Risk · cheat sheet

Probability-impact matrix

A grid that ranks risks by how likely they are and how much they'd hurt (or help), using agreed scales.

Common practice
6 steps
Used by Project Manager

What it is

A grid that ranks risks by how likely they are and how much they'd affect the objectives, using scales everyone has agreed. Each risk lands in a cell; the colour of the cell suggests how urgently to act.

When to use it

After identifying risks, to decide which deserve detailed responses. Repeat at each review.

Why it works

Without shared scales, every risk is “high”. Agreed definitions turn opinions into a ranking, so attention goes to the few risks that matter most.

Do

  • Scores are a ranking aid, not precise numbers.
  • Don't let a low score hide a catastrophic but unlikely risk; some deserve a plan anyway.

Don't

  • Scales without definitions, so “high” means different things to different people.
  • Treating the score as precise; it's a ranking aid.

Step by step

  1. Agree the scales For likelihood and impact, define 1 to 5 with concrete examples: “impact 5 = more than a month late or over €100k”.
  2. Score each risk With the people who know the area. Score the risk as it is now, before new responses.
  3. Place them on the grid Likelihood on one axis, impact on the other. Write the risk ID in the cell.
  4. Agree the zones For example: score 15 or more needs a response now, 8 to 14 needs an owner and watching, below 8 can be accepted.
  5. Plan responses for the top ones Then re-score after responses to see the expected effect.
  6. Re-score regularly At each risk review, move risks as things change.
Also called: Risk matrix, heat map, qualitative risk analysisPrint the blank template ↗

Worked example

The situation. An event company plans an outdoor festival.

  1. Heavy rain: likelihood 3, impact 4 → 12.
  2. Headliner cancels: likelihood 2, impact 5 → 10.
  3. Ticket system fails: likelihood 2, impact 3 → 6.

The result. Effort went to weather and the headliner, not to the ticket system, which had a cheap paper back-up.

Risk scoring sheet Print blank
RiskLike­lihood 1–5Impact 1–5ScoreResponse
Heavy rain3412Marquees, drainage, weather trigger
Headliner cancels2510Back-up act on standby
Ticket system fails236Accept; paper back-up

Filled in for: An event company plans an outdoor festival.

RiskLike­lihood 1–5Impact 1–5ScoreResponse

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

40 risks, all called “high”, drop to 8 in the red zone once the team agrees that impact 5 means “opening delayed over a month or cost over €150k”.

Questions people ask

Should opportunities go on the same grid?

Yes, many teams use a mirrored grid or mark them separately, so positive risks get attention too.