School extension 51 questions 5 phases
Brookfield: a Project Manager case study Brookfield Primary has 120 more children than places. Four classes are taught in old portable cabins. The education authority wants six new classrooms, built on the playground, while 400 children keep coming to school every day. You run the project.
What this case study tests
Safety next to children Summer works window Forecasting cost Handover to the school
You're the Project Manager. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Stakeholders
Asher (Project Manager) You Adelina (Head of Education Estates) Sponsor Agatha (Head Teacher) Senior user: pupils, staff and parents Abner (Architect) Designs the extension Alessia (Contractor Project Manager) Builds it Akira (Health and Safety Advisor) Children on a building site Anouk (Parent Council Chair) Speaks for parents Azra (Finance Manager) Capital budget Brookfield
Starting up Too many children, not enough rooms
Question 1 of 51 Choose 1
Adelina (Head of Education Estates) We need six classrooms. Just get a builder in.
What is the best first step? Understand the need and check the options before committing Correct. Right. Six classrooms is one answer; others might fit better.Hire the builder the authority used last time, to save time Incorrect. Committing before the need and the options are clear risks the wrong solution.Wait for the next school year before doing anything at all Incorrect. The need is real now. Shape it into something that can be decided.
Learn it on Day 1: A request lands on your desk
Check answer
Question 2 of 51 True or false
Azra (Finance Manager) Options: extend the building, buy more cabins, share space with the secondary school, or do nothing.
True or false: “do nothing” should be in the options analysis. True Correct. Correct. It's the baseline every option is compared with.False Incorrect. Without it, you can't show what the investment changes.
Learn it on Day 3: Is it worth it?
Check answer
Question 3 of 51 Choose 1
Agatha (Head Teacher) The benefit I care about is children learning in proper classrooms.
How should the benefit be written? “Better learning for every single child at Brookfield.” Incorrect. Too vague to measure.“All pupils in permanent classrooms by September.” Correct. Right. Baseline, target and date, so it can be checked later.Leave it out: learning is hard to put a price on Incorrect. Benefits you can't price still matter. Describe them.
Learn it on Day 3: Is it worth it?
Check answer
Question 4 of 51 Choose 1
Adelina (Head of Education Estates) Approved: €3.4M. I keep €250,000 aside.
Who can use the €250,000? The contractor, for any extras on site Incorrect. Suppliers don't control the client's reserve.The project manager, whenever needed Incorrect. It's not yours to spend without agreement.The sponsor, who holds the reserve Correct. Right. The project plans within €3.4M and asks Adelina (Head of Education Estates) if a big surprise needs it.
Learn it on Day 4: The decision
Check answer
Question 5 of 51 Choose 1
Adelina (Head of Education Estates) You can approve changes up to €15,000 yourself.
Where should this limit be written down? In the charter, as your authority and tolerance Correct. Right. Everyone sees the same limits.Nowhere: it's an informal agreement between you Incorrect. Informal limits get disputed at the worst moment.Only in your own notebook, as a reminder Incorrect. Others need to know your authority too.
Learn it on Day 5: Who's in charge here? Technique: Management by exception
Check answer
Question 6 of 51 Choose 2
Akira (Health and Safety Advisor) Children will walk past the site every day.
Which two stakeholders are high influence and need close involvement? Agatha (Head Teacher), who runs the school day Correct. Correct.A supplier of paint brushes for the decorators Incorrect. Low influence and interest.Akira (Health and Safety), who can stop works Correct. Correct.A parent who moved away from the area last year Incorrect. No longer affected.
Learn it on Day 6: Everyone who matters Technique: Stakeholder map (power and interest)
Check answer
Question 7 of 51 Choose 1
Anouk (Parent Council Chair) Parents found out about the building plans on social media. They're upset.
What do you do? Explain that it was decided properly by the authority Incorrect. Correct, but it ignores their concern.Promise parents a vote on the whole design, to calm things Incorrect. A promise you can't keep makes things worse.Listen, acknowledge it, and agree how news will reach them Correct. Right. A termly newsletter and a named contact. Recorded in the stakeholder register.
Learn it on Day 6: Everyone who matters Technique: Active listening
Check answer
Question 8 of 51 Choose 1
Agatha (Head Teacher) At the kick-off, my deputy and the architect argued for twenty minutes about the hall.
How do you handle it? Park it, finish the agenda, then meet both afterwards Correct. Right. The meeting stays on track and the issue gets proper attention.Pick a side quickly, so that the meeting can move on Incorrect. The overruled person stops speaking up.Tell them both to stop arguing in front of the others now Incorrect. The disagreement is real; it needs a decision.
Learn it on Day 9: The kick-off Technique: Parking lot
Check answer
Question 9 of 51 Choose 1
Azra (Finance Manager) Modular classrooms cost less now. A permanent extension costs more but saves rent and repairs for 40 years.
What should the business case show? The net present value of each option over the same 40 years Correct. Right. With costs and savings discounted to today's money, plus the payback point, it shows which option gives the best value over its whole life.Only the upfront cost of each of the two options on the table Incorrect. That ignores decades of rent and repairs.Total savings over 40 years, simply added up without discounting Incorrect. That overstates savings far in the future.
Learn it on Day 3: Is it worth it?
Check answer
Question 10 of 51 Choose 1
Adelina (Head of Education Estates) Brookfield is one of six schools in the authority's school-building programme. Do I really need a separate board for it?
What governance fits? No board: the programme decides everything for each school Incorrect. Day-to-day decisions would queue behind six schools.A light project board, reporting to the programme board Correct. Right. A light project board decides for this school within agreed tolerances; the programme board balances contractors and money across all six schools.Ignore the programme: this school is the most urgent Incorrect. Shared contractors and money must be coordinated across schools.
Learn it on Day 7: Who does what
Check answer
Brookfield
Planning Building around the school day
Question 11 of 51 Choose 1
Abner (Architect) Teachers want smartboards, a roof garden, a music room and air conditioning.
How do you decide what's in scope? Include everything, to keep the school and its teachers happy Incorrect. The budget would double.Test each against the objective, and record exclusions Correct. Right. Ventilation is a must; the roof garden is out, recorded for later.Let the architect decide what goes into the design Incorrect. The users and the sponsor decide priorities.
Learn it on Day 10: What exactly are we building? Technique: MoSCoW
Check answer
Question 12 of 51 Choose 1
Abner (Architect) How do we break the extension into plannable pieces?
Which statement about the work breakdown structure is true? It lists all of the project's activities in date order Incorrect. That's a schedule. The WBS is about deliverables.Project management work is always left out of it Incorrect. It needs its own branch.It divides the scope into pieces that someone can own Correct. Right. If it's not in the WBS, it's not in the project.
Learn it on Day 10: What exactly are we building? Technique: Work breakdown (decomposition)
Check answer
Question 13 of 51 Choose 1
Alessia (Contractor Project Manager) Noisy work can only happen in school holidays and after 15:30.
What does this mean for the schedule? Noisy work is tied to set windows, like the summer Correct. Right. Noisy activities are tied to calendar windows, so the critical path may run through the summer holiday.Nothing: the work can happen at any time of day it suits Incorrect. The school day is a hard constraint.Do all the noisy work at night instead of by day Incorrect. Noise at night affects neighbours and costs more.
Learn it on Day 12: How long will it really take? Technique: Critical path
Check answer
Question 14 of 51 Choose 1
Azra (Finance Manager) Here's the budget. When will we actually spend the money?
What do you give finance? Just the total budget for the year Incorrect. Money must be available when invoices arrive.A month-by-month spending profile Correct. Right. The peak is the summer holiday; finance can arrange funding to match.The whole budget released in month one Incorrect. Not how the work happens.
Learn it on Day 14: What will it cost?
Check answer
Question 15 of 51 Choose 1
Akira (Health and Safety Advisor) Risk: a child gets onto the site.
Which response reduces this risk? Accept it: building sites always carry some risk Incorrect. Child safety risks are never simply accepted.Transfer it to the parents by a signed agreement Incorrect. Not possible or acceptable.Fencing, separate entrances, supervised routes Correct. Right. Lower the likelihood and the impact.
Learn it on Day 16: What could go wrong? Technique: Risk responses
Check answer
Question 16 of 51 True or false
Azra (Finance Manager) Good news: a green building grant could pay €120,000 if we apply by March.
True or false: this belongs in the risk register. True Correct. Correct. It's an opportunity: an uncertain event that would help. Give it an owner.False Incorrect. Risks include positive ones; missing an opportunity is a loss.
Learn it on Day 16: What could go wrong?
Check answer
Question 17 of 51 Choose 1
Alessia (Contractor Project Manager) Should the building be fixed price or time and materials?
Which fits a fully designed extension? Fixed price: the scope is clear, so the risk can move Correct. Right.Time and materials: it's more flexible for changes Incorrect. On clear scope, that leaves all cost risk with the authority.No formal contract: trust is enough with a known firm Incorrect. Public money needs a proper contract.
Learn it on Day 18: Buying what we need Technique: Contract types
Check answer
Question 18 of 51 Choose 1
Agatha (Head Teacher) Quality means the most expensive materials.
What does quality mean here? The most expensive option, every single time, to be sure Incorrect. That's gold-plating and breaks the budget.Meeting the requirements: safe, durable, fit for use Correct. Right. Expensive extras are grade, not quality.Whatever the contractor delivers on handover day Incorrect. Quality is defined and checked by the client.
Learn it on Day 19: Good enough, and who hears what
Check answer
Question 19 of 51 Choose 1
Anouk (Parent Council Chair) With 400 families, how will everyone stay informed?
What goes into the communication plan? One big email to all families, every single school day Incorrect. Too much for most, not enough for some.Only tell people when something has gone wrong on site Incorrect. Silence breeds rumours.For each audience: what, how, how often, who sends Correct. Right. Parents: fortnightly email. Staff: Monday briefing. Authority: monthly report.
Learn it on Day 19: Good enough, and who hears what Technique: Stakeholder communication plan
Check answer
Question 20 of 51 Choose 1
Alessia (Contractor Project Manager) We priced every piece of the extension separately and added them up: €3.2M.
What kind of estimate is this? Bottom-up: slower to make, but more accurate Correct. Right. Compare it with the earlier top-down figure and explain the difference.Analogous: based on a similar past project Incorrect. That's top-down. This one adds up the pieces.A rough guess from the quantity surveyor Incorrect. It's built from the work, so it's an estimate, not a guess.
Learn it on Day 14: What will it cost? Technique: Bottom-up estimating
Check answer
Question 21 of 51 Choose 1
Adelina (Head of Education Estates) Before a design, can a two-storey extension even be built on the playground?
What do you check first? Go straight to detailed design, to save some time Incorrect. Expensive if the idea turns out impossible.A short feasibility check: planning, ground, budget Correct. Right. Feasible, with a condition: a temporary playground on the field.Ask the parents to vote on whether to go ahead with it Incorrect. Opinions matter, but they don't answer feasibility.
Learn it on Day 2: Not the only proposal Technique: PESTLE analysis
Check answer
Question 22 of 51 Choose 1
Agatha (Head Teacher) My teachers can't judge a classroom from drawings.
How do you check the layout with them? Show them more detailed drawings of each room, in colour Incorrect. Drawings are hard for most people to read.Wait for the real building to be finished first Incorrect. Changes then cost far more.A full-size mock-up of one classroom, with a real lesson Correct. Right. They find the sink blocks the fire exit route. Fixed on paper.
Learn it on Day 11: From needs to tests Technique: Prototyping and mock-ups
Check answer
Question 23 of 51 Choose 1
Azra (Finance Manager) If we skip the ground survey (€12,000), there's a 25% chance of a €100,000 foundation problem.
Question 24 of 51 Choose 1
Agatha (Head Teacher) The building design is fixed, but how teachers will use the new rooms is still unclear.
How do you plan the work? Fix every classroom detail now, so nothing changes later on Incorrect. Teachers' needs will change the layout later, at higher cost.Leave the whole project open to change throughout Incorrect. Construction needs firm plans, permits and contracts.A hybrid: plan the build, and shape the rooms with teachers Correct. Right. Plan the construction predictively and develop the layouts iteratively with teachers in a mock-up; use agile cycles where users will discover their needs.
Learn it on Day 8: How should we run it?
Check answer
Question 25 of 51 Choose 1
Akira (Health and Safety Advisor) Building beside a working school brings fire rules, building regulations and safeguarding checks for every worker on site.
How do you make sure nothing is missed? List every rule and approval, with owners and dates Correct. Right. Every regulation, approval and safeguarding check gets an owner and a date, and compliance is confirmed before handover; the law makes the authority responsible.Leave it to the contractor, who knows the rules well Incorrect. The authority remains responsible for compliance.Check it all together at the very end of the build Incorrect. Problems found at the end are the most expensive to fix.
Learn it on Day 13: Rules we must follow
Check answer
Brookfield
Delivering A building site next to a playground
Question 26 of 51 Choose 1
Alessia (Contractor Project Manager) Can we move the delivery lorries to 08:30? It's easier for the drivers.
What do you decide? Yes, as long as the drivers are careful near the gate Incorrect. Lorries and 400 children at the gate is a serious risk.No: deliveries stay outside drop-off and pick-up Correct. Right. Child safety comes before convenience.Let the drivers decide what's safe on the day Incorrect. Safety rules are set by the project, not individual drivers.
Learn it on Day 21: Breaking ground
Check answer
Question 27 of 51 Choose 1
Agatha (Head Teacher) The new teachers for September haven't been hired yet.
What should the project do? Ignore it: hiring teachers isn't part of the building work Incorrect. Empty classrooms don't deliver the benefit.Hire the teachers yourself to make sure it happens Incorrect. That's the school's responsibility.Treat it as a risk to the benefit, and agree who owns it Correct. Right. The project delivers rooms; the school delivers teachers. Both matter.
Learn it on Day 23: Building the team Technique: Risk responses
Check answer
Question 28 of 51 Choose 1
Agatha (Head Teacher) My teachers are worn out from working next to a building site all term.
What can the project do? Listen, reduce disruption, and thank staff for patience Correct. Right. Looking after the people affected keeps them on side.Nothing: staff morale is the school's problem, not ours Incorrect. The project causes the disruption; it should help reduce it.Tell them it will all be worth it in the end, soon Incorrect. True, but it doesn't help today.
Learn it on Day 23: Building the team Technique: Recognition
Check answer
Question 29 of 51 Choose 1
Alessia (Contractor Project Manager) Asbestos was found in the old wall we're connecting to. We need €38,000 and two weeks.
What do you do first? Pay at once, to keep the contractor on side Incorrect. Check first.Check the contract and survey, and ask for evidence Correct. Right. The survey excluded that wall; it's a genuine change.Refuse outright: the contract here is fixed price Incorrect. Truly unforeseen conditions are usually the client's risk.
Learn it on Day 25: When a supplier slips Technique: Negotiation
Check answer
Question 30 of 51 Choose 1
Akira (Health and Safety Advisor) An inspection found fire doors without the right closers in two classrooms.
What happens? Accept it for now, and fix the closers in the summer Incorrect. Fire safety can't wait.Close the whole school until it's repaired Incorrect. Out of proportion; the rooms aren't in use yet.Record it; the contractor fixes it at their cost Correct. Right.
Learn it on Day 26: Quality on site Technique: Inspection and testing
Check answer
Question 31 of 51 Choose 1
Alessia (Contractor Project Manager) We have 62 snags: paint, door handles, window catches, signs…
How do you prioritise? Group by cause, and fix the biggest causes first Correct. Right. Two causes (window supplier, painter) make up most of the list.Fix them in the order they were reported to you Incorrect. That treats a missing sign like a broken window catch.Leave them all until the end of the works, then fix Incorrect. Causes keep creating new snags.
Learn it on Day 26: Quality on site Technique: Pareto chart
Check answer
Question 32 of 51 Choose 1
Anouk (Parent Council Chair) Parents complain the site noise disturbs exams week.
What do you do? Explain that building work is always noisy Incorrect. True but unhelpful.Pause noisy work during exams, agreed with all Correct. Right. A practical deal that respects both sides.Stop the works completely for a whole month Incorrect. Unnecessary; a short pause during exams is enough.
Learn it on Day 28: The neighbours are angry Technique: Negotiation
Check answer
Question 33 of 51 Choose 1
Adelina (Head of Education Estates) Let's announce the opening a month early in the press.
How do you respond? Agree: good news is good news for everyone involved Incorrect. An early promise is likely to break publicly.Say nothing, and let Adelina announce it anyway Incorrect. Staying quiet makes you part of a risky promise.Show the real status, and offer a confirmed event Correct. Right. Honest reporting upwards with an alternative.
Learn it on Day 28: The neighbours are angry Technique: Saying no with reasons
Check answer
Question 34 of 51 True or false
Abner (Architect) The head teacher asked my team directly to add a window. We could just do it.
True or false: changes agreed directly between users and suppliers save time. True Incorrect. They bypass cost, design and safety checks and invite claims later.False Correct. Correct. Every change goes through change control.
Learn it on Day 30: A key person leaves
Check answer
Question 35 of 51 Choose 1
Alessia (Contractor Project Manager) Our window supplier has gone bust. The windows were due next week.
What do you do? Log it as an issue, recover what you can, find a replacement Correct. Right. Temporary boarding keeps the site safe while new windows are ordered.Wait for the administrators to sort the supplier out Incorrect. That can take months.Blame procurement for picking such a weak supplier Incorrect. Act first, learn later.
Learn it on Day 29: The supplier goes bust Technique: Escalating impediments
Check answer
Question 36 of 51 Choose 1
Agatha (Head Teacher) My staff are anxious about moving classes mid-year into new rooms with new technology.
How do you help? Tell them it's decided and they need to adapt Incorrect. Resistance grows.Explain why, involve teachers, and train early Correct. Right. People adopt what they help shape.Leave it to the head teacher, who knows them Incorrect. The project caused the change; it should help people adopt it.
Learn it on Day 31: Getting people ready Technique: The change curve
Check answer
Question 37 of 51 Choose 1
Agatha (Head Teacher) Teachers are anxious about the noise and moving classes mid-year. Some feel nobody listens to them.
How do you lead them through it? Send a memo with the plan to every teacher Incorrect. A memo doesn't address fears.Lead through involvement: listen and explain Correct. Right. Listen to the teachers, explain the plan and why, respect the school's culture of routines, and agree how disruption is handled; people accept change better when heard.Leave it to the head teacher, who knows them best Incorrect. The project brings the change; helping people through it is part of the job.
Learn it on Day 31: Getting people ready
Check answer
Brookfield
Keeping control Summer is the critical window
Question 38 of 51 Choose 1
Azra (Finance Manager) Planned value €1.8M, earned value €1.8M, actual cost €2.0M.
What does this show? Ahead of schedule, and on budget so far Incorrect. EV equals PV: on schedule.Under budget, and on schedule too, so far Incorrect. AC is higher than EV: over cost.On schedule (SPI 1.0), over cost (CPI 0.9) Correct. Right. Work is where it should be, but costing more than planned.
Learn it on Day 32: Are we on track? Technique: Earned value
Check answer
Question 39 of 51 Choose 1
Agatha (Head Teacher) Can the music room be added after all? We found some money.
What happens? Log a change request and assess the impact first Correct. Right.Add it straight away, since the money now exists Incorrect. Money isn't the only impact: the summer window may not fit.Refuse it: the scope is frozen now, so no Incorrect. Changes are controlled, not banned.
Learn it on Day 33: The change request Technique: Impact analysis
Check answer
Question 40 of 51 Choose 1
Alessia (Contractor Project Manager) Window delivery is five weeks late. That pushes us beyond the summer holiday.
Your time tolerance is two weeks. What do you do? Wait and see whether the delay recovers itself Incorrect. Waiting removes options.Escalate at once with a report and options Correct. Right. The sponsor decides with all the facts.Ask the contractor to fix it quietly, off the record Incorrect. The sponsor loses the chance to decide.
Learn it on Day 34: Out of tolerance Technique: Management by exception
Check answer
Question 41 of 51 Choose 1
Azra (Finance Manager) Actual cost so far €2.0M, earned value €1.8M, budget €3.4M. What's the likely final cost?
If the overrun was a one-off, what is the estimate at completion? €3.4M, the same as the approved budget Incorrect. The budget is the target, not the forecast.€2.0M, the actual cost spent so far Incorrect. That's only what's been spent so far.About €3.6M: €2.0M + (€3.4M − €1.8M) Correct. Right. €200,000 above budget, which needs the sponsor's reserve.
Learn it on Day 34: Out of tolerance
Check answer
Question 42 of 51 Choose 1
Agatha (Head Teacher) Shall I just sign the acceptance? The rooms look lovely.
How should acceptance work? Check every criterion against the inspection results Correct. Right. Acceptance is against criteria, by the users.Sign it: the rooms look fine on the walk-round today Incorrect. Once signed, fixing defects is much harder.Let the contractor sign it off on your behalf Incorrect. The user side accepts.
Learn it on Day 36: Is it done? Technique: Acceptance criteria and Given/When/Then
Check answer
Question 43 of 51 Choose 1
Akira (Health and Safety Advisor) Our weekly risk review is the same list every week.
How do you make it useful? Drop the weekly risk review entirely, to save time Incorrect. Risks change most near the end.Short and focused: what changed and the top five Correct. Right.Make it longer, so that every risk gets covered Incorrect. Focus beats length.
Learn it on Day 38: The risk review Technique: Timeboxing
Check answer
Question 44 of 51 Choose 2
Adelina (Head of Education Estates) The building phase is done. What does the board decide now?
Which two inputs does the stage gate need? A list of who was to blame for delays Incorrect. Not a decision input.An updated check of the business case Correct. Correct. Is it still worth it?The contractor's latest sales brochure Incorrect. Irrelevant.An end-stage report against the baselines Correct. Correct.
Learn it on Day 40: Ready for the last stage? Technique: Stage gate
Check answer
Question 45 of 51 Choose 1
Akira (Health and Safety Advisor) An audit found that two approved changes never reached the drawings the contractor uses.
What do you do? Accept it, fix the process, and agree a re-check Correct. Right. Fix the process, not just the two drawings.Argue the point with the auditor, bringing evidence Incorrect. Use the finding.Fix the two drawings quickly, then move on to other work Incorrect. It will happen again.
Learn it on Day 37: Is the process working? Technique: Version control
Check answer
Brookfield
Closing First day in the new classrooms
Question 46 of 51 Choose 1
Agatha (Head Teacher) A trial day with two classes found the heating controls confusing and a door that sticks.
What do you do? Cancel the opening until everything is perfect again Incorrect. Small findings are fixable; that's the point of the rehearsal.Log each finding, fix it, and re-test before the day Correct. Right. Rehearsals are meant to find problems.Ignore them: they're small and won't matter much Incorrect. Then children and teachers find them on day one.
Learn it on Day 41: Are we ready to open? Technique: Dress rehearsal
Check answer
Question 47 of 51 Choose 1
Agatha (Head Teacher) From when is the building ours?
How do you hand over? Verbally, to the caretaker, on the opening day Incorrect. Nobody's sure who fixes the next problem.When the very last snag has been fixed Incorrect. List open items and hand over.Formally, with documents and warranties Correct. Right.
Learn it on Day 42: Opening day
Check answer
Question 48 of 51 Choose 1
Alessia (Contractor Project Manager) Our final invoice includes €12,000 for extra cleaning before opening.
How do you respond? Check the contract and change log, then discuss it Correct. Right. Settle final claims with records.Pay it: they did do the extra cleaning, after all Incorrect. Check first.Withhold the whole final payment until he drops it Incorrect. Pay undisputed amounts on time.
Learn it on Day 43: Closing the contracts
Check answer
Question 49 of 51 Choose 2
Anouk (Parent Council Chair) Will anyone check if the children are better off?
Which two statements about benefits are true? Benefits need owners in the organisation who stay after the project closes Correct. Correct. The head teacher owns the learning benefits.Benefits are measured on the very last day of the project itself Incorrect. Most arrive later.Benefits are reviewed against their baseline and target at agreed points Correct. Correct.If the building is finished, the benefits have been achieved Incorrect. The building is the output; benefits are what it changes.
Learn it on Day 46: Was it worth it? Technique: Benefits tracking
Check answer
Question 50 of 51 Choose 1
Adelina (Head of Education Estates) One term later, all four cabins are gone, but two classes are still too big.
How do you describe the outcome? The project failed, as the class-size target wasn't met Incorrect. Not fair: the project's output was delivered.Everything is perfect, as the rooms are open Incorrect. Not honest.Delivered as approved; the benefit is partly there Correct. Right. Separate project success from benefit success.
Learn it on Day 46: Was it worth it?
Check answer
Question 51 of 51 Choose 1
Agatha (Head Teacher) Now we'd love a new sports hall.
What happens with that idea? It's a new request, to be assessed on its own case Correct. Right. The cycle starts again.Add it to this project while the builders are here Incorrect. The project is closed; new work needs its own decision.Say no: the project is already closed, so it can't Incorrect. Good ideas deserve a proper hearing.
Learn it on Day 46: Was it worth it?