Harbour footbridge49 questions5 phases

Harbourbridge: a Project Manager case study

The old footbridge across Porthaven harbour was closed after a safety inspection. Children now walk 25 minutes around the harbour to school, and the shops on the far side are losing trade. The town council wants a new bridge, fast. You've just been asked to run the project.

What this case study tests
Need vs solutionTides and the critical pathClaims and defectsBenefits after opening

You're the Project Manager. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Stakeholders
Alana (Project Manager)You
Augustus (Town Clerk)Sponsor, holds the budget
Ainsley (Structural Engineer)Designs the bridge
Ayesha (Finance Officer)The council's money
Arnav (Contractor Site Manager)Builds the bridge
Aoife (Harbour Master)Boats, tides and harbour safety
Alonzo (Residents' Association Chair)Speaks for local families and shops
Amara (Project Coordinator)Plans, logs and schedules
Harbourbridge

Starting up

A closed bridge and an impatient council

Question 1 of 49

Choose 1
Augustus (Town Clerk)
We need a new bridge exactly like the old one, by Christmas. Can you order it this week?

What do you do first?

Learn it on Day 1: A request lands on your desk

Question 2 of 49

Choose 1
Augustus (Town Clerk)
The objective is obvious: build a bridge.

Which objective is the most useful?

Learn it on Day 1: A request lands on your desk

Question 3 of 49

Choose 2
Ayesha (Finance Officer)
Here are the options: repair the old bridge, build a new bridge, run a ferry, or do nothing.

Which two statements about the options analysis are true?

Learn it on Day 3: Is it worth it?

Question 4 of 49

Choose 1
Ayesha (Finance Officer)
The new bridge costs €2.1M. Is that the number for the business case?

What else belongs in the cost-benefit analysis?

Learn it on Day 3: Is it worth it?

Question 5 of 49

True or false
Augustus (Town Clerk)
The council approved €2.1M, plus €200,000 I'll hold back for surprises.

True or false: the project manager can spend the €200,000 whenever a cost rises.

Learn it on Day 4: The decision

Question 6 of 49

Choose 1
Augustus (Town Clerk)
Let's skip the paperwork and just start.

What does the project charter give you?

Learn it on Day 5: Who's in charge here?

Question 7 of 49

Choose 1
Aoife (Harbour Master)
Nobody asked me. Cranes in the harbour will block the fishing boats at high tide.

What does this tell you?

Learn it on Day 6: Everyone who matters

Question 8 of 49

Choose 1
Amara (Project Coordinator)
Ainsley (Structural Engineer) and Arnav (Contractor Site Manager) both say they decide on the foundations.

Which technique settles this?

Learn it on Day 7: Who does what

Technique: RACI

Question 9 of 49

Choose 1
Ayesha (Finance Officer)
Option A, a steel bridge, is cheaper to build but needs repainting every 10 years and lasts 40. Option B, concrete, costs more now but needs little upkeep for 100 years.

How do you compare them fairly?

Learn it on Day 3: Is it worth it?

Question 10 of 49

Choose 1
Augustus (Town Clerk)
The council's portfolio office wants monthly reports, the harbour board wants a say, and three councillors phone you every week. Who actually decides?

How do you set up governance?

Learn it on Day 7: Who does what
Harbourbridge

Planning

From a crossing to a plan

Question 11 of 49

Choose 1
Alonzo (Residents' Association Chair)
Residents want lighting, benches, a viewing platform and a café on the bridge.

How do you handle the requests?

Learn it on Day 10: What exactly are we building?

Technique: MoSCoW

Question 12 of 49

True or false
Amara (Project Coordinator)
Should the scope statement list what we're NOT doing?

True or false: exclusions belong in the scope statement.

Learn it on Day 10: What exactly are we building?

Question 13 of 49

Choose 1
Ainsley (Structural Engineer)
Building the bridge: best case 10 weeks, most likely 14, worst case 24.

What is the three-point (weighted) estimate?

Learn it on Day 12: How long will it really take?

Technique: Three-point estimating

Question 14 of 49

Choose 1
Aoife (Harbour Master)
Crane lifts can only happen at low tide, on weekdays.

How do you find which activities decide the end date?

Learn it on Day 12: How long will it really take?

Technique: Critical path

Question 15 of 49

Choose 1
Ayesha (Finance Officer)
Estimates add up to €1.95M. Can we give €150,000 back?

What is the €150,000 for?

Learn it on Day 14: What will it cost?

Question 16 of 49

Choose 2
Amara (Project Coordinator)
We've got 30 risks. Where do we start?

Which two steps come first?

Learn it on Day 16: What could go wrong?

Technique: Probability-impact matrix

Question 17 of 49

Choose 1
Ainsley (Structural Engineer)
Steel prices could jump before we order.

Which response transfers this risk?

Learn it on Day 16: What could go wrong?

Technique: Risk responses

Question 18 of 49

Choose 1
Ayesha (Finance Officer)
One bidder is a company owned by Arnav (Contractor Site Manager)'s brother-in-law. Arnav sits on the evaluation panel.

What should happen?

Learn it on Day 18: Buying what we need

Technique: Tender evaluation

Question 19 of 49

Choose 1
Augustus (Town Clerk)
The mayor wants it open two weeks earlier, before the summer festival.

How do you respond?

Learn it on Day 20: Signing off the plan

Technique: Schedule compression

Question 20 of 49

Choose 1
Augustus (Town Clerk)
The council also wants a new skate park this year. Can we have both?

How should the council choose between proposals?

Learn it on Day 2: Not the only proposal

Technique: Value vs effort

Question 21 of 49

Choose 1
Ainsley (Structural Engineer)
Could the lighting and handrail design be done in short cycles with feedback from residents, while the structure follows a fixed plan?

What approach fits?

Learn it on Day 8: How should we run it?

Technique: Tailoring the approach

Harbourbridge

Delivering

Building over water

Question 22 of 49

Choose 1
Arnav (Contractor Site Manager)
We can start the deck before the foundation tests are signed off. Saves a week.

What do you decide?

Learn it on Day 21: Breaking ground

Question 23 of 49

Choose 1
Amara (Project Coordinator)
How do I hand the lighting work to the electricians so they know exactly what to do?

What goes in a work package?

Learn it on Day 21: Breaking ground

Technique: Work authorisation

Question 24 of 49

Choose 1
Aoife (Harbour Master)
A crane blocked the harbour entrance for an hour this morning. Nobody warned me.

How do you fix this?

Learn it on Day 21: Breaking ground

Technique: Dependency board

Question 25 of 49

Choose 1
Arnav (Contractor Site Manager)
The ground was softer than the survey said. We need €45,000 more for deeper piles.

How do you handle the claim?

Learn it on Day 25: When a supplier slips

Technique: Negotiation

Question 26 of 49

Choose 1
Ainsley (Structural Engineer)
Three handrail sections are 2 cm lower than the safety standard.

What do you do?

Learn it on Day 26: Quality on site

Technique: Inspection and testing

Question 27 of 49

Choose 1
Arnav (Contractor Site Manager)
It was just one welder's mistake.

How do you prevent it happening again?

Learn it on Day 26: Quality on site

Technique: 5 Whys

Question 28 of 49

Choose 1
Alonzo (Residents' Association Chair)
Rumours say the bridge will charge a toll. Parents are furious.

What do you do?

Learn it on Day 28: The neighbours are angry

Technique: Stakeholder communication plan

Question 29 of 49

Choose 1
Amara (Project Coordinator)
Ainsley (Structural Engineer) is leaving for another job in three weeks.

What do you do?

Learn it on Day 30: A key person leaves

Technique: Knowledge transfer

Question 30 of 49

True or false
Alonzo (Residents' Association Chair)
Can't Arnav (Contractor Site Manager) just add a bench on the bridge? He says it's easy.

True or false: small changes agreed directly with the contractor are fine.

Learn it on Day 30: A key person leaves

Question 31 of 49

Choose 1
Aoife (Harbour Master)
Planning approval, harbour rules, environmental permits for the river bed… who's tracking all of them?

What do you set up?

Learn it on Day 13: Rules we must follow

Question 32 of 49

Choose 1
Arnav (Contractor Site Manager)
A worker slipped on the wet deck and broke a wrist.

What comes first?

Learn it on Day 27: The accident

Technique: Blameless review

Question 33 of 49

Choose 1
Arnav (Contractor Site Manager)
My crew starts at 6 am and works loud. The harbour staff are used to quiet mornings and the fishermen are complaining. Tempers are rising.

How do you handle it?

Learn it on Day 31: Getting people ready
Harbourbridge

Keeping control

Measuring, changing and deciding

Question 34 of 49

Choose 2
Ayesha (Finance Officer)
Planned value is €1.2M, earned value €1.0M, actual cost €1.1M.

Which two statements are true?

Learn it on Day 32: Are we on track?

Technique: Earned value

Question 35 of 49

Choose 1
Amara (Project Coordinator)
The lighting is green on the dashboard, but the supplier hasn't delivered anything.

What do you do?

Learn it on Day 32: Are we on track?

Technique: RAG status

Question 36 of 49

Choose 1
Alonzo (Residents' Association Chair)
Residents now want the bridge 50 cm wider for mobility scooters.

What happens first?

Learn it on Day 33: The change request

Technique: Impact analysis

Question 37 of 49

Choose 1
Ayesha (Finance Officer)
Widening costs €60,000 and two weeks on the critical path. Your limit is €25,000.

Who decides?

Learn it on Day 33: The change request

Technique: Change board

Question 38 of 49

Choose 1
Ainsley (Structural Engineer)
The steel supplier will be four weeks late. Our time tolerance is two weeks.

What do you do?

Learn it on Day 34: Out of tolerance

Technique: Management by exception

Question 39 of 49

Choose 1
Augustus (Town Clerk)
Whose fault is the steel delay?

How do you run the discussion?

Learn it on Day 34: Out of tolerance

Technique: Blameless review

Question 40 of 49

True or false
Arnav (Contractor Site Manager)
We fitted stainless steel bins instead of the specified ones, free of charge.

True or false: free extras don't need to go through change control.

Learn it on Day 36: Is it done?

Question 41 of 49

Choose 1
Aoife (Harbour Master)
A new risk: the winter storm season starts in three weeks, and the final lift isn't booked.

What do you do?

Learn it on Day 38: The risk review

Technique: Risk responses

Question 42 of 49

Choose 1
Augustus (Town Clerk)
The council needs €150,000 back. The opening date can't move.

How do you decide what to cut?

Learn it on Day 35: The budget is cut

Technique: MoSCoW

Question 43 of 49

Choose 1
Augustus (Town Clerk)
I'm retiring next month. Alba from finance becomes sponsor.

What do you do?

Learn it on Day 39: A new sponsor

Technique: Knowledge transfer

Harbourbridge

Closing

Opening the bridge and closing the project

Question 44 of 49

Choose 1
Ainsley (Structural Engineer)
The bridge passed the load test. Can we open tomorrow?

How do you decide?

Learn it on Day 41: Are we ready to open?

Technique: Go or no-go review

Question 45 of 49

Choose 1
Augustus (Town Clerk)
After the opening, who looks after the bridge?

What does a good handover include?

Learn it on Day 42: Opening day

Question 46 of 49

Choose 1
Arnav (Contractor Site Manager)
Can you release our 5% retention now?

What do you do?

Learn it on Day 43: Closing the contracts

Question 47 of 49

Choose 2
Amara (Project Coordinator)
We have lessons from every stage. Is a final review still needed?

Which two statements are true?

Learn it on Day 44: Letting the team go

Technique: Timeline Retrospective

Question 48 of 49

Choose 1
Augustus (Town Clerk)
Can't you just email that the project is closed?

What does formal closure include?

Learn it on Day 44: Letting the team go

Question 49 of 49

Choose 1
Alonzo (Residents' Association Chair)
Six months on: the walk to school is 4 minutes, but harbour-side shop trade is only up 5%, not 15%.

How do you report this?

Learn it on Day 46: Was it worth it?

Technique: Benefits tracking