Day 6 of 55Stage 0 · Getting startedMondayVariation

Averages hide the pain

The average wait is ten days. But some patients wait two days and others more than three weeks. Amara learns to look at the spread.

Stage goal: See the work as it really is, and pick the problem worth solving.
Team
Astrid (Data Analyst)
Stakeholders
Augustin (Black Belt)
Techniques today Run chart
How the day goes
  1. 09:00First look at the waiting data with Astrid (Data Analyst)
  2. 13:00Plot it over time with Astrid (Data Analyst)
  3. 16:00Review with Augustin (Black Belt)

Situation 1 of 3

09:00 · First look at the waiting data with Astrid (Data Analyst)
Astrid (Data Analyst)
The average wait for a routine appointment is 10 days. But some patients get one in 2 days and some wait 25.

What matters most?

Customers feel variation, not averages. Look at the spread as well as the middle.

Situation 2 of 3

13:00 · Plot it over time with Astrid (Data Analyst)
Astrid (Data Analyst)
Here are 20 weeks of daily figures. Where do I start?

What do you do first?

Plot data over time before you analyse it.
Used here Run chart
Worked example 1

Reading a run chart

Astrid (Data Analyst) plots the median wait for each of the last 20 weeks and adds the median of all 20 as a centre line.

Median wait for a routine appointment, by week, with the overall median05101520Median 9Wk 1: 8Wk 2: 9Wk 3: 8Wk 4: 7Wk 5: 9Wk 6: 8Wk 7: 9Wk 8: 8Wk 9: 8Wk 10: 9Wk 11: 8Wk 12: 10Wk 13: 10Wk 14: 11Wk 15: 11Wk 16: 12Wk 17: 12Wk 18: 13Wk 19: 12Wk 20: 13Wk 1Wk 3Wk 5Wk 7Wk 9Wk 11Wk 13Wk 15Wk 17Wk 19
WeekMedian wait (days)
Wk 18
Wk 29
Wk 38
Wk 47
Wk 59
Wk 68
Wk 79
Wk 88
Wk 98
Wk 109
Wk 118
Wk 1210
Wk 1310
Wk 1411
Wk 1511
Wk 1612
Wk 1712
Wk 1813
Wk 1912
Wk 2013
Download the data (spreadsheet file)
  1. Centre lineSort the 20 values; the median is the middle (10th and 11th values)= 9 days
  2. Mark each pointAbove, below or on the median; ignore points on it= 16 useful points
  3. Look for a shift6 or more points in a row on one side is a signal= weeks 12 to 20: 9 in a row above
  4. Count the runsA run is a series on the same side of the median= 2 runs
  5. Check the number of runsWith 16 useful points, fewer than 5 runs is very unlikely by chance= 2 is a signal
What it meansThe waits didn't just have a few bad weeks: from week 12 the process shifted upwards and stayed there. Something changed around week 12.
What Amara decidesAsk what changed around week 12 and note it for the Analyse phase. Don't react to single bad days; react to signals like this one.
Try it yourself in a spreadsheet
Median=MEDIAN(B2:B21)
Above or below=IF(B2>$D$1,"Above",IF(B2<$D$1,"Below","On"))
ChartInsert a line chart of column B, then add the median as a second series

How many points in a row on one side of the median count as a shift, and which weeks show one here?

Show the answer

6 or more. Weeks 12 to 20 are 9 points in a row above the median.

Situation 3 of 3

16:00 · Review with Augustin (Black Belt)
Augustin (Black Belt)mentor
The doctors want to react every time a day looks bad. Last week they cancelled training after one bad Monday.

What do you advise?

Everyday variation needs a process change; unusual events need investigating. Don't react to every dip.
Used here Run chart

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Customers feel variation

  • An average hides the spread. A wait that averages ten days but often reaches twenty-five is not a ten-day process for the people waiting twenty-five.
  • Improvement aims to move the average to where it should be and to make results consistent.
Common practice

Plot it over time first

  • Before calculating anything, put the data in time order on a chart with a centre line.
  • Trends, sudden shifts and repeating patterns become visible; a single number would hide them.

Where you will meet this: Run chart

Concept

Two kinds of variation

  • Everyday variation comes from how the process is set up. It is always there, and only changing the process reduces it.
  • Unusual variation has a specific cause, such as a broken phone line, and should be investigated. Reacting to everyday ups and downs as if they were unusual makes things worse.

Where you will meet this: Common-cause and special-cause variation · tampering

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 6 complete

3 situations today.

Your responsibility todayUnderstanding variation
Technique you usedRun chart, everyday versus unusual variation
Key points to remember
  • Customers feel variation, not averages. Look at the spread as well as the middle.
  • Plot data over time before you analyse it.
  • Everyday variation needs a process change; unusual events need investigating. Don't react to every dip.