Procurement · cheat sheet Tender evaluation Choosing a supplier fairly by scoring every bid against published criteria, with conflicts of interest declared.
Common practice 6 steps Used by Project Manager
What it is Choosing a supplier fairly by scoring every bid against criteria and weights published in advance, with conflicts of interest declared.
When to use it After bids arrive, before a contract is signed.
Why it works It leads to the best value, protects against favouritism, and can be defended if a losing bidder complains.
Do Never change the criteria after seeing the bids. Don't Changing criteria after seeing the bids. Undeclared relationships with bidders. Step by step Publish criteria and weights With the request for bids: for example price 40%, experience 20%, method 25%, timeline 15%.
Declare conflicts of interest Anyone with a link to a bidder steps out.
Score independently Each panel member first, then agree together.
Check value, not just price The lowest price may be the highest risk.
Record scores and reasons And the decision.
Debrief unsuccessful bidders Honestly and briefly.
What the letters mean
IT Information technology Worked example The situation. Three bids for building works.
Bid A cheapest but weak on method. Bid B slightly more expensive, strongest overall. Panel member related to Bid C stepped out. The result. Bid B won and delivered on time.
Criterion (weight) Bid A Bid B Bid C Price (40) 40 34 30 Experience (20) 12 18 16 Method (25) 10 22 18 Timeline (15) 12 13 10 Total 74 87 74
Filled in for: Three bids for building works.
Criterion Weight Bid 1 Bid 2 Bid 3 Notes
Copy this structure, or print the blank version and fill it in by hand.
Before you use it: check these Check If it fails Criteria and weights published before bids arrive Changing them afterwards is unfair and may be unlawful: re-run the tender Each scorer declares conflicts of interest Replace the scorer before scoring Scores agreed with written reasons Discuss differences until each score can be explained
How to do it with real data The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Worked example with real dataScoring the building bids
From Day 18: Buying what we need of the Project Manager story
Three bids scored 1 to 5 against the published criteria and weights (out of 100).
Step by step Bid A 4 × 40 + 3 × 30 + 3 × 20 + 4 × 10 = 350 Bid B 3 × 40 + 5 × 30 + 4 × 20 + 4 × 10 = 390 Bid C 5 × 40 + 2 × 30 + 2 × 20 + 3 × 10 = 330
Criterion (weight) Bid A Bid B Bid C Price (40) 4 3 5 Quality of approach (30) 3 5 2 Experience (20) 3 4 2 Programme (10) 4 4 3 Weighted total 350 390 330
How to read the result Bid B wins on quality and experience even though Bid C is cheapest. The published weights make the choice defensible.
What it led to Bid B is recommended; the scores and the conflict-of-interest declaration are filed.
Do it in a spreadsheet Weighted total =SUMPRODUCT(B2:B5,{40;30;20;10})
Try it yourself: If price were weighted 60 and quality 10, which bid would win? A: 240 + 30 + 60 + 40 = 370; B: 180 + 50 + 80 + 40 = 350; C: 300 + 20 + 40 + 30 = 390. Bid C: weights decide outcomes, so publish them first.
In the roles How a Project Manager uses itAine (IT Lead) declares that her cousin owns one bidding company and leaves the panel. The building bids are scored on price, experience, method and timeline as published.
Questions people ask Must the cheapest bid win? Not if the criteria value quality and risk too, as published.