Scope and scheduling · cheat sheetRequirements traceability
Linking each requirement to where it comes from, the deliverable that meets it and the test that checks it.
Common practice
6 steps
Used by Project Manager
What it is
Linking each requirement to its source, to the deliverable that meets it, and to the test that checks it, usually in a traceability matrix.
When to use it
Once requirements are agreed, and kept up to date through design, build, test and changes.
Why it works
It shows at any moment whether every need is covered, built and tested, and what a change will affect.
Do
- Keep it as simple as the project allows; a spreadsheet is often enough.
Don't
- A matrix nobody updates after design.
- Requirements without tests.
Step by step
Number every requirement Unique IDs.
Record the source Who asked and why.
Link to deliverables Which part of the design or product meets it?
Link to tests Which test proves it?
Track status Designed, built, tested, accepted.
Use it for changes Find every requirement a change touches.
Worked example
The situation. A new hospital ward.
- Requirement R12: hand-wash basin in every bay.
- Met by drawing M-03; tested by inspection IT-07.
- R19 (hearing loop) had no deliverable: added to the electrical package.
The result. No requirement reached opening day untested.
| ID | Requirement | Met by | Tested by | Status |
|---|
| R12 | Hand-wash basin in every bay | Drawing M-03 | Inspection IT-07 | Tested |
| R19 | Hearing loop at reception | Electrical package (added) | Test IT-15 | Designed |
Filled in for: A new hospital ward.
| ID | Requirement | Source | Met by | Tested by | Status |
|---|
| | | | | |
| | | | | |
| | | | | |
| | | | | |
Copy this structure, or print the blank version and fill it in by hand.
In the roles
How a Project Manager uses it
Riverside's matrix shows two requirements with no owner (the hearing loop and the baby-changing room). Both are assigned before design is finished.
Questions people ask
Is it only for software?
No. Buildings, events and services all have requirements worth tracing.