Harbour footbridge 49 questions 5 phases
Harbourbridge: a Project Manager case study The old footbridge across Porthaven harbour was closed after a safety inspection. Children now walk 25 minutes around the harbour to school, and the shops on the far side are losing trade. The town council wants a new bridge, fast. You've just been asked to run the project.
What this case study tests
Need vs solution Tides and the critical path Claims and defects Benefits after opening
You're the Project Manager. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Stakeholders
Alana (Project Manager) You Augustus (Town Clerk) Sponsor, holds the budget Ainsley (Structural Engineer) Designs the bridge Ayesha (Finance Officer) The council's money Arnav (Contractor Site Manager) Builds the bridge Aoife (Harbour Master) Boats, tides and harbour safety Alonzo (Residents' Association Chair) Speaks for local families and shops Amara (Project Coordinator) Plans, logs and schedules Harbourbridge
Starting up A closed bridge and an impatient council
Question 1 of 49 Choose 1
Augustus (Town Clerk) We need a new bridge exactly like the old one, by Christmas. Can you order it this week?
What do you do first? Clarify the real need, and check a project is justified Correct. Right. The need is a safe, short crossing for walkers and cyclists. A bridge is one way to meet it.Order a copy of the old bridge, to save design time Incorrect. A copy repeats whatever made the old one unsafe, and nobody has checked whether it's the best way to meet the need.Refuse to start until a full specification exists for it Incorrect. Nobody can write a full specification yet. You help shape the request into something a decision can be made about.
Learn it on Day 1: A request lands on your desk
Check answer
Question 2 of 49 Choose 1
Augustus (Town Clerk) The objective is obvious: build a bridge.
Which objective is the most useful? “Build a new footbridge across the harbour by Christmas.” Incorrect. That's a solution. It hides other options and says nothing about success.“People cross safely on foot or bike in under 5 minutes.” Correct. Right. A need-based objective lets you compare options and later measure success.“Make the harbour a better place for everyone who uses it.” Incorrect. Too vague to plan against or measure.
Learn it on Day 1: A request lands on your desk
Check answer
Question 3 of 49 Choose 2
Ayesha (Finance Officer) Here are the options: repair the old bridge, build a new bridge, run a ferry, or do nothing.
Which two statements about the options analysis are true? Each option is compared on the same criteria Correct. Correct. Different criteria per option make the comparison meaningless.The sponsor's favourite option is scored highest Incorrect. Choosing first and scoring later makes the analysis worthless.“Do nothing” is included and assessed honestly Correct. Correct. It's the baseline every other option is compared with.Running costs can be ignored for a footbridge Incorrect. Maintenance over 50 years can be larger than the build cost.
Learn it on Day 3: Is it worth it?
Check answer
Question 4 of 49 Choose 1
Ayesha (Finance Officer) The new bridge costs €2.1M. Is that the number for the business case?
What else belongs in the cost-benefit analysis? Lifetime maintenance, benefits, and sensitivity to costs Correct. Right. A sensitivity check shows whether the case still holds if steel prices rise 20%.Only the build cost: maintenance comes out of a different budget Incorrect. Leaving out whole-life costs misleads the decision-makers.Only the benefits, to make the case look more convincing Incorrect. One-sided cases lose trust the first time someone checks.
Learn it on Day 3: Is it worth it?
Check answer
Question 5 of 49 True or false
Augustus (Town Clerk) The council approved €2.1M, plus €200,000 I'll hold back for surprises.
True or false: the project manager can spend the €200,000 whenever a cost rises. True Incorrect. That reserve is held by the sponsor. Using it needs his agreement.False Correct. Correct. Who holds the reserve, and how it's released, is agreed at the start.
Learn it on Day 4: The decision
Check answer
Question 6 of 49 Choose 1
Augustus (Town Clerk) Let's skip the paperwork and just start.
What does the project charter give you? Nothing useful: it's bureaucracy before the real work Incorrect. Without it, nobody knows your authority, the limits or what's out of scope.An official start, scope, budget and your authority Correct. Right. Two pages, signed by the sponsor, prevent many later arguments.A detailed schedule of every task, week by week Incorrect. Detailed planning comes later; the charter authorises it.
Learn it on Day 5: Who's in charge here?
Check answer
Question 7 of 49 Choose 1
Aoife (Harbour Master) Nobody asked me. Cranes in the harbour will block the fishing boats at high tide.
What does this tell you? Aoife (Harbour Master) is just being difficult about it Incorrect. She has real influence: she can stop work in the harbour.Tell her the project is already approved by council Incorrect. Approval doesn't remove the harbour's rules or her authority.A key stakeholder was missed: add her and involve her Correct. Right. High influence, high interest: manage closely. Her tide tables become part of the schedule.
Learn it on Day 6: Everyone who matters
Check answer
Question 8 of 49 Choose 1
Amara (Project Coordinator) Ainsley (Structural Engineer) and Arnav (Contractor Site Manager) both say they decide on the foundations.
Which technique settles this? A RACI chart with one person accountable for each item Correct. Right. Ainsley is accountable for the design, Arnav responsible for building it as designed.Let whichever of them is louder decide it each time Incorrect. That creates resentment and doesn't prevent the next dispute.Decide it yourself every time the two of them disagree Incorrect. You'd become a bottleneck on technical decisions you're not qualified to make.
Learn it on Day 7: Who does what Technique: RACI
Check answer
Question 9 of 49 Choose 1
Ayesha (Finance Officer) Option A, a steel bridge, is cheaper to build but needs repainting every 10 years and lasts 40. Option B, concrete, costs more now but needs little upkeep for 100 years.
How do you compare them fairly? Compare whole-life costs in today's money for both Correct. Right. Discount each option's building, maintenance and replacement costs over the same period and compare the net present values: the bridge that is cheaper to build can be dearer to own.Choose the steel bridge, as it's cheaper to build Incorrect. Build cost alone ignores decades of maintenance.Choose the concrete bridge, as it lasts the longest Incorrect. Lifespan alone doesn't show which gives better value for money.
Learn it on Day 3: Is it worth it?
Check answer
Question 10 of 49 Choose 1
Augustus (Town Clerk) The council's portfolio office wants monthly reports, the harbour board wants a say, and three councillors phone you every week. Who actually decides?
How do you set up governance? Report to everyone and follow whoever spoke last Incorrect. Conflicting instructions stall the project.Form a small project board with clear decision rights Correct. Right. A project board with the sponsor, a user voice and the supplier decides; you report to the portfolio office in its format; everyone else is informed, not deciding.Decide everything yourself, to keep it simple and fast Incorrect. Decisions on money, scope and dates belong to the sponsor and the board.
Learn it on Day 7: Who does what
Check answer
Harbourbridge
Planning From a crossing to a plan
Question 11 of 49 Choose 1
Alonzo (Residents' Association Chair) Residents want lighting, benches, a viewing platform and a café on the bridge.
How do you handle the requests? Accept everything, to keep the residents happy and on side Incorrect. The budget was approved for a defined scope. Everything would cost far more.Test each against the objective and prioritise openly Correct. Right. Clear reasons make a “no” acceptable.Ignore residents: the council decides the scope Incorrect. They're the users. Listen, then decide openly.
Learn it on Day 10: What exactly are we building? Technique: MoSCoW
Check answer
Question 12 of 49 True or false
Amara (Project Coordinator) Should the scope statement list what we're NOT doing?
True or false: exclusions belong in the scope statement. True Correct. Correct. Writing down what's out prevents as many arguments as what's in.False Incorrect. Without exclusions, people assume their idea is included.
Learn it on Day 10: What exactly are we building?
Check answer
Question 13 of 49 Choose 1
Ainsley (Structural Engineer) Building the bridge: best case 10 weeks, most likely 14, worst case 24.
What is the three-point (weighted) estimate? 14 weeks, the most likely figure from Ainsley Incorrect. That ignores the risk of a much longer job.24 weeks, the worst case, just to be safe Incorrect. Planning every task on its worst case makes the plan unbelievable.About 15 weeks: (10 + 4 × 14 + 24) ÷ 6 Correct. Right. And the wide spread marks the bridge works as a schedule risk.
Learn it on Day 12: How long will it really take? Technique: Three-point estimating
Check answer
Question 14 of 49 Choose 1
Aoife (Harbour Master) Crane lifts can only happen at low tide, on weekdays.
How do you find which activities decide the end date? Link the activities by dependency; find the longest path Correct. Right. Foundations → steel delivery → crane lifts → deck → handrails → inspection. Lighting has slack.The most expensive activities decide when it ends Incorrect. Cost doesn't decide the end date; the chain of dependencies does.Every activity matters equally to the end date, so track all Incorrect. Then you can't focus your attention.
Learn it on Day 12: How long will it really take? Technique: Critical path
Check answer
Question 15 of 49 Choose 1
Ayesha (Finance Officer) Estimates add up to €1.95M. Can we give €150,000 back?
What is the €150,000 for? Return it to the council, as the project doesn't need it Incorrect. You already know of risks, like poor ground under the foundations.Contingency for known risks, inside the cost baseline Correct. Right. Known risks: contingency. Unknown: management reserve.Add a viewing platform to the bridge with the money Incorrect. That spends the safety margin on unapproved scope.
Learn it on Day 14: What will it cost?
Check answer
Question 16 of 49 Choose 2
Amara (Project Coordinator) We've got 30 risks. Where do we start?
Which two steps come first? Treat all 30 risks exactly the same way Incorrect. Equal effort on unequal risks wastes time.Score each risk and focus on the highest Correct. Correct. Detailed responses go to the few that matter most.Only record risks that the sponsor agrees with Incorrect. Hiding risks doesn't remove them.Agree likelihood and impact scales first Correct. Correct. Shared definitions turn opinions into a ranking.
Learn it on Day 16: What could go wrong? Technique: Probability-impact matrix
Check answer
Question 17 of 49 Choose 1
Ainsley (Structural Engineer) Steel prices could jump before we order.
Which response transfers this risk? A fixed-price contract for the steel, signed early Correct. Right. The supplier carries the price risk.Accepting it, and hoping that steel prices fall again Incorrect. That's acceptance, not transfer, and too passive for a big risk.Building a wooden bridge instead of a steel one Incorrect. That changes the plan to avoid the risk, but likely fails other requirements.
Learn it on Day 16: What could go wrong? Technique: Risk responses
Check answer
Question 18 of 49 Choose 1
Ayesha (Finance Officer) One bidder is a company owned by Arnav (Contractor Site Manager)'s brother-in-law. Arnav sits on the evaluation panel.
What should happen? Nothing: his family's business doesn't matter here Incorrect. Even the appearance of favouritism can invalidate a public tender.Arnav declares the link and leaves the evaluation panel Correct. Right. The process stays fair and defensible.Exclude that bidder quietly, without telling anyone why Incorrect. That's unfair too and can be challenged.
Learn it on Day 18: Buying what we need Technique: Tender evaluation
Check answer
Question 19 of 49 Choose 1
Augustus (Town Clerk) The mayor wants it open two weeks earlier, before the summer festival.
How do you respond? Promise it, and ask everyone to work harder to make it happen Incorrect. The critical path has no slack; the promise would likely break in public.Say it's impossible, and close the topic quickly and firmly Incorrect. It's possible at a price. Show the price.Show the options with costs and risks; the sponsor decides Correct. Right. You give the trade-offs; Augustus (Town Clerk) chooses.
Learn it on Day 20: Signing off the plan Technique: Schedule compression
Check answer
Question 20 of 49 Choose 1
Augustus (Town Clerk) The council also wants a new skate park this year. Can we have both?
How should the council choose between proposals? Score both on the same criteria, then decide openly Correct. Right. The bridge scores higher on safety and urgency; the skate park waits for next year's budget.Fund whichever proposal has the louder supporters behind it Incorrect. Volume isn't a criterion.Split the money evenly between the two of them, to be fair Incorrect. Two underfunded projects usually deliver less than one done properly.
Learn it on Day 2: Not the only proposal Technique: Value vs effort
Check answer
Question 21 of 49 Choose 1
Ainsley (Structural Engineer) Could the lighting and handrail design be done in short cycles with feedback from residents, while the structure follows a fixed plan?
What approach fits? Everything agile, in short Sprints, for flexibility Incorrect. You can't build a bridge structure a bit at a time.Hybrid: predictive structure, iterative finishes Correct. Right. Each part runs the way that fits it, under one plan and board.Everything predictive, with no resident feedback Incorrect. You'd lose cheap chances to improve the parts users notice most.
Learn it on Day 8: How should we run it? Technique: Tailoring the approach
Check answer
Harbourbridge
Delivering Building over water
Question 22 of 49 Choose 1
Arnav (Contractor Site Manager) We can start the deck before the foundation tests are signed off. Saves a week.
What do you decide? Yes: saving a week is worth it on any project Incorrect. Building on untested foundations risks safety and rework.Let Arnav decide: it's his site and his crew Incorrect. Structural safety sign-off is the engineer's, not the builder's.Not until the engineer signs off the tests Correct. Right. Safety and legal requirements are never traded for speed.
Learn it on Day 21: Breaking ground
Check answer
Question 23 of 49 Choose 1
Amara (Project Coordinator) How do I hand the lighting work to the electricians so they know exactly what to do?
What goes in a work package? What to deliver, acceptance, dates and reporting Correct. Right. Everyone knows what they own and when to escalate.Just the deadline for the work, nothing else Incorrect. Without acceptance criteria and limits, “done” will be argued about.The full project plan, so they can see everything Incorrect. Too much, and it doesn't say what they own.
Learn it on Day 21: Breaking ground Technique: Work authorisation
Check answer
Question 24 of 49 Choose 1
Aoife (Harbour Master) A crane blocked the harbour entrance for an hour this morning. Nobody warned me.
How do you fix this? Apologise to Aoife, and hope it doesn't happen again soon Incorrect. Nothing changes in how information flows.A weekly meeting with a three-week look-ahead of lifts Correct. Right. Dependencies become visible before they hurt.Ask Aoife to come to the site every day to check Incorrect. That puts the burden on her, not the process.
Learn it on Day 21: Breaking ground Technique: Dependency board
Check answer
Question 25 of 49 Choose 1
Arnav (Contractor Site Manager) The ground was softer than the survey said. We need €45,000 more for deeper piles.
How do you handle the claim? Pay it immediately, to avoid a long and costly dispute Incorrect. Check what the contract and survey say first.Refuse it outright, since the contract price is fixed Incorrect. Genuinely unforeseen conditions are usually the buyer's risk.Check the contract, ask for evidence, negotiate Correct. Right. The survey flagged “variable ground”; you agree €25,000 and no extra time.
Learn it on Day 25: When a supplier slips Technique: Negotiation
Check answer
Question 26 of 49 Choose 1
Ainsley (Structural Engineer) Three handrail sections are 2 cm lower than the safety standard.
What do you do? Record it; the contractor replaces them at their cost Correct. Right. Inspect against the requirement and fix before handover.Accept them: 2 cm is nothing on a bridge this long Incorrect. Safety standards for handrails exist to stop children falling.Pay another firm to fix the railings quickly, to save time Incorrect. The contractor is responsible under the contract.
Learn it on Day 26: Quality on site Technique: Inspection and testing
Check answer
Question 27 of 49 Choose 1
Arnav (Contractor Site Manager) It was just one welder's mistake.
How do you prevent it happening again? Have the welder removed from the site at once Incorrect. The next one would get the same old drawing.Ask “why?” until you reach a process to fix Correct. Right. Fix the process: a drawing revision log confirmed by every trade.Trust that it won't happen again now it's known Incorrect. Without knowing the cause, nothing has changed.
Learn it on Day 26: Quality on site Technique: 5 Whys
Check answer
Question 28 of 49 Choose 1
Alonzo (Residents' Association Chair) Rumours say the bridge will charge a toll. Parents are furious.
What do you do? Ignore it: rumours about tolls always die down by themselves Incorrect. Rumours grow when nobody answers.Correct people one by one, replying in the comments Incorrect. That spreads the rumour further.Answer quickly with facts through the agreed channels Correct. Right. The bridge is free. Alonzo (Residents' Association Chair) shares the statement.
Learn it on Day 28: The neighbours are angry Technique: Stakeholder communication plan
Check answer
Question 29 of 49 Choose 1
Amara (Project Coordinator) Ainsley (Structural Engineer) is leaving for another job in three weeks.
What do you do? Record it as an issue and plan a handover to a successor Correct. Right. Plan the handover while he's still here.Hope the design files are enough for whoever comes next Incorrect. Much of the knowledge is in his head.Ask him to stay on unpaid for a few weeks to finish Incorrect. Not fair, and not a plan.
Learn it on Day 30: A key person leaves Technique: Knowledge transfer
Check answer
Question 30 of 49 True or false
Alonzo (Residents' Association Chair) Can't Arnav (Contractor Site Manager) just add a bench on the bridge? He says it's easy.
True or false: small changes agreed directly with the contractor are fine. True Incorrect. Changes made directly bypass cost, safety and design checks.False Correct. Correct. All changes go through one agreed route, however small.
Learn it on Day 30: A key person leaves
Check answer
Question 31 of 49 Choose 1
Aoife (Harbour Master) Planning approval, harbour rules, environmental permits for the river bed… who's tracking all of them?
What do you set up? Each specialist tracks their own rules separately Incorrect. Obligations that cross specialists get missed.A compliance register with owners and due dates Correct. Right. The marine works licence is found missing and applied for in time.Check every rule at handover, all at once Incorrect. Too late to fix without delay.
Learn it on Day 13: Rules we must follow
Check answer
Question 32 of 49 Choose 1
Arnav (Contractor Site Manager) A worker slipped on the wet deck and broke a wrist.
What comes first? Finish today's concrete pour first, then deal with it Incorrect. People first, always.Find out straight away who's to blame for it Incorrect. Investigate causes, not people, and only after the area is safe.Care for the worker, stop work, and report it Correct. Right. Then a blameless investigation finds the missing anti-slip boards.
Learn it on Day 27: The accident Technique: Blameless review
Check answer
Question 33 of 49 Choose 1
Arnav (Contractor Site Manager) My crew starts at 6 am and works loud. The harbour staff are used to quiet mornings and the fishermen are complaining. Tempers are rising.
How do you handle it? Let them sort it out between themselves on site Incorrect. Small clashes grow into stoppages and complaints.Side with the contractor: the bridge comes first Incorrect. The harbour must keep working; ignoring it creates new problems.Bring both sides together and agree shared site rules Correct. Right. Explaining each other's working culture and agreeing rules such as noise windows helps the harbour team adopt the new routines; most clashes come from unspoken expectations.
Learn it on Day 31: Getting people ready
Check answer
Harbourbridge
Keeping control Measuring, changing and deciding
Question 34 of 49 Choose 2
Ayesha (Finance Officer) Planned value is €1.2M, earned value €1.0M, actual cost €1.1M.
Which two statements are true? It's under budget, as it spent less than planned Incorrect. Spending less than planned says nothing about the work done.The project is over cost: CPI is about 0.91 Correct. Correct. EV ÷ AC = 1.0 ÷ 1.1.Earned value is simply what has been spent Incorrect. That's actual cost. Earned value is the budgeted value of the work done.The project is behind schedule (SPI ≈ 0.83) Correct. Correct. EV ÷ PV = 1.0 ÷ 1.2.
Learn it on Day 32: Are we on track? Technique: Earned value
Check answer
Question 35 of 49 Choose 1
Amara (Project Coordinator) The lighting is green on the dashboard, but the supplier hasn't delivered anything.
What do you do? Keep it green: there's still time to recover Incorrect. Green outside, red inside hides problems until it's too late.Apply the agreed rules: amber, with a recovery plan Correct. Right. Colours follow rules, not mood.Remove the colours, to stop the arguments about them Incorrect. The rules make colours useful; removing them loses the signal.
Learn it on Day 32: Are we on track? Technique: RAG status
Check answer
Question 36 of 49 Choose 1
Alonzo (Residents' Association Chair) Residents now want the bridge 50 cm wider for mobility scooters.
What happens first? Approve it at once: accessibility matters most Incorrect. It may be right, but nobody yet knows the cost or delay.Reject it: the design is approved and final Incorrect. Approved designs can change for good reasons. Control it, don't forbid it.Log a change request and assess its impact first Correct. Right. A good reason still needs a known cost and effect.
Learn it on Day 33: The change request Technique: Impact analysis
Check answer
Question 37 of 49 Choose 1
Ayesha (Finance Officer) Widening costs €60,000 and two weeks on the critical path. Your limit is €25,000.
Who decides? The change board or sponsor, with the options Correct. Right. Beyond your tolerance, it goes up, with a recommendation.You, because accessibility is so important Incorrect. Importance doesn't change who has the authority.The contractor, because he'll have to build it Incorrect. Suppliers don't approve changes to the council's project.
Learn it on Day 33: The change request Technique: Change board
Check answer
Question 38 of 49 Choose 1
Ainsley (Structural Engineer) The steel supplier will be four weeks late. Our time tolerance is two weeks.
What do you do? Wait a week, to see whether the delay improves by itself Incorrect. Waiting turns options into problems.Escalate today with an exception report and options Correct. Right. Beyond tolerance means the sponsor decides, now.Ask the team to work weekends quietly to catch up Incorrect. That hides it and may not work.
Learn it on Day 34: Out of tolerance Technique: Management by exception
Check answer
Question 39 of 49 Choose 1
Augustus (Town Clerk) Whose fault is the steel delay?
How do you run the discussion? Blame the supplier clearly in the minutes, for the record Incorrect. Blame doesn't open the bridge.Blame yourself, to end the discussion quickly and move on Incorrect. That's not honest either, and it doesn't help decide.Focus on the decision; record causes without blame Correct. Right. Decide first, learn after.
Learn it on Day 34: Out of tolerance Technique: Blameless review
Check answer
Question 40 of 49 True or false
Arnav (Contractor Site Manager) We fitted stainless steel bins instead of the specified ones, free of charge.
True or false: free extras don't need to go through change control. True Incorrect. Free extras can add maintenance or safety issues. They're changes too.False Correct. Correct. Gold-plating is still a change: check and record it.
Learn it on Day 36: Is it done?
Check answer
Question 41 of 49 Choose 1
Aoife (Harbour Master) A new risk: the winter storm season starts in three weeks, and the final lift isn't booked.
What do you do? Add it to the register and book the lift now Correct. Right. Early responses are cheap.Wait to see the weather forecast nearer the time Incorrect. By then, the crane may not be available.Leave the old risks as they are and add nothing Incorrect. Risk reviews must add new risks and close old ones.
Learn it on Day 38: The risk review Technique: Risk responses
Check answer
Question 42 of 49 Choose 1
Augustus (Town Clerk) The council needs €150,000 back. The opening date can't move.
How do you decide what to cut? Cut every budget line by the same percentage, to be fair Incorrect. That can break something critical, like the handrails.By priority and benefit, keeping safety and lighting Correct. Right. Then re-baseline after approval.Refuse: the council already approved this budget in full Incorrect. Budgets can change; show the consequences.
Learn it on Day 35: The budget is cut Technique: MoSCoW
Check answer
Question 43 of 49 Choose 1
Augustus (Town Clerk) I'm retiring next month. Alba from finance becomes sponsor.
What do you do? Nothing: the project is nearly done anyway, so carry on Incorrect. Late surprises need a sponsor who understands the history.Send her the whole project file to read in her own time Incorrect. Too much to be useful. Brief her on what matters.Arrange a handover with both, then brief the new one Correct. Right. A new sponsor needs to own the project, not just inherit it.
Learn it on Day 39: A new sponsor Technique: Knowledge transfer
Check answer
Harbourbridge
Closing Opening the bridge and closing the project
Question 44 of 49 Choose 1
Ainsley (Structural Engineer) The bridge passed the load test. Can we open tomorrow?
How do you decide? Use the readiness checklist: go if critical items are ready Correct. Right. Decide on agreed criteria, not excitement.Open now: the load test has passed, so it's safe Incorrect. The load test is one item. Signage and lighting are safety items too.Wait until every small defect is fixed first, then open Incorrect. Minor defects can be listed with dates. Perfection isn't the criterion.
Learn it on Day 41: Are we ready to open? Technique: Go or no-go review
Check answer
Question 45 of 49 Choose 1
Augustus (Town Clerk) After the opening, who looks after the bridge?
What does a good handover include? A thank-you email to the maintenance team, and done Incorrect. Nobody knows who fixes the next problem.A formal handover with documents, warranties and owners Correct. Right. Ownership changes clearly.Keep the project open until the warranties expire Incorrect. Operations should own it; the project closes.
Learn it on Day 42: Opening day
Check answer
Question 46 of 49 Choose 1
Arnav (Contractor Site Manager) Can you release our 5% retention now?
What do you do? Release it now, as a goodwill gesture to the contractor Incorrect. The retention protects the council against later defects.Keep the retention indefinitely, in case of trouble Incorrect. Withholding beyond the agreement is unfair.Release it on the contract's date and terms, in writing Correct. Right. Close contracts on the agreed terms.
Learn it on Day 43: Closing the contracts
Check answer
Question 47 of 49 Choose 2
Amara (Project Coordinator) We have lessons from every stage. Is a final review still needed?
Which two statements are true? Only the project manager should write it up Incorrect. The team and suppliers see things you didn't.It should recommend changes for future projects Correct. Correct. Lessons without recommendations rarely get used.It's mainly about who made the mistakes, and when Incorrect. It's about improving processes, not blame.A whole-project review finds patterns stages miss Correct. Correct.
Learn it on Day 44: Letting the team go Technique: Timeline Retrospective
Check answer
Question 48 of 49 Choose 1
Augustus (Town Clerk) Can't you just email that the project is closed?
What does formal closure include? An email to the sponsor is enough to close it Incorrect. Nobody can see what was delivered against what was approved.A closure report that the sponsor signs off Correct. Right. Closure is a decision, not a fade-out.Keep it open until the benefits are measured Incorrect. Benefits are measured by the organisation after closure.
Learn it on Day 44: Letting the team go
Check answer
Question 49 of 49 Choose 1
Alonzo (Residents' Association Chair) Six months on: the walk to school is 4 minutes, but harbour-side shop trade is only up 5%, not 15%.
How do you report this? Lower the trade target to 5%, to match the result Incorrect. Changing targets to fit results destroys trust.Call the project a failure, to be honest about it Incorrect. The project delivered what was approved; benefits often take longer.Honestly: one benefit achieved, the other on its way Correct. Right. Project success and benefit success are reported separately.
Learn it on Day 46: Was it worth it? Technique: Benefits tracking
Check answer