Quick wins and the plan
Some fixes are too obvious to wait five months. Amara takes them now, puts a price on the benefits, and plans the rest of the project.
- 09:00Quick wins with Alma (Reception Team Lead)
- 11:00The benefits with Abigail (Finance Business Partner)
- 15:00Plan the phases
Situation 1 of 3
09:00 · Quick wins with Alma (Reception Team Lead)Should you wait for the analysis?
Situation 2 of 3
11:00 · The benefits with Abigail (Finance Business Partner)How do you estimate the benefits?
Estimating the benefits
If the project reaches its goal, how much of the €67,035 cost of poor quality goes away? Amara and Abigail (Finance Business Partner) estimate each line.
| Benefit | Today | After the project | Saving a year (€) |
|---|---|---|---|
| Missed appointments | 15% | 8% | 13335 |
| Repeat calls | 11,250 | 3,375 | 9450 |
| Emergency visits | 208 | 104 | 12480 |
- Missed appointments
12,700 × (15% − 8%) = 889 fewer; × €15= €13,335 - Repeat calls
70% fewer: 11,250 × 70% × €1.20= €9,450 - Emergency visits
half as many: 104 fewer × €120= €12,480 - Total
€13,335 + €9,450 + €12,480= €35,265 a year
Try it yourself in a spreadsheet
| Fewer missed appointments | =12700*(0.15-0.08) |
| Saving | =B2*15 |
| Total | =SUM(D2:D4) |
If missed appointments only fell to 10%, what would the total saving be?
Show the answer
12,700 × 5% × €15 = €9,525; plus €9,450 and €12,480 = €31,455 a year.
Situation 3 of 3
15:00 · Plan the phasesWhat does the plan need?
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Quick wins
- If a fix is obvious, cheap, low-risk and easy to undo, do it now. Patients shouldn't wait for the method.
- Log each change with its date, so its effect can be seen in the data and isn't mistaken for something else.
Estimating the benefits
- Estimate what reaching the goal is worth: cash savings, avoided costs, and benefits that aren't cash, like patient experience.
- Agree the counting method with finance at the start.
Where you will meet this: Hard and soft savings · benefits estimate
Plan the phases, detail as you go
- Put dates on each phase and its review. Plan in detail only the next few weeks; later phases depend on what you find.
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 12 complete
3 situations today.
- Take obvious quick wins straight away, log them with a date, and watch their effect.
- Estimate the benefits early, in money and beyond money, and agree the method with finance.
- Plan the phases and their reviews with dates; add detail as you learn.