Library move 51 questions 5 phases
Readwell: a Project Manager case study Readwell's central library is in a building with a leaking roof and no lift. The city will move it into a new community hub across the square: 180,000 books, a children's floor, computers and a café run by volunteers. The library may close for at most six weeks. You run the project.
What this case study tests
Scope and exclusions Volunteers as a workforce Quality criteria Reopening
You're the Project Manager. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Stakeholders
Amira (Project Manager) You Aldous (Head of Culture) Sponsor Agnes (Chief Librarian) Senior user: staff and readers Axel (Removals Supplier Manager) Moves the books Ama (IT Manager) Computers, Wi-Fi and the catalogue Aaliyah (Friends of the Library Chair) Volunteers and regular readers Anders (Facilities Manager) Runs the new hub building Ayla (Project Coordinator) Plans and logs Readwell
Starting up A leaking roof and a new building
Question 1 of 51 Choose 1
Aldous (Head of Culture) Just move everything over the summer.
What is your first step? Clarify the need and constraints, like the six weeks Correct. Right. The six-week limit shapes everything.Hire removers for July, before they're all booked Incorrect. Before the need and constraints are clear, you can't know what to move or when.Close the library until the new hub is completely ready Incorrect. Readers depend on it; closure must be limited.
Learn it on Day 1: A request lands on your desk
Check answer
Question 2 of 51 Choose 1
Agnes (Chief Librarian) Do we even need to move all 180,000 books?
Which option should the analysis include? Only “move everything”, as the council asked Incorrect. One option isn't an analysis.Every real option, including doing nothing Correct. Right. Including doing nothing shows what the move really changes.Only the cheapest option, to save time Incorrect. Compare on all criteria.
Learn it on Day 3: Is it worth it?
Check answer
Question 3 of 51 Choose 1
Aldous (Head of Culture) The benefit is obvious: a nicer library.
How do you make benefits measurable? “A nicer, brighter library for everyone in the city” Incorrect. Not measurable.Skip benefits: it's only a move, not a change to the service Incorrect. The move costs money; benefits justify it.Visitors, access and events, from a baseline to a target Correct. Right.
Learn it on Day 3: Is it worth it?
Check answer
Question 4 of 51 True or false
Aldous (Head of Culture) Approved: €900,000. I'll keep €80,000 for surprises.
True or false: the €80,000 is the project's contingency to spend on known risks. True Incorrect. It's the sponsor's management reserve for unknowns.False Correct. Correct. Known risks are covered by contingency inside the €900,000.
Learn it on Day 4: The decision
Check answer
Question 5 of 51 Choose 1
Aldous (Head of Culture) Do we really need a charter for a move?
Why write one? It sets scope, limits, budget and your authority Correct. Right. Short, but it prevents later arguments.It isn't needed for small projects like a move Incorrect. Small projects still need clear authority and limits.Only to keep the auditors happy later on Incorrect. It's for everyone involved.
Learn it on Day 5: Who's in charge here?
Check answer
Question 6 of 51 Choose 1
Aaliyah (Friends of the Library Chair) Regular readers and volunteers feel nobody listens to them.
How do you engage them? Send them the finished plan to read and comment Incorrect. Listening comes first.Meet them, listen, and agree how they're involved Correct. Right. Volunteers will help with the move.Ignore them: the council decides, not the volunteers Incorrect. They're the library's most loyal users.
Learn it on Day 6: Everyone who matters Technique: Active listening
Check answer
Question 7 of 51 Choose 1
Ayla (Project Coordinator) Ama (IT Manager) and Anders (Facilities Manager) both think the Wi-Fi is theirs.
What clarifies it? Let them argue it out until one of them gives way Incorrect. Unclear ownership becomes a gap on opening day.Give the Wi-Fi to the removals company to set up Incorrect. Not their expertise.A RACI with one accountable person for the Wi-Fi Correct. Right.
Learn it on Day 7: Who does what Technique: RACI
Check answer
Question 8 of 51 Choose 1
Agnes (Chief Librarian) My staff are anxious about the new building and new ways of working.
What should the kick-off include for them? Why, what changes for them, timeline, questions Correct. Right. People leave knowing what happens to them.Only the detailed removal schedule for each day Incorrect. Their concerns need space too.Nothing: their own managers will tell them later Incorrect. A shared start builds trust.
Learn it on Day 9: The kick-off Technique: Kick-off meeting
Check answer
Question 9 of 51 Choose 1
Aldous (Head of Culture) Councillors ask why we spend €2M moving the library instead of just fixing the roof.
How do you compare the two options? Compare only the move cost with the roof repair cost Incorrect. That ignores running costs and the lack of a lift.Say the new building is simply better for everyone, full stop Incorrect. Councillors need evidence, not opinion.Compare both options' net present value over 25 years Correct. Right. Repairs, running costs, accessibility and visitor benefits over 25 years, all discounted to today's money: running costs and benefits often outweigh the first cost.
Learn it on Day 3: Is it worth it?
Check answer
Question 10 of 51 Choose 1
Aldous (Head of Culture) The hub is part of the city's regeneration programme. How much can you change without asking me?
How do you agree your authority? Agree tolerances within which you decide alone Correct. Right. Tolerances, for example one week and 5% of cost, let you act; anything bigger goes to the project board, and you report to the regeneration programme.Ask Aldous about every single change, however small Incorrect. Everything would slow down.Approve every change yourself, however big Incorrect. Big changes need the board's approval.
Learn it on Day 7: Who does what
Check answer
Readwell
Planning 180,000 books in six weeks
Question 11 of 51 Choose 1
Agnes (Chief Librarian) Staff also want new shelving systems, self-service kiosks and a podcast studio.
How do you handle the requests? Include everything, to keep all the users happy Incorrect. Breaks the budget and the six weeks.Prioritise against the objective; record the rest Correct. Right.Refuse them all: the scope is already set, so no Incorrect. Some may be essential to the new service.
Learn it on Day 10: What exactly are we building? Technique: MoSCoW
Check answer
Question 12 of 51 Choose 1
Ayla (Project Coordinator) How do we make sure nothing is forgotten?
Question 13 of 51 Choose 1
Axel (Removals Supplier Manager) Packing and moving: best 3 weeks, likely 4, worst 7.
Question 14 of 51 Choose 1
Ama (IT Manager) The catalogue system can't be moved until the network in the hub is live.
Question 15 of 51 Choose 1
Anders (Facilities Manager) The total estimate, piece by piece, is €840,000.
What is the remaining €60,000 for? A party for the staff at the opening of the hub Incorrect. Not its purpose.Return it to the council immediately, as spare Incorrect. Known risks still need cover.Contingency for known risks, in the baseline Correct. Right.
Learn it on Day 14: What will it cost?
Check answer
Question 16 of 51 Choose 1
Ayla (Project Coordinator) Risk: rare books damaged in the move.
Which response fits? Reduce it with careful packing, and transfer it Correct. Right.Accept it: some damage is unavoidable in a move Incorrect. Irreplaceable items need more.Avoid it by leaving the rare books behind Incorrect. The old building is leaking.
Learn it on Day 16: What could go wrong? Technique: Risk responses
Check answer
Question 17 of 51 Choose 1
Ayla (Project Coordinator) We listed 25 risks. Everyone says theirs is the biggest.
How do you rank them? By whoever shouts loudest about their own risks Incorrect. Volume isn't evidence.Score every risk on agreed scales; focus on the top Correct. Right. Shared scales turn opinions into a ranking.Treat them all exactly the same way, to be fair Incorrect. Equal effort on unequal risks wastes time.
Learn it on Day 16: What could go wrong? Technique: Probability-impact matrix
Check answer
Question 18 of 51 Choose 1
Axel (Removals Supplier Manager) Should we charge a fixed price for the whole move?
When does that work best? Always, whatever is known about the job in advance Incorrect. On unclear scope, prices balloon or claims follow.Never for moves, as the volumes always change Incorrect. It works when scope is clear.When the volume is clearly defined by an inventory Correct. Right.
Learn it on Day 18: Buying what we need Technique: Contract types
Check answer
Question 19 of 51 Choose 1
Agnes (Chief Librarian) Quality means every book exactly where it was, on day one.
Is that the right quality requirement? Agree measurable criteria instead, like 99.5% findable Correct. Right. Requirements you can check.Yes: perfection is the only acceptable standard Incorrect. Unmeasurable and unrealistic.Whatever the remover delivers on the day itself Incorrect. The client defines quality.
Learn it on Day 19: Good enough, and who hears what
Check answer
Question 20 of 51 Choose 1
Aaliyah (Friends of the Library Chair) How will readers know where to find us during the closure?
Question 21 of 51 Choose 1
Aldous (Head of Culture) The library move uses our IT department's project method, written for software.
Question 22 of 51 Choose 1
Ama (IT Manager) The self-service kiosks will store readers' card numbers and borrowing history.
What do you do? An early check of what data is used and protected Correct. Right. A data protection impact assessment early: what data, why, who sees it, how long it's kept, and safeguards; it's a legal requirement for compliance.Nothing: the kiosk supplier handles all of that Incorrect. The city is responsible for readers' data.Collect everything, in case it proves useful later on Incorrect. Collect only what's needed.
Learn it on Day 13: Rules we must follow
Check answer
Question 23 of 51 Choose 1
Ayla (Project Coordinator) Ama (IT Manager) is booked for 150% during the catalogue move week.
How do you fix it? Ask her to work nights that month, to catch up the load Incorrect. Burnout at the riskiest moment.Move tasks that have float, and get vendor help Correct. Right.Delay the reopening by a couple of weeks, to be safe Incorrect. Try moving work with float first.
Learn it on Day 15: Who's needed when? Technique: Resource levelling
Check answer
Question 24 of 51 Choose 1
Ama (IT Manager) The book move is fixed to the day, but the new computer area depends on what users actually want.
How do you plan it? Plan the computer area in full detail now, to be safe Incorrect. Users' needs would be guessed, not learned.A hybrid: plan the move, and shape services with users Correct. Right. Plan the move predictively and develop the digital services iteratively with library users: firm plans for logistics, short agile cycles for services.Run the book move itself in short iterations too Incorrect. The six-week closure needs a firm plan.
Learn it on Day 8: How should we run it?
Check answer
Question 25 of 51 Choose 1
Anders (Facilities Manager) The new hub needs accessibility, fire safety and data protection checks before it can open.
How do you make sure it's ready? Check it all together in the week before opening Incorrect. Too late to fix anything that fails.Leave it to the building owner to sort out Incorrect. The library remains responsible for its services.A compliance checklist with owners and dates Correct. Right. A checklist of legal requirements, built into the plan and checked before reopening; compliance planned early avoids a delayed opening.
Learn it on Day 13: Rules we must follow
Check answer
Readwell
Delivering Boxes, shelves and cables
Question 26 of 51 Choose 1
Axel (Removals Supplier Manager) My crew wants to carry book crates down the old stairs without the lift hoist. Faster.
What do you decide? Yes, as long as they're very careful Incorrect. Heavy crates on old stairs injure people.Let the crew decide what's safe for them Incorrect. Safety rules are set by the project.No: the agreed safe lifting method stays Correct. Right. Safety isn't traded for speed.
Learn it on Day 21: Breaking ground
Check answer
Question 27 of 51 Choose 1
Aaliyah (Friends of the Library Chair) Twenty volunteers want to help pack books.
How do you use them? Give them a clear work package and safety rules Correct. Right.Let them pack whatever they like, wherever they like Incorrect. Chaos and mislabelled boxes.Turn them away: volunteers aren't insured for this Incorrect. Their help and goodwill are valuable.
Learn it on Day 21: Breaking ground Technique: Work authorisation
Check answer
Question 28 of 51 Choose 1
Agnes (Chief Librarian) Two of my senior librarians are on leave during the move.
What do you do? Ask them to cancel their summer leave for the move Incorrect. Not fair, and unlikely to work.Treat it as a risk happening: adjust, bring in cover Correct. Right.Carry on as planned, and hope the work still fits the weeks Incorrect. Fewer experts means slower shelving.
Learn it on Day 23: Building the team
Check answer
Question 29 of 51 Choose 1
Axel (Removals Supplier Manager) We need an extra €15,000: there were more books than in your inventory.
What do you do? Pay immediately, to keep the move on track this week Incorrect. Check first.Refuse it outright: the contract price was fixed Incorrect. If the inventory was wrong, the claim may be fair.Check the contract, ask for evidence, agree fairly Correct. Right.
Learn it on Day 25: When a supplier slips Technique: Negotiation
Check answer
Question 30 of 51 Choose 1
Agnes (Chief Librarian) Spot checks show 4% of books on the wrong shelves.
What do you do? Group errors by cause, and fix the biggest first Correct. Right. A few causes behind most errors.Re-shelve everything from scratch to be certain Incorrect. Out of proportion.Accept it: some errors are inevitable in a move Incorrect. It fails the 99.5% criterion.
Learn it on Day 26: Quality on site Technique: Pareto chart
Check answer
Question 31 of 51 Choose 1
Aaliyah (Friends of the Library Chair) A local paper says the move will cut opening hours.
Question 32 of 51 Choose 1
Ama (IT Manager) I've been offered a job elsewhere. I leave in two weeks, just before the catalogue move.
Question 33 of 51 True or false
Anders (Facilities Manager) Agnes (Chief Librarian) asked my team to move the reading room walls.
True or false: building changes requested directly by users can go ahead if facilities agree. True Incorrect. They need to go through change control, with impact assessed.False Correct. Correct. One route for all changes.
Learn it on Day 30: A key person leaves
Check answer
Question 34 of 51 Choose 1
Axel (Removals Supplier Manager) The shelving supplier has gone into administration. Half the shelves arrived.
Question 35 of 51 Choose 1
Agnes (Chief Librarian) My staff are being asked to work in a completely new way: roaming instead of behind a desk.
How do you help them? Tell them they'll need to adapt to the new way Incorrect. Resistance grows.Explain why, involve them, and train them early Correct. Right.Keep the old desks, so that nothing has to change Incorrect. That undoes the benefit of the new building.
Learn it on Day 31: Getting people ready Technique: The change curve
Check answer
Question 36 of 51 Choose 1
Agnes (Chief Librarian) Long-serving staff love the old building and resist the new self-service machines.
How do you lead them through it? Lead with empathy: involve staff, train early Correct. Right. Involve staff in designing the new layout, respect the library's culture, train them early and celebrate together; staff who shape the change help others adopt it.Install the machines and expect staff to adapt Incorrect. Resistance grows when people feel ignored.Leave it to HR to handle the staff's concerns Incorrect. Helping staff accept the move is part of delivering it, not someone else's task.
Learn it on Day 31: Getting people ready
Check answer
Readwell
Keeping control Four weeks in
Question 37 of 51 Choose 1
Ayla (Project Coordinator) Planned value €600,000, earned value €540,000, actual cost €570,000.
Question 38 of 51 Choose 1
Aldous (Head of Culture) Just tell me everything is fine.
What do you do? An honest amber status, with a recovery plan Correct. Right.Say it's fine, to avoid worrying anyone Incorrect. Hiding problems removes the sponsor's chance to help.Send all the logs instead of a summary Incorrect. A short summary is what's needed.
Learn it on Day 32: Are we on track? Technique: RAG status
Check answer
Question 39 of 51 Choose 1
Agnes (Chief Librarian) We'd like to add a quiet study room after all.
Question 40 of 51 Choose 1
Ama (IT Manager) The new network will be live two weeks late. Reopening would slip beyond six weeks.
Question 41 of 51 Choose 1
Axel (Removals Supplier Manager) We added free bookends to every shelf.
What is this? Gold-plating: check it, record it, use the process Correct. Right.Free, so there's no issue with it at all for us Incorrect. Extras are changes too.A breach of contract that should be penalised Incorrect. Check before judging.
Learn it on Day 36: Is it done?
Check answer
Question 42 of 51 Choose 1
Agnes (Chief Librarian) Can I sign off the children's floor?
Question 43 of 51 Choose 1
Ayla (Project Coordinator) The risk review keeps listing the same risks.
What should it focus on? Nothing new: drop the weekly review now, to save time Incorrect. Risks change near the end.Every single risk, in full detail, each and every week Incorrect. Focus beats length.What changed, triggers, and new or closed risks Correct. Right.
Learn it on Day 38: The risk review Technique: Risk identification
Check answer
Question 44 of 51 Choose 2
Aldous (Head of Culture) Before reopening, the board wants to check the business case.
Which two questions does that check answer? Is it still worth it, at the latest costs? Correct. Correct.Who exactly caused the network delay? Incorrect. That's for lessons, not the gate.Is it still affordable to finish the move? Correct. Correct.Which colour should the new carpets be? Incorrect. Not a business case question.
Learn it on Day 40: Ready for the last stage? Technique: Stage gate
Check answer
Question 45 of 51 Choose 1
Aldous (Head of Culture) The city needs €60,000 back.
How do you decide what goes? Cut every budget line by the same share Incorrect. May break something critical.By priority and benefit, then re-baseline Correct. Right.Refuse it outright: the budget was agreed Incorrect. Show the consequences instead.
Learn it on Day 35: The budget is cut Technique: MoSCoW
Check answer
Readwell
Closing Reopening day
Question 46 of 51 Choose 1
Agnes (Chief Librarian) Shall we do a practice day with staff and volunteers as readers?
Question 47 of 51 Choose 1
Agnes (Chief Librarian) When does the hub stop being your project and become my library?
How do you hand over? Formally, with open items, then joint support Correct. Right.Informally, on the day the library opens again Incorrect. Ownership must be clear.When every small issue has been fixed Incorrect. List them and hand over.
Learn it on Day 42: Opening day Technique: Hypercare
Check answer
Question 48 of 51 Choose 1
Axel (Removals Supplier Manager) Can you close our contract?
Question 49 of 51 Choose 1
Aldous (Head of Culture) What do we keep for the next move?
What does the lessons report include? A list of the mistakes made by each person Incorrect. Blame helps nobody.Only the final cost against the budget Incorrect. Too little.What worked, what didn't, and recommendations Correct. Right.
Learn it on Day 44: Letting the team go
Check answer
Question 50 of 51 Choose 1
Aaliyah (Friends of the Library Chair) Visits are up 30% in three months, but older readers find the kiosks hard.
How do you report this? Against the baseline, with a cause and an action Correct. Right.Only report the 30% rise, which worked well Incorrect. Report honestly, including problems.Remove the kiosks and go back to the desks Incorrect. Fix the cause first.
Learn it on Day 46: Was it worth it? Technique: Benefits tracking
Check answer
Question 51 of 51 Choose 1
Aldous (Head of Culture) Readers now want a mobile library van.
What happens? Add it to the closed project's remaining budget Incorrect. New work needs its own decision.A new request, assessed on its own business case Correct. Right. The cycle starts again.Turn it down: the project is now closed for good Incorrect. Good ideas deserve a hearing.
Learn it on Day 46: Was it worth it?