Office relocation51 questions5 phases

Northgate: a Project Manager case study

An insurance company's lease ends in nine months. 400 staff, two call centres and a server room must move to a new office across the city, with no break in customer service. Half the staff would rather work from home. You run the project.

What this case study tests
Staff consultationDependencies and phonesConflicts of interestHypercare

You're the Project Manager. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Stakeholders
Alexis (Project Manager)You
Atlas (Chief Operating Officer)Sponsor
Alba (Head of Customer Service)Senior user: the call centres
Ansel (Fit-out Contractor Manager)Builds the new office
Arianna (IT Infrastructure Lead)Network, phones and servers
Abdul (HR Business Partner)Staff, consultation and the unions
Alma (Staff Representative)Speaks for employees
Anton (Procurement Manager)Contracts and suppliers
Northgate

Starting up

A lease that ends in nine months

Question 1 of 51

Choose 1
Atlas (Chief Operating Officer)
Find a building like this one and move everyone.

What do you clarify first?

Learn it on Day 1: A request lands on your desk

Question 2 of 51

Choose 2
Atlas (Chief Operating Officer)
Options: a new office of the same size, a smaller hybrid office, extend the lease, or go fully remote.

Which two statements are true?

Learn it on Day 3: Is it worth it?

Question 3 of 51

True or false
Atlas (Chief Operating Officer)
We chose a smaller hybrid office. €2.8M, and I keep €200,000 aside.

True or false: the €200,000 is for scope the users ask for later.

Learn it on Day 4: The decision

Question 4 of 51

Choose 1
Atlas (Chief Operating Officer)
You can decide changes up to €30,000.

Where is that recorded?

Learn it on Day 5: Who's in charge here?

Technique: Management by exception

Question 5 of 51

Choose 1
Alma (Staff Representative)
Staff heard about fewer desks from the canteen gossip.

What do you do?

Learn it on Day 6: Everyone who matters

Technique: Active listening

Question 6 of 51

Choose 1
Abdul (HR Business Partner)
Changing working arrangements needs formal consultation with staff representatives.

How do you treat this?

Learn it on Day 6: Everyone who matters

Technique: Stakeholder engagement assessment

Question 7 of 51

Choose 1
Arianna (IT Infrastructure Lead)
Who decides where the server room goes: me or the fit-out contractor?

What clarifies it?

Learn it on Day 7: Who does what

Technique: RACI

Question 8 of 51

Choose 1
Alba (Head of Customer Service)
At the kick-off, my team leads argued about who moves first.

How do you handle it?

Learn it on Day 9: The kick-off

Technique: Conflict styles

Question 9 of 51

Choose 1
Atlas (Chief Operating Officer)
Is the new building even suitable? Lifts, power for servers, parking, accessibility?

What do you do first?

Learn it on Day 2: Not the only proposal

Technique: SWOT analysis

Question 10 of 51

Choose 1
Atlas (Chief Operating Officer)
Buying the new office costs more upfront than leasing, but saves rent for 20 years.

How do you compare the options?

Learn it on Day 3: Is it worth it?

Question 11 of 51

Choose 1
Atlas (Chief Operating Officer)
The company's portfolio office asks how this move fits with the IT upgrade planned for the same year.

What do you do?

Learn it on Day 7: Who does what
Northgate

Planning

Desks, phones and a weekend move

Question 12 of 51

Choose 1
Alba (Head of Customer Service)
Teams want nap pods, a gym and a rooftop bar.

How do you decide?

Learn it on Day 10: What exactly are we building?

Technique: MoSCoW

Question 13 of 51

Choose 1
Arianna (IT Infrastructure Lead)
Phone lines must be tested two weeks before the call centres move.

What is this?

Learn it on Day 12: How long will it really take?

Technique: Critical path

Question 14 of 51

Choose 1
Ansel (Fit-out Contractor Manager)
Fit-out: 10 to 18 weeks, most likely 12.

What's the weighted estimate?

Learn it on Day 12: How long will it really take?

Technique: Three-point estimating

Question 15 of 51

Choose 1
Anton (Procurement Manager)
We'll pay the furniture, fit-out and movers in different months.

What does finance need?

Learn it on Day 14: What will it cost?

Question 16 of 51

Choose 1
Arianna (IT Infrastructure Lead)
Risk: the server move fails and systems are down on Monday.

Which response fits?

Learn it on Day 16: What could go wrong?

Technique: Risk responses

Question 17 of 51

Choose 1
Anton (Procurement Manager)
Should the movers be fixed price?

What helps make that fair?

Learn it on Day 18: Buying what we need

Technique: Contract types

Question 18 of 51

Choose 1
Anton (Procurement Manager)
One supplier gave a manager free event tickets during the tender.

What should happen?

Learn it on Day 18: Buying what we need

Technique: Tender evaluation

Question 19 of 51

Choose 1
Alba (Head of Customer Service)
How do we tell 400 people what happens and when?

What belongs in the communication plan?

Learn it on Day 19: Good enough, and who hears what

Technique: Stakeholder communication plan

Question 20 of 51

Choose 1
Atlas (Chief Operating Officer)
Can the move be a month earlier?

What do you do?

Learn it on Day 20: Signing off the plan

Technique: Schedule compression

Question 21 of 51

Choose 1
Alba (Head of Customer Service)
The phone routing for the call centres is new and complex.

How do you check it works before the move?

Learn it on Day 11: From needs to tests

Technique: Requirements traceability

Question 22 of 51

Choose 1
Abdul (HR Business Partner)
The building must meet accessibility law, fire rules and data protection for the CCTV.

How do you make sure nothing is missed?

Learn it on Day 13: Rules we must follow

Question 23 of 51

Choose 1
Ansel (Fit-out Contractor Manager)
Fit-out, IT, furniture and the weekend move each have a plan, but the plans don't connect.

How do you find the gaps?

Learn it on Day 10: What exactly are we building?
Northgate

Delivering

Building the new office

Question 24 of 51

Choose 1
Ansel (Fit-out Contractor Manager)
Can we install ceiling cables before the fire officer's inspection?

What do you decide?

Learn it on Day 21: Breaking ground

Question 25 of 51

Choose 1
Abdul (HR Business Partner)
The new team leads are clashing about desk-booking rules.

How do you see it?

Learn it on Day 23: Building the team

Technique: Team stages (forming to performing)

Question 26 of 51

Choose 1
Ansel (Fit-out Contractor Manager)
The floor wasn't level. We need €22,000 to fix it.

What do you do?

Learn it on Day 25: When a supplier slips

Technique: Negotiation

Question 27 of 51

Choose 1
Arianna (IT Infrastructure Lead)
Network tests failed in 30 of 400 desk ports.

What happens?

Learn it on Day 26: Quality on site

Technique: Inspection and testing

Question 28 of 51

Choose 1
Arianna (IT Infrastructure Lead)
Why did the ports fail?

How do you find out?

Learn it on Day 26: Quality on site

Technique: 5 Whys

Question 29 of 51

Choose 1
Alma (Staff Representative)
Staff fear losing their parking spaces.

How do you respond?

Learn it on Day 28: The neighbours are angry

Technique: Negotiation

Question 30 of 51

Choose 1
Atlas (Chief Operating Officer)
Let's tell customers we're moving a week early.

How do you respond?

Learn it on Day 28: The neighbours are angry

Technique: Saying no with reasons

Question 31 of 51

Choose 1
Arianna (IT Infrastructure Lead)
My network engineer is leaving in three weeks.

What do you do?

Learn it on Day 30: A key person leaves

Technique: Knowledge transfer

Question 32 of 51

True or false
Alba (Head of Customer Service)
Why record lessons now?

True or false: lessons are captured during the project and applied straight away.

Learn it on Day 30: A key person leaves

Question 33 of 51

Choose 1
Ansel (Fit-out Contractor Manager)
A fitter fell from a ladder. He's in hospital.

What happens first?

Learn it on Day 27: The accident

Technique: Blameless review

Question 34 of 51

Choose 1
Alma (Staff Representative)
Staff are unhappy about hot-desking. Some talk about leaving.

How do you help them through the change?

Learn it on Day 31: Getting people ready

Technique: The change curve

Question 35 of 51

Choose 1
Alba (Head of Customer Service)
Call-centre staff fear the open-plan office: they need quiet for calls, and half would rather work from home.

How do you help?

Learn it on Day 31: Getting people ready
Northgate

Keeping control

Eight weeks to go

Question 36 of 51

Choose 1
Atlas (Chief Operating Officer)
Planned value €1.4M, earned value €1.4M, actual cost €1.3M.

What does this show?

Learn it on Day 32: Are we on track?

Technique: Earned value

Question 37 of 51

Choose 1
Alba (Head of Customer Service)
We want two more meeting rooms.

What happens?

Learn it on Day 33: The change request

Technique: Impact analysis

Question 38 of 51

Choose 1
Anton (Procurement Manager)
Furniture delivery will be five weeks late. Tolerance is two.

What do you do?

Learn it on Day 34: Out of tolerance

Technique: Management by exception

Question 39 of 51

Choose 1
Ansel (Fit-out Contractor Manager)
We added glass walls instead of the specified ones, same price.

What do you do?

Learn it on Day 36: Is it done?

Question 40 of 51

Choose 1
Alba (Head of Customer Service)
Can I sign off the call-centre floor?

How?

Learn it on Day 36: Is it done?

Technique: Acceptance criteria and Given/When/Then

Question 41 of 51

Choose 1
Arianna (IT Infrastructure Lead)
A new risk: the telecom provider has a two-week backlog for line activation.

What do you do?

Learn it on Day 38: The risk review

Technique: Risk responses

Question 42 of 51

Choose 2
Atlas (Chief Operating Officer)
Before the move weekend, should the board decide anything?

Which two inputs does the stage decision need?

Learn it on Day 40: Ready for the last stage?

Technique: Stage gate

Question 43 of 51

Choose 1
Atlas (Chief Operating Officer)
I'm leaving the company. The CFO takes over as sponsor.

What do you do?

Learn it on Day 39: A new sponsor

Technique: Knowledge transfer

Question 44 of 51

Choose 1
Ansel (Fit-out Contractor Manager)
The furniture delivery is two weeks late, and the move weekend can't change.

How do you handle it?

Learn it on Day 29: The supplier goes bust
Northgate

Closing

Monday morning in the new office

Question 45 of 51

Choose 1
Arianna (IT Infrastructure Lead)
Shall we test a full call-centre shift in the new office before the move?

Why?

Learn it on Day 41: Are we ready to open?

Technique: Dress rehearsal

Question 46 of 51

Choose 1
Atlas (Chief Operating Officer)
Do we move this weekend?

How do you decide?

Learn it on Day 41: Are we ready to open?

Technique: Go or no-go review

Question 47 of 51

Choose 1
Alba (Head of Customer Service)
Monday: 40 people can't log in.

Who fixes it?

Learn it on Day 42: Opening day

Technique: Hypercare

Question 48 of 51

Choose 1
Anton (Procurement Manager)
The movers billed for an extra truck.

What do you do?

Learn it on Day 43: Closing the contracts

Question 49 of 51

Choose 1
Atlas (Chief Operating Officer)
Can we close the project?

What's needed?

Learn it on Day 44: Letting the team go

Question 50 of 51

Choose 1
Abdul (HR Business Partner)
People are moving back to their old teams. How do we release them well?

What do you do?

Learn it on Day 44: Letting the team go

Technique: Recognition

Question 51 of 51

Choose 1
Alma (Staff Representative)
Six months later, desks are full on Tuesdays and empty on Fridays.

How is this used?

Learn it on Day 46: Was it worth it?

Technique: Benefits tracking