Office relocation51 questions5 phases
Northgate: a Project Manager case study
An insurance company's lease ends in nine months. 400 staff, two call centres and a server room must move to a new office across the city, with no break in customer service. Half the staff would rather work from home. You run the project.
What this case study tests
Staff consultationDependencies and phonesConflicts of interestHypercare
You're the Project Manager. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.
Stakeholders
Alexis (Project Manager)You
Atlas (Chief Operating Officer)Sponsor
Alba (Head of Customer Service)Senior user: the call centres
Ansel (Fit-out Contractor Manager)Builds the new office
Arianna (IT Infrastructure Lead)Network, phones and servers
Abdul (HR Business Partner)Staff, consultation and the unions
Alma (Staff Representative)Speaks for employees
Anton (Procurement Manager)Contracts and suppliers
Northgate
Starting up
A lease that ends in nine months
Question 1 of 51
Choose 1Atlas (Chief Operating Officer)
Find a building like this one and move everyone.
What do you clarify first?
Learn it on Day 1: A request lands on your deskQuestion 2 of 51
Choose 2Atlas (Chief Operating Officer)
Options: a new office of the same size, a smaller hybrid office, extend the lease, or go fully remote.
Which two statements are true?
Learn it on Day 3: Is it worth it?Question 3 of 51
True or falseAtlas (Chief Operating Officer)
We chose a smaller hybrid office. €2.8M, and I keep €200,000 aside.
True or false: the €200,000 is for scope the users ask for later.
Learn it on Day 4: The decisionQuestion 4 of 51
Choose 1Atlas (Chief Operating Officer)
You can decide changes up to €30,000.
Question 5 of 51
Choose 1Alma (Staff Representative)
Staff heard about fewer desks from the canteen gossip.
Question 6 of 51
Choose 1Abdul (HR Business Partner)
Changing working arrangements needs formal consultation with staff representatives.
How do you treat this?
Learn it on Day 6: Everyone who mattersQuestion 7 of 51
Choose 1Arianna (IT Infrastructure Lead)
Who decides where the server room goes: me or the fit-out contractor?
Question 8 of 51
Choose 1Alba (Head of Customer Service)
At the kick-off, my team leads argued about who moves first.
Question 9 of 51
Choose 1Atlas (Chief Operating Officer)
Is the new building even suitable? Lifts, power for servers, parking, accessibility?
Question 10 of 51
Choose 1Atlas (Chief Operating Officer)
Buying the new office costs more upfront than leasing, but saves rent for 20 years.
How do you compare the options?
Learn it on Day 3: Is it worth it?Question 11 of 51
Choose 1Atlas (Chief Operating Officer)
The company's portfolio office asks how this move fits with the IT upgrade planned for the same year.
What do you do?
Learn it on Day 7: Who does whatNorthgate
Planning
Desks, phones and a weekend move
Question 12 of 51
Choose 1Alba (Head of Customer Service)
Teams want nap pods, a gym and a rooftop bar.
Question 13 of 51
Choose 1Arianna (IT Infrastructure Lead)
Phone lines must be tested two weeks before the call centres move.
Question 14 of 51
Choose 1Ansel (Fit-out Contractor Manager)
Fit-out: 10 to 18 weeks, most likely 12.
What's the weighted estimate?
Learn it on Day 12: How long will it really take?Question 15 of 51
Choose 1Anton (Procurement Manager)
We'll pay the furniture, fit-out and movers in different months.
What does finance need?
Learn it on Day 14: What will it cost?Question 16 of 51
Choose 1Arianna (IT Infrastructure Lead)
Risk: the server move fails and systems are down on Monday.
Question 17 of 51
Choose 1Anton (Procurement Manager)
Should the movers be fixed price?
Question 18 of 51
Choose 1Anton (Procurement Manager)
One supplier gave a manager free event tickets during the tender.
Question 19 of 51
Choose 1Alba (Head of Customer Service)
How do we tell 400 people what happens and when?
What belongs in the communication plan?
Learn it on Day 19: Good enough, and who hears whatQuestion 20 of 51
Choose 1Atlas (Chief Operating Officer)
Can the move be a month earlier?
Question 21 of 51
Choose 1Alba (Head of Customer Service)
The phone routing for the call centres is new and complex.
How do you check it works before the move?
Learn it on Day 11: From needs to testsQuestion 22 of 51
Choose 1Abdul (HR Business Partner)
The building must meet accessibility law, fire rules and data protection for the CCTV.
How do you make sure nothing is missed?
Learn it on Day 13: Rules we must followQuestion 23 of 51
Choose 1Ansel (Fit-out Contractor Manager)
Fit-out, IT, furniture and the weekend move each have a plan, but the plans don't connect.
How do you find the gaps?
Learn it on Day 10: What exactly are we building?Northgate
Delivering
Building the new office
Question 24 of 51
Choose 1Ansel (Fit-out Contractor Manager)
Can we install ceiling cables before the fire officer's inspection?
What do you decide?
Learn it on Day 21: Breaking groundQuestion 25 of 51
Choose 1Abdul (HR Business Partner)
The new team leads are clashing about desk-booking rules.
Question 26 of 51
Choose 1Ansel (Fit-out Contractor Manager)
The floor wasn't level. We need €22,000 to fix it.
Question 27 of 51
Choose 1Arianna (IT Infrastructure Lead)
Network tests failed in 30 of 400 desk ports.
Question 28 of 51
Choose 1Arianna (IT Infrastructure Lead)
Why did the ports fail?
Question 29 of 51
Choose 1Alma (Staff Representative)
Staff fear losing their parking spaces.
Question 30 of 51
Choose 1Atlas (Chief Operating Officer)
Let's tell customers we're moving a week early.
Question 31 of 51
Choose 1Arianna (IT Infrastructure Lead)
My network engineer is leaving in three weeks.
Question 32 of 51
True or falseAlba (Head of Customer Service)
Why record lessons now?
True or false: lessons are captured during the project and applied straight away.
Learn it on Day 30: A key person leavesQuestion 33 of 51
Choose 1Ansel (Fit-out Contractor Manager)
A fitter fell from a ladder. He's in hospital.
Question 34 of 51
Choose 1Alma (Staff Representative)
Staff are unhappy about hot-desking. Some talk about leaving.
How do you help them through the change?
Learn it on Day 31: Getting people readyQuestion 35 of 51
Choose 1Alba (Head of Customer Service)
Call-centre staff fear the open-plan office: they need quiet for calls, and half would rather work from home.
How do you help?
Learn it on Day 31: Getting people readyNorthgate
Keeping control
Eight weeks to go
Question 36 of 51
Choose 1Atlas (Chief Operating Officer)
Planned value €1.4M, earned value €1.4M, actual cost €1.3M.
Question 37 of 51
Choose 1Alba (Head of Customer Service)
We want two more meeting rooms.
Question 38 of 51
Choose 1Anton (Procurement Manager)
Furniture delivery will be five weeks late. Tolerance is two.
Question 39 of 51
Choose 1Ansel (Fit-out Contractor Manager)
We added glass walls instead of the specified ones, same price.
What do you do?
Learn it on Day 36: Is it done?Question 40 of 51
Choose 1Alba (Head of Customer Service)
Can I sign off the call-centre floor?
Question 41 of 51
Choose 1Arianna (IT Infrastructure Lead)
A new risk: the telecom provider has a two-week backlog for line activation.
Question 42 of 51
Choose 2Atlas (Chief Operating Officer)
Before the move weekend, should the board decide anything?
Which two inputs does the stage decision need?
Learn it on Day 40: Ready for the last stage?Question 43 of 51
Choose 1Atlas (Chief Operating Officer)
I'm leaving the company. The CFO takes over as sponsor.
Question 44 of 51
Choose 1Ansel (Fit-out Contractor Manager)
The furniture delivery is two weeks late, and the move weekend can't change.
How do you handle it?
Learn it on Day 29: The supplier goes bustNorthgate
Closing
Monday morning in the new office
Question 45 of 51
Choose 1Arianna (IT Infrastructure Lead)
Shall we test a full call-centre shift in the new office before the move?
Question 46 of 51
Choose 1Atlas (Chief Operating Officer)
Do we move this weekend?
Question 47 of 51
Choose 1Alba (Head of Customer Service)
Monday: 40 people can't log in.
Question 48 of 51
Choose 1Anton (Procurement Manager)
The movers billed for an extra truck.
What do you do?
Learn it on Day 43: Closing the contractsQuestion 49 of 51
Choose 1Atlas (Chief Operating Officer)
Can we close the project?
What's needed?
Learn it on Day 44: Letting the team goQuestion 50 of 51
Choose 1Abdul (HR Business Partner)
People are moving back to their old teams. How do we release them well?
Question 51 of 51
Choose 1Alma (Staff Representative)
Six months later, desks are full on Tuesdays and empty on Fridays.