Copy this structure, or print the blank version and fill it in by hand. Categories: prevention · appraisal (checking) · internal failure · external failure.
How to do it with real data
The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Slow access costs about €67,000 a year before counting harm to patients. The emergency visits are paid by the wider health system, so they're shown separately when reporting the clinic's own savings.
What it led to
Use about €67,000 a year as the size of the problem in the project selection, with the method agreed with Abigail (Finance Business Partner).
Do it in a spreadsheet
Cost a year
=B2*C2
Total
=SUM(D2:D4)
Try it yourself: If missed appointments fell from 15% to 10%, how much would that line save a year?
If the project reaches its goal, how much of the €67,035 cost of poor quality goes away? Amara and Abigail (Finance Business Partner) estimate each line.
Reaching the goal is worth about €35,000 a year, around half the cost of poor quality. €22,785 is the clinic's own money; €12,480 is avoided cost for the wider health system.
What it led to
The charter says “about €35,000 a year”, split into the clinic's savings and avoided cost, with the method agreed with Abigail (Finance Business Partner). The real figures are checked in Control.
Do it in a spreadsheet
Fewer missed appointments
=12700*(0.15-0.08)
Saving
=B2*15
Total
=SUM(D2:D4)
Try it yourself: If missed appointments only fell to 10%, what would the total saving be?
12,700 × 5% × €15 = €9,525; plus €9,450 and €12,480 = €31,455 a year.
The project is worth about €36,700 a year, slightly more than the €35,300 estimated. On the clinic's own savings alone, it pays back in about 9 months. Covering the lost sessions costs nothing extra: they were already in the budget.
What it led to
Abigail (Finance Business Partner) signs off the benefits. They will be checked again at 12 months.
Do it in a spreadsheet
Missed appointments
=12700*(0.157-0.083)*15
Total
=SUM(D2:D4)
Payback in months
=18500/(D2+D3)*12
Try it yourself: If missed appointments had only fallen to 10%, what would the payback be?
12,700 × 5.7% × €15 = €10,859; with €10,125 that's €20,984 a year of clinic savings; €18,500 ÷ €20,984 × 12 = about 10.6 months.
In the roles
How a Project Manager uses it
Booking system defects found in testing cost days of rework. A joint requirements review each Sprint halves them within two cycles.