Day 17 of 55Stage 2 · MeasureTuesdayData collection plan

What exactly do we count?

“Waiting time” sounds simple, until three people measure it three ways. Amara writes down exactly what is measured, how, by whom, and how much.

Stage goal: Map the process and measure how it performs today, with data you can trust.
Team
Astrid (Data Analyst) Alma (Reception Team Lead)
Stakeholders
Augustin (Black Belt)
Documents today Data collection plan
How the day goes
  1. 09:00Define the measures with Astrid (Data Analyst)
  2. 11:00Sample size with Augustin (Black Belt) and Alma (Reception Team Lead)
  3. 15:00Write the data collection plan

Situation 1 of 3

09:00 · Define the measures with Astrid (Data Analyst)
Astrid (Data Analyst)
Waiting time: from when? The first call? The call when they finally got through? And until the appointment, or the day it was booked?

How do you settle it?

Write an operational definition for every measure: exactly what, from when to when, and in what units.

Situation 2 of 3

11:00 · Sample size with Augustin (Black Belt) and Alma (Reception Team Lead)
Alma (Reception Team Lead)
Some of what we want to know is a number, like days. Some is yes or no, like “got a date on the first call”. Does it matter?

Why does the type of data matter?

Know your data type: continuous (measured) or discrete (counted, yes or no). It decides the tools and how much data you need.

Situation 3 of 3

11:00 · Sample size with Augustin (Black Belt) and Alma (Reception Team Lead)
Augustin (Black Belt)mentor
How many requests do you need to look at, to know the average wait well enough?

How do you decide the sample size?

Calculate the sample size from the precision you need and the spread of the data.
Worked example 1

How many records do we need?

To estimate the average wait within ±2 days with 95% confidence, Augustin (Black Belt) shows the sample size formula. A pilot of 20 records gave a standard deviation of about 6.5 days.

InputValue
Confidence95% (z = 1.96)
Standard deviation (pilot)6.5 days
Precision wanted (±)2 days
Download the data (spreadsheet file)
  1. Formulan = (z × s ÷ E)²
  2. Fill in(1.96 × 6.5 ÷ 2)²= 40.6
  3. Round upalways round up= 41 records
  4. What 60 givesE = 1.96 × 6.46 ÷ √60= ±1.6 days
What it meansAt least 41 random records are needed to know the average wait within 2 days. With 60, the estimate is within about 1.6 days.
What Amara decidesAstrid (Data Analyst) takes 60 requests at random from weeks 12 to 20, the period since the process shifted.
Try it yourself in a spreadsheet
Sample size=ROUNDUP((1.96*B3/B4)^2,0)
z for 95%=NORM.S.INV(0.975)
Random sample=RANDARRAY to number the records, then sort and take the first 60

How many records would you need for ±1 day?

Show the answer

(1.96 × 6.5 ÷ 1)² = 162.3, so 163 records. Halving the error quadruples the sample.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

Operational definitions

  • Write exactly what each measure means: start and end, units, what counts, borderline cases, source. Then anyone gets the same number.
Concept

Types of data

  • Continuous data is measured on a scale (days, minutes). Discrete data is counted or sorted (yes or no, number of errors).
  • Continuous data carries more information, so it needs fewer records; yes-or-no data needs many more.

Where you will meet this: Continuous (variable) and discrete (attribute) data

Common practice

How much data is enough

  • Sample size n = (z × s ÷ E)²: z for the confidence wanted (1.96 for 95%), s the spread from a pilot, E the precision wanted.
  • Choose records at random, from a period when the process was stable.

Where you will meet this: Sample size · random sampling · stratified sampling

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 17 complete

3 situations today.

Your responsibility todayPlanning the data
Technique you usedOperational definitions, data types, sample size
Key points to remember
  • Write an operational definition for every measure: exactly what, from when to when, and in what units.
  • Know your data type: continuous (measured) or discrete (counted, yes or no). It decides the tools and how much data you need.
  • Calculate the sample size from the precision you need and the spread of the data.
Documents today Data collection plan