Procurement · cheat sheet

Tender evaluation

Choosing a supplier fairly by scoring every bid against published criteria, with conflicts of interest declared.

Common practice
6 steps
Used by Project Manager

What it is

Choosing a supplier fairly by scoring every bid against criteria and weights published in advance, with conflicts of interest declared.

When to use it

After bids arrive, before a contract is signed.

Why it works

It leads to the best value, protects against favouritism, and can be defended if a losing bidder complains.

Do

  • Never change the criteria after seeing the bids.

Don't

  • Changing criteria after seeing the bids.
  • Undeclared relationships with bidders.

Step by step

  1. Publish criteria and weights With the request for bids: for example price 40%, experience 20%, method 25%, timeline 15%.
  2. Declare conflicts of interest Anyone with a link to a bidder steps out.
  3. Score independently Each panel member first, then agree together.
  4. Check value, not just price The lowest price may be the highest risk.
  5. Record scores and reasons And the decision.
  6. Debrief unsuccessful bidders Honestly and briefly.
Also called: Bid evaluation, weighted scoring, source selectionPrint the blank template ↗

Worked example

The situation. Three bids for building works.

  1. Bid A cheapest but weak on method.
  2. Bid B slightly more expensive, strongest overall.
  3. Panel member related to Bid C stepped out.

The result. Bid B won and delivered on time.

Bid scoring sheet Print blank
Crite­rion (weight)Bid ABid BBid C
Price (40)403430
Experience (20)121816
Method (25)102218
Timeline (15)121310
Total748774

Filled in for: Three bids for building works.

Crite­rionWeightBid 1Bid 2Bid 3Notes

Copy this structure, or print the blank version and fill it in by hand.

Before you use it: check these

CheckIf it fails
Criteria and weights published before bids arriveChanging them afterwards is unfair and may be unlawful: re-run the tender
Each scorer declares conflicts of interestReplace the scorer before scoring
Scores agreed with written reasonsDiscuss differences until each score can be explained

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

Scoring the building bids

From Day 18: Buying what we need of the Project Manager story

Three bids scored 1 to 5 against the published criteria and weights (out of 100).

Step by step

  1. Bid A4 × 40 + 3 × 30 + 3 × 20 + 4 × 10= 350
  2. Bid B3 × 40 + 5 × 30 + 4 × 20 + 4 × 10= 390
  3. Bid C5 × 40 + 2 × 30 + 2 × 20 + 3 × 10= 330
Criterion (weight)Bid ABid BBid C
Price (40)435
Quality of approach (30)352
Experience (20)342
Programme (10)443
Weighted total350390330

How to read the result

Bid B wins on quality and experience even though Bid C is cheapest. The published weights make the choice defensible.

What it led to

Bid B is recommended; the scores and the conflict-of-interest declaration are filed.

Do it in a spreadsheet

Weighted total=SUMPRODUCT(B2:B5,{40;30;20;10})
Try it yourself: If price were weighted 60 and quality 10, which bid would win?

A: 240 + 30 + 60 + 40 = 370; B: 180 + 50 + 80 + 40 = 350; C: 300 + 20 + 40 + 30 = 390. Bid C: weights decide outcomes, so publish them first.

In the roles

How a Project Manager uses it

Aine (IT Lead) declares that her cousin owns one bidding company and leaves the panel. The building bids are scored on price, experience, method and timeline as published.

Questions people ask

Must the cheapest bid win?

Not if the criteria value quality and risk too, as published.