River flood defence51 questions5 phases

Floodwall: a Project Manager case study

Millbrook flooded twice in three years. 600 homes and the high street were under water. The environment agency and the council want flood defences before the next winter storms. Rivers don't wait, wildlife is protected, and every resident has an opinion. You run the project.

What this case study tests
Legal constraintsResistant stakeholdersRoot causesExceptions

You're the Project Manager. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Stakeholders
Aurora (Project Manager)You
Archibald (Area Flood Manager)Sponsor
Anjali (Hydraulic Engineer)Designs the defences
Arlo (Ecologist)Protected otters and fish
Aziz (Contractor Project Manager)Builds the walls
Adele (Flood Action Group Chair)Residents who were flooded
Alistair (Landowner)Owns the fields upstream
Amaya (Project Accountant)Grants and spending
Floodwall

Starting up

After the second flood

Question 1 of 51

Choose 1
Archibald (Area Flood Manager)
We need a two-metre wall along the whole river. Start designing.

What do you do first?

Learn it on Day 1: A request lands on your desk

Question 2 of 51

Choose 2
Amaya (Project Accountant)
Options: walls, upstream flood storage, a mix, or property-level protection.

Which two statements about comparing them are true?

Learn it on Day 3: Is it worth it?

Question 3 of 51

Choose 1
Amaya (Project Accountant)
The mixed option costs €8M and avoids about €2M of flood damage a year.

How should benefits be stated?

Learn it on Day 3: Is it worth it?

Question 4 of 51

True or false
Archibald (Area Flood Manager)
The board approved €8M. €600,000 stays with me for surprises.

True or false: the project manager should plan to spend the €600,000.

Learn it on Day 4: The decision

Question 5 of 51

Choose 1
Archibald (Area Flood Manager)
You may approve changes up to €50,000 and two weeks.

What is this called?

Learn it on Day 5: Who's in charge here?

Technique: Management by exception

Question 6 of 51

Choose 1
Alistair (Landowner)
You want to flood my fields to protect the town? Nobody asked me.

How do you see Alistair?

Learn it on Day 6: Everyone who matters

Technique: Stakeholder engagement assessment

Question 7 of 51

Choose 1
Arlo (Ecologist)
Otters breed here from March to June. No river work then.

What is this?

Learn it on Day 5: Who's in charge here?

Technique: Risk identification

Question 8 of 51

Choose 1
Archibald (Area Flood Manager)
Do we need a kick-off with residents too?

What's the best approach?

Learn it on Day 9: The kick-off

Technique: Kick-off meeting

Question 9 of 51

Choose 1
Amaya (Project Accountant)
A higher wall costs €1.2M more but protects against a once-in-200-years flood instead of once in 100.

How do you judge whether it's worth it?

Learn it on Day 3: Is it worth it?

Question 10 of 51

Choose 1
Archibald (Area Flood Manager)
The environment agency and the council both fund the scheme, and both want the final say on changes.

How do you set up governance?

Learn it on Day 7: Who does what

Question 11 of 51

Choose 1
Anjali (Hydraulic Engineer)
Nobody knows who is responsible for checking river levels during the works. Everyone assumed someone else was.

What fixes this?

Learn it on Day 7: Who does what
Floodwall

Planning

Working with the river

Question 12 of 51

Choose 1
Adele (Flood Action Group Chair)
Residents also want new pavements and street lights along the wall.

How do you handle this?

Learn it on Day 10: What exactly are we building?

Technique: MoSCoW

Question 13 of 51

Choose 1
Anjali (Hydraulic Engineer)
Building the walls: best 16 weeks, likely 20, worst 34.

What does the spread tell you?

Learn it on Day 12: How long will it really take?

Technique: Three-point estimating

Question 14 of 51

Choose 1
Arlo (Ecologist)
River work must stop by 1 March for otters.

How does this shape the schedule?

Learn it on Day 12: How long will it really take?

Technique: Critical path

Question 15 of 51

Choose 1
Amaya (Project Accountant)
Grants arrive in three payments tied to milestones.

What does finance need from you?

Learn it on Day 14: What will it cost?

Question 16 of 51

Choose 1
Anjali (Hydraulic Engineer)
Risk: a flood during construction washes away the works.

Which response fits?

Learn it on Day 16: What could go wrong?

Technique: Risk responses

Question 17 of 51

Choose 1
Amaya (Project Accountant)
A biodiversity fund might pay for wetland planting.

How do you treat this?

Learn it on Day 16: What could go wrong?

Question 18 of 51

Choose 1
Aziz (Contractor Project Manager)
Should the walls be fixed price?

When does a fixed-price contract fit?

Learn it on Day 18: Buying what we need

Technique: Contract types

Question 19 of 51

Choose 1
Adele (Flood Action Group Chair)
How will residents know what's happening each month?

What goes in the communication plan?

Learn it on Day 19: Good enough, and who hears what

Technique: Stakeholder communication plan

Question 20 of 51

True or false
Archibald (Area Flood Manager)
Once approved, can the plan change?

True or false: baselines change only through approved change requests.

Learn it on Day 20: Signing off the plan

Question 21 of 51

Choose 1
Archibald (Area Flood Manager)
Two other towns also need flood defences. The agency can fund one this year.

How should it decide?

Learn it on Day 2: Not the only proposal

Technique: WSJF and cost of delay

Question 22 of 51

Choose 1
Anjali (Hydraulic Engineer)
The flood gates' control software could be built in short cycles with the operators.

What approach fits?

Learn it on Day 8: How should we run it?

Technique: Tailoring the approach

Question 23 of 51

Choose 1
Archibald (Area Flood Manager)
How much risk are we willing to take?

What do you agree?

Learn it on Day 17: Putting numbers on risk

Question 24 of 51

Choose 1
Aziz (Contractor Project Manager)
Walls, wetlands, pumps, footpaths: every meeting adds something new, and nobody can say what is in scope.

How do you control the scope?

Learn it on Day 10: What exactly are we building?
Floodwall

Delivering

Walls, wetlands and weather

Question 25 of 51

Choose 1
Aziz (Contractor Project Manager)
The river is high. Can my team work from the bank without the safety boat?

What do you decide?

Learn it on Day 21: Breaking ground

Question 26 of 51

Choose 1
Aziz (Contractor Project Manager)
My team doesn't know when the ecologist needs to check each section.

How do you fix this?

Learn it on Day 21: Breaking ground

Technique: Dependency board

Question 27 of 51

Choose 1
Aziz (Contractor Project Manager)
We hit an old sewer pipe not on any map. Extra €70,000.

What do you do?

Learn it on Day 25: When a supplier slips

Technique: Negotiation

Question 28 of 51

Choose 1
Anjali (Hydraulic Engineer)
Concrete samples from one section failed strength tests.

What happens?

Learn it on Day 26: Quality on site

Technique: Inspection and testing

Question 29 of 51

Choose 1
Anjali (Hydraulic Engineer)
Why did the concrete fail?

Which technique finds the root cause?

Learn it on Day 26: Quality on site

Technique: Fishbone diagram

Question 30 of 51

Choose 1
Adele (Flood Action Group Chair)
Residents say lorries are damaging the narrow lanes.

What do you do?

Learn it on Day 28: The neighbours are angry

Technique: Negotiation

Question 31 of 51

Choose 1
Alistair (Landowner)
I'll sign the land agreement, but only if the council fixes my farm road.

How do you handle this?

Learn it on Day 28: The neighbours are angry

Technique: Negotiation

Question 32 of 51

Choose 1
Anjali (Hydraulic Engineer)
I'm moving to another region next month.

What do you do?

Learn it on Day 30: A key person leaves

Technique: Knowledge transfer

Question 33 of 51

True or false
Adele (Flood Action Group Chair)
Why not just record lessons at the end?

True or false: lessons should be captured during the project.

Learn it on Day 30: A key person leaves

Question 34 of 51

Choose 1
Aziz (Contractor Project Manager)
A digger tipped over near the river. The driver is shaken but unhurt.

What happens?

Learn it on Day 27: The accident

Technique: 5 Whys

Question 35 of 51

Choose 1
Adele (Flood Action Group Chair)
The engineers want to work from the town office, the contractor from the site, and the agency is in another city.

How do you keep them working as one team?

Learn it on Day 22: Working with an agile supplier

Technique: Working agreements

Question 36 of 51

Choose 1
Adele (Flood Action Group Chair)
After two floods, residents distrust the agency. Many refuse to sign up for the new flood warnings.

How do you lead this?

Learn it on Day 31: Getting people ready
Floodwall

Keeping control

The race against winter

Question 37 of 51

Choose 1
Amaya (Project Accountant)
Planned value €4M, earned value €3.6M, actual cost €3.5M.

What does this show?

Learn it on Day 32: Are we on track?

Technique: Earned value

Question 38 of 51

Choose 1
Archibald (Area Flood Manager)
Make the status green; the board is nervous.

What do you do?

Learn it on Day 32: Are we on track?

Technique: RAG status

Question 39 of 51

Choose 1
Adele (Flood Action Group Chair)
Residents want a glass panel in the wall so they can see the river.

What happens first?

Learn it on Day 33: The change request

Technique: Impact analysis

Question 40 of 51

Choose 1
Aziz (Contractor Project Manager)
Bad weather means river work will finish three weeks late, into the otter season.

Your tolerance is two weeks. What do you do?

Learn it on Day 34: Out of tolerance

Technique: Management by exception

Question 41 of 51

Choose 1
Aziz (Contractor Project Manager)
We added decorative stone facing to the wall, at no charge.

What do you do?

Learn it on Day 36: Is it done?

Question 42 of 51

Choose 1
Amaya (Project Accountant)
How much contingency is left?

What is reserve analysis?

Learn it on Day 38: The risk review

Technique: Reserve analysis

Question 43 of 51

Choose 1
Archibald (Area Flood Manager)
The walls are done. Do we go ahead with the wetland stage?

What does the board use to decide?

Learn it on Day 40: Ready for the last stage?

Technique: Stage gate

Question 44 of 51

Choose 2
Archibald (Area Flood Manager)
Which two things belong in the end-stage report?

Choose two.

Learn it on Day 40: Ready for the last stage?

Question 45 of 51

Choose 1
Archibald (Area Flood Manager)
I'm moving to another region. Your new sponsor wasn't part of any decision.

What do you prepare?

Learn it on Day 39: A new sponsor

Technique: Knowledge transfer

Floodwall

Closing

Before the winter storms

Question 46 of 51

Choose 1
Anjali (Hydraulic Engineer)
Should we test the flood gates before handing over?

Why rehearse?

Learn it on Day 41: Are we ready to open?

Technique: Dress rehearsal

Question 47 of 51

Choose 1
Archibald (Area Flood Manager)
Who closes the gates at 3 a.m. in a storm?

What does handover include?

Learn it on Day 42: Opening day

Question 48 of 51

Choose 1
Aziz (Contractor Project Manager)
Our final account includes €30,000 for weather delays.

How do you respond?

Learn it on Day 43: Closing the contracts

Question 49 of 51

Choose 1
Archibald (Area Flood Manager)
Can we close the project now?

What does the closure report include?

Learn it on Day 44: Letting the team go

Question 50 of 51

Choose 1
Adele (Flood Action Group Chair)
We had a big storm. The river rose, but no homes flooded.

How is this used?

Learn it on Day 46: Was it worth it?

Technique: Benefits tracking

Question 51 of 51

Choose 1
Alistair (Landowner)
Now the fields flood on purpose. Some farmers want compensation schemes for other rivers.

What happens?

Learn it on Day 46: Was it worth it?