Prioritisation · cheat sheet

WSJF and cost of delay

Do first what loses the most value per week of waiting, divided by how long it takes.

Common practice
5 steps
Used by Product Owner, Project Manager

What it is

Weighted Shortest Job First: rank work by the cost of waiting divided by its size. Things that lose a lot of value by waiting, and are small, go first.

When to use it

When several big items compete and waiting has a real cost, for example a competitor or a deadline.

Why it works

It adds the cost of delay to prioritisation. A small, urgent item can be worth more now than a big valuable one later.

Do

  • Use relative numbers (like 1, 2, 3, 5, 8, 13), not money, unless you really know it.

Don't

  • Fake precision: the scores are rough relative guesses.
  • Using it for small items where a quick conversation is faster.

Step by step

  1. Estimate the cost of delay Often as the sum of three relative scores: value to users, time criticality, and risk reduction or opportunity.
  2. Estimate the size Relative size or duration.
  3. Divide WSJF = cost of delay ÷ size.
  4. Rank by the result Highest first.
  5. Re-score regularly Time criticality changes, especially near deadlines.
Also called: Weighted Shortest Job First, CD3Print the blank template ↗

Worked example

The situation. Three items compete for the next month.

  1. Regulatory report: cost of delay 20, size 5 → 4.
  2. New dashboard: 15, size 10 → 1.5.
  3. Payment fix: 18, size 3 → 6.

The result. The payment fix and the report went first; the dashboard waited without much lost value.

WSJF scoring Print blank
ItemCost of delaySizeWSJF
Payment fix1836
Regulatory report2054
New dashboard15101.5

Filled in for: Three items compete for the next month.

ItemUser valueTime criti­calityRisk / oppor­tunityCost of delay (sum)SizeWSJF

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Product Owner uses it

On Day 16, 40% of users leave without a delivery time. Delivery slots have a high cost of delay and a medium size; ratings have a low cost of delay. Slots go first.

How a Project Manager uses it

The portfolio office ranks proposals by cost of delay divided by size; the clinic's urgency (rising waiting times) puts it first.

Questions people ask

Is this only for large organisations?

No. The idea of cost of delay divided by size works anywhere.