River flood defence 51 questions 5 phases
Floodwall: a Project Manager case study Millbrook flooded twice in three years. 600 homes and the high street were under water. The environment agency and the council want flood defences before the next winter storms. Rivers don't wait, wildlife is protected, and every resident has an opinion. You run the project.
What this case study tests
Legal constraints Resistant stakeholders Root causes Exceptions
You're the Project Manager. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Stakeholders
Aurora (Project Manager) You Archibald (Area Flood Manager) Sponsor Anjali (Hydraulic Engineer) Designs the defences Arlo (Ecologist) Protected otters and fish Aziz (Contractor Project Manager) Builds the walls Adele (Flood Action Group Chair) Residents who were flooded Alistair (Landowner) Owns the fields upstream Amaya (Project Accountant) Grants and spending Floodwall
Starting up After the second flood
Question 1 of 51 Choose 1
Archibald (Area Flood Manager) We need a two-metre wall along the whole river. Start designing.
What do you do first? Write the need first: protect 600 homes from floods Correct. Right. Then compare options against that need.Design the wall exactly as the agency has asked for it Incorrect. A wall is one solution. Upstream storage or raised properties might protect more homes for less.Wait for the next flood to see how bad it gets Incorrect. The need is already clear.
Learn it on Day 1: A request lands on your desk
Check answer
Question 2 of 51 Choose 2
Amaya (Project Accountant) Options: walls, upstream flood storage, a mix, or property-level protection.
Which two statements about comparing them are true? Leave out environmental impact: it's hard to price Incorrect. It's a key criterion here and can be described if not priced.Include doing nothing, as the baseline option Correct. Correct.Pick whichever option is cheapest to build Incorrect. Whole-life cost and benefits matter.Compare all on the same criteria, upkeep too Correct. Correct.
Learn it on Day 3: Is it worth it?
Check answer
Question 3 of 51 Choose 1
Amaya (Project Accountant) The mixed option costs €8M and avoids about €2M of flood damage a year.
How should benefits be stated? “A much safer town for every single resident” Incorrect. Not measurable.Only in money saved each year, since that's measurable Incorrect. Describe benefits you can't price too, like reduced stress.With a baseline and target: homes flooded, 600 to 0 Correct. Right.
Learn it on Day 3: Is it worth it?
Check answer
Question 4 of 51 True or false
Archibald (Area Flood Manager) The board approved €8M. €600,000 stays with me for surprises.
True or false: the project manager should plan to spend the €600,000. True Incorrect. Planning to spend the reserve leaves nothing for real surprises.False Correct. Correct. Plan within €8M; the reserve needs the sponsor's agreement.
Learn it on Day 4: The decision
Check answer
Question 5 of 51 Choose 1
Archibald (Area Flood Manager) You may approve changes up to €50,000 and two weeks.
What is this called? Tolerances: inside them you decide alone Correct. Right. Written in the charter.A budget for the project manager to spend Incorrect. The budget is the total; tolerances are the limits of your authority.A risk allowance written into the plan Incorrect. It's an authority limit, not an uncertain event.
Learn it on Day 5: Who's in charge here? Technique: Management by exception
Check answer
Question 6 of 51 Choose 1
Alistair (Landowner) You want to flood my fields to protect the town? Nobody asked me.
How do you see Alistair? A troublemaker the project should simply ignore Incorrect. Without his land, upstream storage fails.High influence, now resistant: start with a meeting Correct. Right. Compare current and needed engagement, then act.Someone to pressure firmly through the council, if needed Incorrect. Pressure hardens resistance.
Learn it on Day 6: Everyone who matters Technique: Stakeholder engagement assessment
Check answer
Question 7 of 51 Choose 1
Arlo (Ecologist) Otters breed here from March to June. No river work then.
What is this? A suggestion the plan can ignore if needed Incorrect. Protected species rules are law.An issue that has already happened to the project Incorrect. It isn't a problem yet; it's a known constraint and a risk.A constraint the plan must respect, and a risk Correct. Right. Record it and build the plan around it.
Learn it on Day 5: Who's in charge here? Technique: Risk identification
Check answer
Question 8 of 51 Choose 1
Archibald (Area Flood Manager) Do we need a kick-off with residents too?
What's the best approach? A team kick-off, plus a separate public meeting Correct. Right. Different audiences need different meetings.One big meeting for the team and residents together Incorrect. Too many purposes; nobody gets what they need.No meetings: just a website with all the updates Incorrect. Flooded residents deserve to be heard in person.
Learn it on Day 9: The kick-off Technique: Kick-off meeting
Check answer
Question 9 of 51 Choose 1
Amaya (Project Accountant) A higher wall costs €1.2M more but protects against a once-in-200-years flood instead of once in 100.
How do you judge whether it's worth it? Always build the highest wall that the money allows for Incorrect. Protection beyond what's worth paying for takes money from other needs.Compare the extra cost with the discounted damage it avoids Correct. Right. Compare the extra cost with the expected flood damage avoided each year, discounted over the wall's life: if the net present value is positive, it's worth it.Always build the cheapest wall that still meets the rules Incorrect. It may fail in a flood that more protection would have stopped.
Learn it on Day 3: Is it worth it?
Check answer
Question 10 of 51 Choose 1
Archibald (Area Flood Manager) The environment agency and the council both fund the scheme, and both want the final say on changes.
How do you set up governance? Whoever pays more decides on every change Incorrect. Both funders must be able to trust the decisions.Decide yourself, to keep things moving Incorrect. Changes beyond your tolerance aren't yours to approve.A joint project board with both funders Correct. Right. A joint project board with agreed tolerances and decision rights, reporting into the agency's flood programme: shared funding needs shared decisions.
Learn it on Day 7: Who does what
Check answer
Question 11 of 51 Choose 1
Anjali (Hydraulic Engineer) Nobody knows who is responsible for checking river levels during the works. Everyone assumed someone else was.
What fixes this? Agree a RACI chart, with one accountable person Correct. Right. A RACI chart shows, for river monitoring, who's accountable, who does it, who is consulted and informed; one accountable person stops tasks falling between teams.Ask everyone to keep an eye on the river levels Incorrect. Shared responsibility often means nobody's responsibility.Assume the contractor does it, as it's their site Incorrect. An assumption isn't an agreement.
Learn it on Day 7: Who does what
Check answer
Floodwall
Planning Working with the river
Question 12 of 51 Choose 1
Adele (Flood Action Group Chair) Residents also want new pavements and street lights along the wall.
How do you handle this? Add everything that the residents have asked for Incorrect. Scope creep.Test against the objective; record what's out Correct. Right.Ignore residents: the agency decides the scope here Incorrect. They're the people the project is for.
Learn it on Day 10: What exactly are we building? Technique: MoSCoW
Check answer
Question 13 of 51 Choose 1
Anjali (Hydraulic Engineer) Building the walls: best 16 weeks, likely 20, worst 34.
Question 14 of 51 Choose 1
Arlo (Ecologist) River work must stop by 1 March for otters.
Question 15 of 51 Choose 1
Amaya (Project Accountant) Grants arrive in three payments tied to milestones.
What does finance need from you? Just the total cost for the whole project Incorrect. Timing matters with milestone-based grants.A monthly spending profile and grant milestones Correct. Right. Cash must be there when invoices arrive.Nothing until the end, when costs are known Incorrect. Too late.
Learn it on Day 14: What will it cost?
Check answer
Question 16 of 51 Choose 1
Anjali (Hydraulic Engineer) Risk: a flood during construction washes away the works.
Which response fits? Accept it: floods during the works are rare Incorrect. Too large to accept.Avoid it by not building at any point in the year Incorrect. That defeats the purpose.Reduce it: build in sections, with barriers ready Correct. Right. Combine reducing and transferring.
Learn it on Day 16: What could go wrong? Technique: Risk responses
Check answer
Question 17 of 51 Choose 1
Amaya (Project Accountant) A biodiversity fund might pay for wetland planting.
How do you treat this? As an opportunity, with an owner and deadline Correct. Right.Ignore it until the grant is actually confirmed Incorrect. Unmanaged opportunities slip away.Spend it now, before it's even confirmed Incorrect. Not until it's confirmed.
Learn it on Day 16: What could go wrong?
Check answer
Question 18 of 51 Choose 1
Aziz (Contractor Project Manager) Should the walls be fixed price?
When does a fixed-price contract fit? Always, for every single kind of work Incorrect. On unclear work, suppliers price in huge buffers.When the scope is clear, like the walls Correct. Right.Never, as flood work always ends up changing Incorrect. It's the right choice for well-defined work.
Learn it on Day 18: Buying what we need Technique: Contract types
Check answer
Question 19 of 51 Choose 1
Adele (Flood Action Group Chair) How will residents know what's happening each month?
Question 20 of 51 True or false
Archibald (Area Flood Manager) Once approved, can the plan change?
True or false: baselines change only through approved change requests. True Correct. Correct. Forecasts move; baselines only through change control.False Incorrect. Then progress can't be measured against anything stable.
Learn it on Day 20: Signing off the plan
Check answer
Question 21 of 51 Choose 1
Archibald (Area Flood Manager) Two other towns also need flood defences. The agency can fund one this year.
Question 22 of 51 Choose 1
Anjali (Hydraulic Engineer) The flood gates' control software could be built in short cycles with the operators.
What approach fits? Everything agile, in short iterations, walls too Incorrect. Concrete walls can't be built in cycles.Hybrid: walls planned, software built with operators Correct. Right. A hybrid suits the walls predictively and the control software iteratively, in short cycles with the operators who'll use it.No feedback from operators: it slows things down Incorrect. They'll be the ones using it at 3 a.m.
Learn it on Day 8: How should we run it? Technique: Tailoring the approach
Check answer
Question 23 of 51 Choose 1
Archibald (Area Flood Manager) How much risk are we willing to take?
What do you agree? Avoid all risk, whatever it costs us Incorrect. Impossible and very expensive.Let each engineer decide for their own part Incorrect. Inconsistent decisions follow.A risk appetite per area, lowest for safety Correct. Right. It guides every later risk decision.
Learn it on Day 17: Putting numbers on risk
Check answer
Question 24 of 51 Choose 1
Aziz (Contractor Project Manager) Walls, wetlands, pumps, footpaths: every meeting adds something new, and nobody can say what is in scope.
How do you control the scope? Keep a running list of every request people make Incorrect. A list hides gaps and overlaps.Build a WBS, and treat anything new as a change Correct. Right. A work breakdown structure of all deliverables and work packages, agreed with the board, defines the scope; anything outside it needs a decision.Add whatever people ask for, to keep peace Incorrect. That's scope creep, and it breaks budget and dates.
Learn it on Day 10: What exactly are we building?
Check answer
Floodwall
Delivering Walls, wetlands and weather
Question 25 of 51 Choose 1
Aziz (Contractor Project Manager) The river is high. Can my team work from the bank without the safety boat?
What do you decide? No: safety rules stay; wait for the boat Correct. Right. Safety is never traded for speed.Yes, as long as they're careful near the edge Incorrect. High water is exactly when the boat is needed.Let the workers decide what's safe on the day Incorrect. Safety rules are set by the project and the law.
Learn it on Day 21: Breaking ground
Check answer
Question 26 of 51 Choose 1
Aziz (Contractor Project Manager) My team doesn't know when the ecologist needs to check each section.
How do you fix this? Tell the ecologist to visit the site every single day Incorrect. That wastes effort and doesn't make dependencies visible.A weekly look-ahead with ecology checks planned Correct. Right.Skip the ecology checks, to keep the work moving Incorrect. Illegal and harmful.
Learn it on Day 21: Breaking ground Technique: Dependency board
Check answer
Question 27 of 51 Choose 1
Aziz (Contractor Project Manager) We hit an old sewer pipe not on any map. Extra €70,000.
What do you do? Approve the extra cost yourself, quickly, to keep going Incorrect. Beyond your tolerance.Tell the contractor to fix it for free, as their risk Incorrect. Truly unforeseen ground is usually the client's risk.Check the contract, ask for evidence, and route it Correct. Right. It's beyond your €50,000 limit, so it goes up.
Learn it on Day 25: When a supplier slips Technique: Negotiation
Check answer
Question 28 of 51 Choose 1
Anjali (Hydraulic Engineer) Concrete samples from one section failed strength tests.
Question 29 of 51 Choose 1
Anjali (Hydraulic Engineer) Why did the concrete fail?
Which technique finds the root cause? Blame the concrete supplier, and move on quickly Incorrect. Find the cause before blaming.A fishbone diagram of all the possible causes Correct. Right. Cold weather pours without covers were the cause.Do nothing, as it's been fixed now anyway Incorrect. It may happen again.
Learn it on Day 26: Quality on site Technique: Fishbone diagram
Check answer
Question 30 of 51 Choose 1
Adele (Flood Action Group Chair) Residents say lorries are damaging the narrow lanes.
Question 31 of 51 Choose 1
Alistair (Landowner) I'll sign the land agreement, but only if the council fixes my farm road.
How do you handle this? Explore his interests; use change control Correct. Right. Interests, options, fair criteria.Agree on the spot, to secure the land quickly Incorrect. You may not have the authority or budget.Refuse outright: it's just blackmail, really Incorrect. It's a negotiation. Understand what he needs.
Learn it on Day 28: The neighbours are angry Technique: Negotiation
Check answer
Question 32 of 51 Choose 1
Anjali (Hydraulic Engineer) I'm moving to another region next month.
Question 33 of 51 True or false
Adele (Flood Action Group Chair) Why not just record lessons at the end?
True or false: lessons should be captured during the project. True Correct. Correct. Use them while the project is still running.False Incorrect. By the end, details are forgotten and it's too late to help.
Learn it on Day 30: A key person leaves
Check answer
Question 34 of 51 Choose 1
Aziz (Contractor Project Manager) A digger tipped over near the river. The driver is shaken but unhurt.
What happens? Nobody was hurt, so there's nothing to do Incorrect. Near misses are free lessons.Discipline the driver for the mistake, firmly Incorrect. Find the cause first.Make it safe, record a near miss, investigate Correct. Right. The bank was undermined by rain; a ground check before each move is added.
Learn it on Day 27: The accident Technique: 5 Whys
Check answer
Question 35 of 51 Choose 1
Adele (Flood Action Group Chair) The engineers want to work from the town office, the contractor from the site, and the agency is in another city.
Question 36 of 51 Choose 1
Adele (Flood Action Group Chair) After two floods, residents distrust the agency. Many refuse to sign up for the new flood warnings.
How do you lead this? Send every household a letter about the warnings Incorrect. Letters won't rebuild trust.Make sign-up compulsory for every home in the town Incorrect. Forcing people creates resistance.Lead through the flood action group, in person Correct. Right. Lead with the community: respect the town's culture and history, explain the plan in person, and help people adopt the warnings with demonstrations.
Learn it on Day 31: Getting people ready
Check answer
Floodwall
Keeping control The race against winter
Question 37 of 51 Choose 1
Amaya (Project Accountant) Planned value €4M, earned value €3.6M, actual cost €3.5M.
What does this show? Ahead of schedule, and over budget as well Incorrect. Check the ratios: EV ÷ PV and EV ÷ AC.Behind (SPI 0.9), slightly under cost (CPI 1.03) Correct. Right.Exactly on plan, for both the time and the cost Incorrect. EV is below PV.
Learn it on Day 32: Are we on track? Technique: Earned value
Check answer
Question 38 of 51 Choose 1
Archibald (Area Flood Manager) Make the status green; the board is nervous.
What do you do? Make it green, to keep the funders calm for now Incorrect. Hiding problems removes the board's chance to help.Stop the reports until it's back on track Incorrect. Not an option.Report the colour the rules give, with a plan Correct. Right. Honest status helps nervous boards most.
Learn it on Day 32: Are we on track? Technique: RAG status
Check answer
Question 39 of 51 Choose 1
Adele (Flood Action Group Chair) Residents want a glass panel in the wall so they can see the river.
Question 40 of 51 Choose 1
Aziz (Contractor Project Manager) Bad weather means river work will finish three weeks late, into the otter season.
Question 41 of 51 Choose 1
Aziz (Contractor Project Manager) We added decorative stone facing to the wall, at no charge.
What do you do? Accept it with thanks: free stone is a bonus Incorrect. Free extras can cause hidden problems.Demand its removal at once, without checking it Incorrect. Check first.Thank him, check it against the requirements Correct. Right. Gold-plating is still a change.
Learn it on Day 36: Is it done?
Check answer
Question 42 of 51 Choose 1
Amaya (Project Accountant) How much contingency is left?
What is reserve analysis? Weighing the contingency left against open risks Correct. Right. Is what's left enough?Adding more money to it every single month Incorrect. Only when analysis shows it's needed.Spending whatever is left before the end Incorrect. Unused contingency goes back.
Learn it on Day 38: The risk review Technique: Reserve analysis
Check answer
Question 43 of 51 Choose 1
Archibald (Area Flood Manager) The walls are done. Do we go ahead with the wetland stage?
What does the board use to decide? Momentum: it's too far along to stop now Incorrect. Momentum isn't a decision criterion.The end-stage report and updated business case Correct. Right. Go, go with conditions, or stop.The contractor's own opinion on the progress Incorrect. The board decides on evidence.
Learn it on Day 40: Ready for the last stage? Technique: Stage gate
Check answer
Question 44 of 51 Choose 2
Archibald (Area Flood Manager) Which two things belong in the end-stage report?
Choose two. A list of people to blame Incorrect. Not useful.Lessons learned in this stage Correct. Correct.Next year's holiday plans Incorrect. Irrelevant.Results against the baselines Correct. Correct.
Learn it on Day 40: Ready for the last stage?
Check answer
Question 45 of 51 Choose 1
Archibald (Area Flood Manager) I'm moving to another region. Your new sponsor wasn't part of any decision.
What do you prepare? A sponsor briefing on status, decisions and risks Correct. Right.Nothing: the project is nearly finished anyway Incorrect. Late decisions need an informed sponsor.The full project file, to read at leisure later Incorrect. Too much. Brief what matters.
Learn it on Day 39: A new sponsor Technique: Knowledge transfer
Check answer
Floodwall
Closing Before the winter storms
Question 46 of 51 Choose 1
Anjali (Hydraulic Engineer) Should we test the flood gates before handing over?
Why rehearse? It's not needed: the pumps and gates are brand new Incorrect. New equipment fails too.A test with operations finds problems cheaply Correct. Right. One gate jammed; fixed before winter.Wait for a real flood to test it properly Incorrect. Too late.
Learn it on Day 41: Are we ready to open? Technique: Dress rehearsal
Check answer
Question 47 of 51 Choose 1
Archibald (Area Flood Manager) Who closes the gates at 3 a.m. in a storm?
What does handover include? A thank-you letter to the operations team Incorrect. Ownership must be clear before the storm.The project team stays on indefinitely to run it Incorrect. Operations owns it after a support period.Manuals, trained staff, on-call rota, warranties Correct. Right.
Learn it on Day 42: Opening day
Check answer
Question 48 of 51 Choose 1
Aziz (Contractor Project Manager) Our final account includes €30,000 for weather delays.
How do you respond? Check the weather clause; pay what's due Correct. Right.Pay it all, to keep good relations with Aziz Incorrect. Check first.Refuse all of it: weather is their risk Incorrect. If the contract allows it, it's owed.
Learn it on Day 43: Closing the contracts
Check answer
Question 49 of 51 Choose 1
Archibald (Area Flood Manager) Can we close the project now?
What does the closure report include? Only the final cost of the whole scheme Incorrect. Too little.Results against objectives, and open items Correct. Right. The board formally closes it.Nothing: just stop the work and leave the site Incorrect. Closure is a decision.
Learn it on Day 44: Letting the team go
Check answer
Question 50 of 51 Choose 1
Adele (Flood Action Group Chair) We had a big storm. The river rose, but no homes flooded.
How is this used? Celebrate, then move on to the next job Incorrect. Evidence of benefits justifies the investment.Claim that all future floods are now prevented Incorrect. Report what the evidence shows.Recorded against the baseline, with evidence Correct. Right.
Learn it on Day 46: Was it worth it? Technique: Benefits tracking
Check answer
Question 51 of 51 Choose 1
Alistair (Landowner) Now the fields flood on purpose. Some farmers want compensation schemes for other rivers.
What happens? It's a new request, needing its own business case Correct. Right.Add it to this project while crews are here Incorrect. This project is closed.Ignore it: the project is already closed Incorrect. Good ideas deserve a proper hearing.
Learn it on Day 46: Was it worth it?
Check answer