Day 12 of 55Stage 1 · DefineTuesdayPlanning the project

Quick wins and the plan

Some fixes are too obvious to wait five months. Amara takes them now, puts a price on the benefits, and plans the rest of the project.

Stage goal: Agree the problem, the goal, the scope and who is involved.
Team
Alma (Reception Team Lead) Amara (Process Improvement Specialist)
Stakeholders
Abigail (Finance Business Partner)
How the day goes
  1. 09:00Quick wins with Alma (Reception Team Lead)
  2. 11:00The benefits with Abigail (Finance Business Partner)
  3. 15:00Plan the phases

Situation 1 of 3

09:00 · Quick wins with Alma (Reception Team Lead)
Alma (Reception Team Lead)
The phone message still says “call back tomorrow” when we're full. People hang up and call again at eight. Can we change it today?

Should you wait for the analysis?

Take obvious quick wins straight away, log them with a date, and watch their effect.

Situation 2 of 3

11:00 · The benefits with Abigail (Finance Business Partner)
Abigail (Finance Business Partner)
What will the project be worth if it reaches the goal?

How do you estimate the benefits?

Estimate the benefits early, in money and beyond money, and agree the method with finance.
Worked example 1

Estimating the benefits

If the project reaches its goal, how much of the €67,035 cost of poor quality goes away? Amara and Abigail (Finance Business Partner) estimate each line.

Expected saving per year, by source05,00010,00015,00020,000Missed / appointments: €13,335€13,335MissedappointmentsRepeat / calls: €9,450€9,450RepeatcallsEmergency / visits: €12,480€12,480Emergencyvisits
BenefitTodayAfter the projectSaving a year (€)
Missed appointments15%8%13335
Repeat calls11,2503,3759450
Emergency visits20810412480
Download the data (spreadsheet file)
  1. Missed appointments12,700 × (15% − 8%) = 889 fewer; × €15= €13,335
  2. Repeat calls70% fewer: 11,250 × 70% × €1.20= €9,450
  3. Emergency visitshalf as many: 104 fewer × €120= €12,480
  4. Total€13,335 + €9,450 + €12,480= €35,265 a year
What it meansReaching the goal is worth about €35,000 a year, around half the cost of poor quality. €22,785 is the clinic's own money; €12,480 is avoided cost for the wider health system.
What Amara decidesThe charter says “about €35,000 a year”, split into the clinic's savings and avoided cost, with the method agreed with Abigail (Finance Business Partner). The real figures are checked in Control.
Try it yourself in a spreadsheet
Fewer missed appointments=12700*(0.15-0.08)
Saving=B2*15
Total=SUM(D2:D4)

If missed appointments only fell to 10%, what would the total saving be?

Show the answer

12,700 × 5% × €15 = €9,525; plus €9,450 and €12,480 = €31,455 a year.

Situation 3 of 3

15:00 · Plan the phases
Amara (Process Improvement Specialist)
Five months, five phases, a team working four hours a week. Time to plan.

What does the plan need?

Plan the phases and their reviews with dates; add detail as you learn.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

Quick wins

  • If a fix is obvious, cheap, low-risk and easy to undo, do it now. Patients shouldn't wait for the method.
  • Log each change with its date, so its effect can be seen in the data and isn't mistaken for something else.
Common practice

Estimating the benefits

  • Estimate what reaching the goal is worth: cash savings, avoided costs, and benefits that aren't cash, like patient experience.
  • Agree the counting method with finance at the start.

Where you will meet this: Hard and soft savings · benefits estimate

Concept

Plan the phases, detail as you go

  • Put dates on each phase and its review. Plan in detail only the next few weeks; later phases depend on what you find.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 12 complete

3 situations today.

Your responsibility todayPlanning the project
Technique you usedQuick wins, benefits estimate, phase plan
Key points to remember
  • Take obvious quick wins straight away, log them with a date, and watch their effect.
  • Estimate the benefits early, in money and beyond money, and agree the method with finance.
  • Plan the phases and their reviews with dates; add detail as you learn.