Unity: a Project Manager case study

Two logistics companies have merged. 3,000 people are paid by two payroll systems, with two holiday policies and two ways of doing almost everything. The new board wants one way of working within a year, and nobody's pay can go wrong. You run the project.

What this case study tests
Union consultationAccountabilityParallel pay runsChange with people

You're the Project Manager. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Stakeholders
Adrienne (Project Manager)You
Arturo (Chief People Officer)Sponsor
Aisling (Payroll Manager (company A))Pays 1,800 people
Akim (Payroll Manager (company B))Pays 1,200 people
Anouska (Union Representative)Speaks for employees
Auden (HR Systems Lead)The new HR system
Annabel (Legal Counsel)Employment law
Aldo (Communications Manager)Messages to 3,000 people
Unity

Starting up

Two companies, one way of working

Question 1 of 54

Choose 1
Arturo (Chief People Officer)
Put everyone on company A's system and policies. Done.

What do you clarify first?

Learn it on Day 1: A request lands on your desk

Question 2 of 54

Choose 2
Arturo (Chief People Officer)
Options: A's system, B's system, a new system, or keep both.

Which two statements are true?

Learn it on Day 3: Is it worth it?

Question 3 of 54

True or false
Arturo (Chief People Officer)
€2.2M approved, €200,000 kept back.

True or false: the €200,000 is the sponsor's management reserve.

Learn it on Day 4: The decision

Question 4 of 54

Choose 1
Annabel (Legal Counsel)
Changing contracts needs consultation with the union, by law.

What does the charter need to reflect?

Learn it on Day 5: Who's in charge here?

Question 5 of 54

Choose 1
Anouska (Union Representative)
Staff in company B fear losing their extra holiday days.

How do you engage the union?

Learn it on Day 6: Everyone who matters

Technique: Active listening

Question 6 of 54

Choose 1
Aisling (Payroll Manager (company A))
Akim (Payroll Manager, company B) and I both think we own the new payroll process.

What settles it?

Learn it on Day 7: Who does what

Technique: RACI

Question 7 of 54

Choose 1
Arturo (Chief People Officer)
I want to be in every working session.

What do you propose?

Learn it on Day 7: Who does what

Technique: Management by exception

Question 8 of 54

Choose 1
Auden (HR Systems Lead)
At the kick-off: company B's employee data is in spreadsheets, not a system.

What happens to the assumption that data is in a system?

Learn it on Day 9: The kick-off

Technique: Risk identification

Question 9 of 54

Choose 1
Arturo (Chief People Officer)
Can we even merge the payrolls in a year, given the union agreements and two different systems?

What do you check?

Learn it on Day 2: Not the only proposal

Technique: PESTLE analysis

Question 10 of 54

Choose 1
Arturo (Chief People Officer)
One payroll system costs €1.5M now and saves €400,000 a year. The board asks whether it's worth it.

How do you justify it?

Learn it on Day 3: Is it worth it?

Question 11 of 54

Choose 1
Arturo (Chief People Officer)
The merger has several projects: IT, finance and HR. They all affect each other.

How do you coordinate them?

Learn it on Day 7: Who does what

Question 12 of 54

Choose 1
Arturo (Chief People Officer)
The board approved the merger. Why do we need a business case for payroll as well?

What do you answer?

Learn it on Day 3: Is it worth it?
Unity

Planning

One payroll, no mistakes

Question 13 of 54

Choose 1
Auden (HR Systems Lead)
Managers also want new performance reviews, learning portals and a staff app.

How do you handle it?

Learn it on Day 10: What exactly are we building?

Technique: MoSCoW

Question 14 of 54

Choose 1
Aisling (Payroll Manager (company A))
Pay runs on the 25th. We can't switch mid-month.

What does this mean for the schedule?

Learn it on Day 12: How long will it really take?

Technique: Critical path

Question 15 of 54

Choose 1
Auden (HR Systems Lead)
Configuring the payroll: best 8 weeks, likely 12, worst 22.

What does the spread show?

Learn it on Day 12: How long will it really take?

Technique: Three-point estimating

Question 16 of 54

Choose 1
Arturo (Chief People Officer)
Where's the money for problems we already know about?

Where does it sit?

Learn it on Day 14: What will it cost?

Question 17 of 54

Choose 1
Aisling (Payroll Manager (company A))
Risk: people paid wrongly in the first month.

Which response fits?

Learn it on Day 16: What could go wrong?

Technique: Risk responses

Question 18 of 54

Choose 1
Annabel (Legal Counsel)
Some of company B's terms can't legally be changed without agreement.

Is this a risk or an issue?

Learn it on Day 16: What could go wrong?

Question 19 of 54

Choose 1
Auden (HR Systems Lead)
Should the system vendor work fixed price?

What's sensible?

Learn it on Day 18: Buying what we need

Technique: Contract types

Question 20 of 54

Choose 1
Aldo (Communications Manager)
How do we tell 3,000 people what's changing?

What goes in the communication plan?

Learn it on Day 19: Good enough, and who hears what

Technique: Stakeholder communication plan

Question 21 of 54

Choose 1
Aisling (Payroll Manager (company A))
How do we know the new payroll is right?

What makes a good quality plan?

Learn it on Day 19: Good enough, and who hears what

Technique: Acceptance criteria and Given/When/Then

Question 22 of 54

Choose 1
Annabel (Legal Counsel)
Salary, bank details and health data will move between systems.

What do you do?

Learn it on Day 13: Rules we must follow

Question 23 of 54

Choose 1
Arturo (Chief People Officer)
How confident are we about the go-live month?

How do you answer?

Learn it on Day 17: Putting numbers on risk

Technique: Schedule simulation

Question 24 of 54

Choose 1
Auden (HR Systems Lead)
HR system setup, data cleaning, policy changes, training: the list keeps growing.

How do you organise the scope?

Learn it on Day 10: What exactly are we building?

Question 25 of 54

Choose 1
Aldo (Communications Manager)
The payroll switch date is fixed, but our messages to staff keep changing as we hear their concerns.

How do you plan?

Learn it on Day 8: How should we run it?
Unity

Delivering

Policies, data and people

Question 26 of 54

Choose 1
Akim (Payroll Manager (company B))
In company B we decide together in meetings. In company A managers decide and announce. Each side thinks the other is doing it wrong.

What do you do?

Learn it on Day 22: Working with an agile supplier

Question 27 of 54

Choose 1
Auden (HR Systems Lead)
Can we load real salary data into the test system without masking it?

What do you decide?

Learn it on Day 21: Breaking ground

Question 28 of 54

Choose 1
Aisling (Payroll Manager (company A))
The two payroll teams are working together for the first time and clashing.

How do you see it?

Learn it on Day 23: Building the team

Technique: Team stages (forming to performing)

Question 29 of 54

Choose 1
Auden (HR Systems Lead)
The vendor says the holiday calculation wasn't in scope.

What do you do first?

Learn it on Day 25: When a supplier slips

Technique: Negotiation

Question 30 of 54

Choose 1
Aisling (Payroll Manager (company A))
Parallel run 1: 340 differences.

How do you prioritise?

Learn it on Day 26: Quality on site

Technique: Pareto chart

Question 31 of 54

Choose 1
Akim (Payroll Manager (company B))
Why do overtime errors keep coming back?

How do you find the root cause?

Learn it on Day 26: Quality on site

Technique: 5 Whys

Question 32 of 54

Choose 1
Anouska (Union Representative)
Staff heard rumours that pay will drop.

What do you do?

Learn it on Day 28: The neighbours are angry

Technique: Stakeholder communication plan

Question 33 of 54

Choose 1
Anouska (Union Representative)
The union wants the extra holiday days kept for existing staff.

How do you approach it?

Learn it on Day 28: The neighbours are angry

Technique: Negotiation

Question 34 of 54

Choose 1
Akim (Payroll Manager (company B))
I'm retiring in two months. Only I know company B's payroll quirks.

What do you do?

Learn it on Day 30: A key person leaves

Technique: Knowledge transfer

Question 35 of 54

True or false
Aisling (Payroll Manager (company A))
Can't the vendor just add a small allowance type for us?

True or false: small changes can skip change control.

Learn it on Day 30: A key person leaves

Question 36 of 54

Choose 1
Akim (Payroll Manager (company B))
My payroll team feels they're losing everything they built.

How do you support them?

Learn it on Day 31: Getting people ready

Technique: The change curve

Question 37 of 54

Choose 1
Anouska (Union Representative)
Staff fear losing holidays and benefits. Rumours are spreading faster than facts.

How do you lead the change?

Learn it on Day 31: Getting people ready

Question 38 of 54

Choose 1
Aisling (Payroll Manager (company A))
Our HR trainers will visit 14 depots to explain the new payroll, walking between forklifts and loading bays they've never seen.

How do you keep them safe?

Learn it on Day 27: The accident
Unity

Keeping control

Three months to the switch

Question 39 of 54

Choose 1
Arturo (Chief People Officer)
Planned value €1.1M, earned value €0.99M, actual cost €1.0M.

What does this show?

Learn it on Day 32: Are we on track?

Technique: Earned value

Question 40 of 54

Choose 1
Auden (HR Systems Lead)
Let's keep payroll green; we'll catch up.

What do you report?

Learn it on Day 32: Are we on track?

Technique: RAG status

Question 41 of 54

Choose 1
Annabel (Legal Counsel)
A new law changes holiday pay calculations from next month.

What happens?

Learn it on Day 33: The change request

Technique: Impact analysis

Question 42 of 54

Choose 1
Aisling (Payroll Manager (company A))
Parallel run 2 still has 60 differences. The switch would slip by a full pay cycle.

It's beyond your tolerance. What do you do?

Learn it on Day 34: Out of tolerance

Technique: Management by exception

Question 43 of 54

Choose 1
Arturo (Chief People Officer)
Who's to blame for the delay?

How do you respond?

Learn it on Day 34: Out of tolerance

Technique: Blameless review

Question 44 of 54

Choose 1
Aisling (Payroll Manager (company A))
Can I accept payroll for company A?

How?

Learn it on Day 36: Is it done?

Technique: Acceptance criteria and Given/When/Then

Question 45 of 54

Choose 1
Auden (HR Systems Lead)
New risk: the bank needs four weeks to set up the new payment file.

What do you do?

Learn it on Day 38: The risk review

Technique: Risk responses

Question 46 of 54

Choose 1
Arturo (Chief People Officer)
The new board cuts the budget by 10%.

How do you decide what to cut?

Learn it on Day 35: The budget is cut

Technique: MoSCoW

Question 47 of 54

Choose 1
Arturo (Chief People Officer)
I'm moving to the group board. The new HR director will sponsor this.

What do you prepare?

Learn it on Day 39: A new sponsor

Technique: Knowledge transfer

Unity

Closing

The first payday on one system

Question 48 of 54

Choose 1
Arturo (Chief People Officer)
Do we switch everyone this month?

How do you decide?

Learn it on Day 41: Are we ready to open?

Technique: Go or no-go review

Question 49 of 54

Choose 1
Aisling (Payroll Manager (company A))
Payday: 12 people underpaid.

What happens?

Learn it on Day 42: Opening day

Technique: Hypercare

Question 50 of 54

Choose 1
Auden (HR Systems Lead)
Can we close the vendor contract?

What's needed?

Learn it on Day 43: Closing the contracts

Question 51 of 54

Choose 1
Aldo (Communications Manager)
Payroll staff from both companies are moving to new roles. How do we release the project team?

What do you do?

Learn it on Day 44: Letting the team go

Technique: Recognition

Question 52 of 54

Choose 1
Arturo (Chief People Officer)
Can we just tell everyone it's done?

What does formal closure include?

Learn it on Day 44: Letting the team go

Question 53 of 54

Choose 2
Arturo (Chief People Officer)
What do we tell the next merger project?

Which two lessons are most useful?

Learn it on Day 44: Letting the team go

Question 54 of 54

Choose 1
Anouska (Union Representative)
Six months later: pay queries are down 40%, but fewer than half of staff use the new self-service.

How do you report it?

Learn it on Day 46: Was it worth it?

Technique: Benefits tracking