Scope and scheduling · cheat sheet

Gantt chart

A chart with activities down the side and time across, each activity shown as a bar, often with links and milestones.

Common practice
6 steps
Used by Project Manager, Process Improvement Specialist

What it is

A bar chart of a schedule: activities down the side, time across the top, each activity a bar from start to finish, often with dependencies and milestones.

When to use it

To show and discuss the schedule with the team, the sponsor and suppliers.

Why it works

It's the easiest way to show a plan to people: what happens when, what overlaps, and what's critical.

Do

  • Show only as much detail as the audience needs.

Don't

  • Drawing bars without dependencies: it looks like a plan but can't be recalculated.
  • Too much detail for the audience.

Step by step

  1. List activities Grouped by deliverable.
  2. Set durations and dependencies From estimates and logic.
  3. Draw the bars Against a time scale.
  4. Add milestones As diamonds.
  5. Highlight the critical path In a different colour.
  6. Update with progress And show the baseline for comparison.
Also called: Bar chart schedulePrint the blank template ↗

Worked example

The situation. A six-week website launch.

  1. Bars: content (weeks 1–3), design (1–2), build (3–5), test (5–6).
  2. Milestone: launch end of week 6.
  3. Critical: design → build → test.

The result. Everyone could see that late content would hold up testing.

Gantt worksheet Print blank
ActivityStartDurationDepends onWk 1Wk 2Wk 3Wk 4Wk 5Wk 6

Copy this structure, or print the blank version and fill it in by hand.

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

Finding the critical path

From Day 12: How long will it really take? of the Project Manager story

Twelve activities with durations (weeks) and what must finish first. A forward pass finds the earliest dates, a backward pass the latest; the difference is the float.

Float for each activity, in weeks (0 = critical)02468A1: 00A1A2: 00A2A3: 00A3A4: 00A4A5: 44A5A6: 77A6A7: 55A7A8: 55A8A9: 00A9A10: 00A10A11: 00A11A12: 00A12

Step by step

  1. Forward passeach activity starts when all its predecessors finish; earliest finish = start + duration= opening at the end of week 30
  2. Backward passfrom week 30 back, the latest each activity can finish without delaying the end
  3. Floatlatest start − earliest start= hiring 5, equipment order 4, booking setup 7
  4. Critical pathactivities with zero float= A1 → A2 → A3 → A4 → A9 → A10 → A11 → A12
IDActivityWeeksStarts weekFinishes weekFloat (weeks)
A1Survey and design7170
A2Purchase completes1880
A3Asbestos removal39110
A4Building works1412250
A5Equipment order and delivery148214
A6Booking system setup109187
A7Hiring129205
A8Training521255
A9Equipment installation226270
A10Inspection128280
A11Licence229300
A12Opening030300

How to read the result

Eight activities have no float: any delay to them delays opening. Hiring can slip 5 weeks and booking setup 7 without harm.

What it led to

Annelise (Project Manager) watches the building works and licence most closely, and uses the float in hiring when people are double-booked.

Do it in a spreadsheet

Earliest finish=start + duration (start = MAX of predecessors' finishes)
Float=latest start - earliest start
Gantt chartstacked bar chart: invisible bar for the start, visible bar for the duration
Try it yourself: If building works take 16 weeks instead of 14, when does the clinic open?

Building works are critical, so opening moves 2 weeks, to the end of week 32.

In the roles

How a Project Manager uses it

Annelise (Project Manager)'s Gantt chart shows the building works as the longest bar in red (critical), hiring with its 5 weeks of slack, and the opening milestone in week 30.

How a Process Improvement Specialist uses it

Define, Measure, Analyse, Improve and Control on one chart over five months, with a review at the end of each phase.

Questions people ask

Is a Gantt chart a plan?

It's a picture of the schedule; the logic (dependencies) behind it is what makes it a plan.