Day 7 of 55Stage 1 · DefineTuesdayThe problem statement

A problem, not a solution

Everyone already knows the answer: more doctors, a new phone system, online booking. Amara asks them to agree on the problem first.

Stage goal: Agree the problem, the goal, the scope and who is involved.
Team
Astrid (Data Analyst)
Stakeholders
Aurelie (Practice Nurse Manager) Atticus (Director of Community Health)
Documents today Improvement charter
How the day goes
  1. 09:00Draft the problem with Astrid (Data Analyst)
  2. 11:00Check it with Aurelie (Practice Nurse Manager)
  3. 15:00Set the goal with Atticus (Sponsor)

Situation 1 of 3

09:00 · Draft the problem with Astrid (Data Analyst)
Astrid (Data Analyst)
Here's my draft: “Patients wait too long because we don't have enough doctors.”

What's wrong with it?

A problem statement describes what, where, since when and how big, plus the impact. No causes, no solutions.

Situation 2 of 3

11:00 · Check it with Aurelie (Practice Nurse Manager)
Aurelie (Practice Nurse Manager)process owner
“Over the last 20 weeks, patients asking for a routine appointment waited a median of 10 days, and 1 in 4 waited more than 14. The target is under 7.” Is that fair?

What else does it need?

Show the impact in the problem statement: it explains why the problem deserves time and money.
Worked example 1

Sizing the problem with Six Sigma metrics

Over 20 weeks, 4,800 patients asked for a routine appointment. Each request can go wrong in three ways. Astrid (Data Analyst) counts the defects.

First-time yield of each check, in percent0255075100Date on / first contact: 6565Date onfirst contactWithin / 7 days: 4545Within7 daysRight / type: 9696Righttype
CheckRequestsPassed first timeDefectsFirst-time yield
Date offered on first contact48003120168065%
Appointment within 7 days48002160264045%
Right type of appointment4800460819296%
Download the data (spreadsheet file)
  1. Total defects1,680 + 2,640 + 192= 4,512
  2. Defects per unit4,512 ÷ 4,800 requests= 0.94
  3. Defects per million opportunities4,512 ÷ (4,800 × 3 opportunities) × 1,000,000= 313,333
  4. First-time yield of each checkpassed first time ÷ requests= 65%, 45%, 96%
  5. Rolled throughput yield0.65 × 0.45 × 0.96= 0.28, so 28%
  6. Sigma levelfrom the defects per million, with the usual 1.5 shift= about 2.0
What it meansOnly 28 of every 100 requests get through all three checks without a problem. A sigma level of about 2 is typical of a service process that struggles. The weakest check by far is the 7-day wait.
What Amara decidesRecord these as the baseline in the charter: 45% within 7 days, 28% rolled throughput yield, about 313,000 defects per million opportunities. The goal is measured on the same definitions.
Try it yourself in a spreadsheet
Total defects=SUM(D2:D4)
Defects per unit=D5/B2
Defects per million opportunities=D5/(B2*3)*1000000
First-time yield=C2/B2
Rolled throughput yield=PRODUCT(E2:E4)
Sigma level=NORM.S.INV(1-F2/1000000)+1.5 (F2 = defects per million)

If the 7-day check improved to 90% and the others stayed the same, what would the rolled throughput yield be?

Show the answer

0.65 × 0.90 × 0.96 = 0.56, so 56%.

Situation 3 of 3

15:00 · Set the goal with Atticus (Sponsor)
Atticus (Director of Community Health)sponsor
Let's make the goal ambitious: zero waiting, by next month.

What goal do you propose?

Set a goal that is specific, measurable, realistic and has a date. It tells everyone when the project is done.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

A good problem statement

  • It says what is wrong, where, since when and how big, and what it costs the customer and the organisation.
  • It contains no causes and no solutions. Those come later, from the data.
Concept

Impact explains why now

  • Showing the impact (lost appointments, repeat work, money, risk) explains why this problem deserves time ahead of others.
  • It also becomes the starting point for measuring the benefits at the end.
Common practice

A goal with a finish line

  • The goal says how far, by when, measured how. It should be ambitious but realistic, and linked to the organisation's targets.
  • Without it, the project never knows when it's done.

Where you will meet this: Goal statement · SMART goals

Concept

The result depends on its causes

  • Every result (the wait, the error rate) depends on the inputs and steps that produce it. Change the right causes and the result follows; push on the result alone and nothing lasts.
  • The project's job is to find which few causes drive the result, and prove it.

Where you will meet this: Y = f(x)

Common practice

Counting defects

  • A defect is any failure to meet a customer requirement. Defects per unit, defects per million opportunities, first-time yield and rolled throughput yield all describe the same problem from different angles.
  • Rolled throughput yield multiplies the first-time yield of every step: it shows how rarely work gets through the whole process cleanly.

Where you will meet this: DPU · DPMO · FTY · RTY · sigma level

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 7 complete

3 situations today.

Your responsibility todayDefining the problem and the goal
Technique you usedProblem statement, goal statement
Key points to remember
  • A problem statement describes what, where, since when and how big, plus the impact. No causes, no solutions.
  • Show the impact in the problem statement: it explains why the problem deserves time and money.
  • Set a goal that is specific, measurable, realistic and has a date. It tells everyone when the project is done.
Documents today Improvement charter