A chart with activities down the side and time across, each activity shown as a bar, often with links and milestones.
Common practice 6 steps Used by Project Manager, Process Improvement Specialist
What it is
A bar chart of a schedule: activities down the side, time across the top, each activity a bar from start to finish, often with dependencies and milestones.
When to use it
To show and discuss the schedule with the team, the sponsor and suppliers.
Why it works
It's the easiest way to show a plan to people: what happens when, what overlaps, and what's critical.
Do
Show only as much detail as the audience needs.
Don't
Drawing bars without dependencies: it looks like a plan but can't be recalculated.
Too much detail for the audience.
Step by step
List activitiesGrouped by deliverable.
Set durations and dependenciesFrom estimates and logic.
Draw the barsAgainst a time scale.
Add milestonesAs diamonds.
Highlight the critical pathIn a different colour.
Update with progressAnd show the baseline for comparison.
Twelve activities with durations (weeks) and what must finish first. A forward pass finds the earliest dates, a backward pass the latest; the difference is the float.
Step by step
Forward passeach activity starts when all its predecessors finish; earliest finish = start + duration= opening at the end of week 30
Backward passfrom week 30 back, the latest each activity can finish without delaying the end
Eight activities have no float: any delay to them delays opening. Hiring can slip 5 weeks and booking setup 7 without harm.
What it led to
Annelise (Project Manager) watches the building works and licence most closely, and uses the float in hiring when people are double-booked.
Do it in a spreadsheet
Earliest finish
=start + duration (start = MAX of predecessors' finishes)
Float
=latest start - earliest start
Gantt chart
stacked bar chart: invisible bar for the start, visible bar for the duration
Try it yourself: If building works take 16 weeks instead of 14, when does the clinic open?
Building works are critical, so opening moves 2 weeks, to the end of week 32.
In the roles
How a Project Manager uses it
Annelise (Project Manager)'s Gantt chart shows the building works as the longest bar in red (critical), hiring with its 5 weeks of slack, and the opening milestone in week 30.