Forecasting · cheat sheet Burn-up and burn-down charts Charts of work done over time that show a likely range for when a set of work might be finished.
Named in the Scrum Guide 6 steps Used by Product Owner, Scrum Master, Project Manager
What it is A chart with two lines over time: total work in scope and work completed. Where the completed line is heading shows when the work is likely to finish.
When to use it To answer “when?” with evidence. The Scrum Guide names burn-downs and burn-ups as useful, but says they don't replace empiricism.
Why it works It shows progress and scope changes on one chart, so stakeholders see both why dates move and how fast work is getting done.
Do Always show a range; a single line suggests false certainty. Don't Promising the fastest line. Using burn-downs to pressure the Developers. Step by step Choose a unit Items, points or value.
Plot total scope It goes up when scope is added.
Plot completed work Each period.
Draw the trend Use a range from slow to fast periods, not one line.
Read the forecast Where the completed range meets the scope line.
Update every period And explain scope changes.
Worked example The situation. A team with 120 items to finish.
They complete 10 to 14 items per fortnight. Scope grows by 10 items mid-way. Forecast: 9 to 13 fortnights. The result. Stakeholders saw that the date moved because scope grew, not because the team slowed.
Period Total scope Completed (cumulative) Notes
Copy this structure, or print the blank version and fill it in by hand.
In the roles How a Product Owner uses itAli (Sales Director) wants a date for promo codes. The burn-up shows 4 to 6 items per Sprint and 9 items ahead of promo codes: likely Sprint 4, possibly Sprint 3. Ali gets a range, and it holds.
How a Scrum Master uses itAli (Sales Director) wants Aaron (Scrum Master) to give him a date. Aaron helps Anna (Product Owner) build a burn-up from what the team really finished, so Ali gets a range he can plan with.
How a Project Manager uses itThe booking system's progress is reported as a burn-up of features against the release goal, next to the building's earned value.
Questions people ask Burn-up or burn-down? Burn-up shows scope changes; burn-down hides them in one line.