, always.
Where you will meet this: Health and safety · incident reporting
Common practice
Investigate without blame
- Look for what in the process allowed the incident, with the contractor and the authorities.
- Fix the process, and share the lesson.
Common practice
One honest voice
- Brief the sponsor quickly with facts and actions. Speak to the public with one agreed message.
- Never downplay a safety incident.
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 27 complete
3 situations today.
Your responsibility todayResponding to a safety incident
Technique you usedIncident response, blameless investigation, honest communication
Key points to remember
- In an incident: people first, make the area safe, preserve evidence and report as required. The schedule comes later.
- Investigate incidents without blame, to find and fix what in the process allowed them, and cooperate with the authorities.
- Report incidents honestly and quickly upwards, speak with one voice to the public, and record the lessons.
Techniques today 5 Whys Blameless review
Documents today Lessons log Incident report