Day 47 of 55Stage 5 · ControlTuesdayXbar-R chart with Astrid (Data Analyst)

Choosing the right chart

Control charts tell normal variation from real signals. But which chart? It depends on the data. Amara starts with daily samples of waiting times.

Stage goal: Make the gains last and hand the process back.
Team
Astrid (Data Analyst)
How the day goes
  1. 09:00Data for control charts with Astrid (Data Analyst)
  2. 11:00Xbar-R chart with Astrid (Data Analyst)
  3. 15:00Investigate day 14

Situation 1 of 2

09:00 · Data for control charts with Astrid (Data Analyst)
Astrid (Data Analyst)
We could chart every single request, or take a few each day. What's best?

How do you collect data for the chart?

Collect data in rational subgroups: small samples taken under the same conditions, so differences between subgroups show real changes.

Situation 2 of 2

11:00 · Xbar-R chart with Astrid (Data Analyst)
Astrid (Data Analyst)
Day 14 is above the upper limit. Everything else is inside.

What do you do?

A point outside the limits is a special cause: investigate it, act on the cause, and don't change the process for normal variation.
Used here Xbar-R chart
Worked example 1

Xbar-R chart of waiting times

Every day after roll-out, Astrid (Data Analyst) picks 5 new routine requests at random and records each wait. Each day is one subgroup.

Xbar chart: daily average of 5 waits02468CLUCLLCLDay 1: 4.4Day 2: 3.4Day 3: 4.8Day 4: 4.8Day 5: 4.4Day 6: 3.4Day 7: 3.8Day 8: 4.4Day 9: 4Day 10: 4.6Day 11: 3.8Day 12: 4.4Day 13: 5Day 14: 7.2 (outside the limits)Day 15: 5.4Day 16: 3.4Day 17: 5.4Day 18: 3.4Day 19: 3.8Day 20: 4.6Day 1Day 4Day 7Day 10Day 13Day 16Day 19Average wait (days)R chart: daily range of 5 waits02.557.51012.5CLUCLDay 1: 6Day 2: 2Day 3: 6Day 4: 8Day 5: 4Day 6: 4Day 7: 4Day 8: 3Day 9: 3Day 10: 6Day 11: 2Day 12: 5Day 13: 2Day 14: 4Day 15: 7Day 16: 4Day 17: 8Day 18: 4Day 19: 5Day 20: 2Day 1Day 4Day 7Day 10Day 13Day 16Day 19Range (days)
DayWait 1Wait 2Wait 3Wait 4Wait 5AverageRange
Day 1348524.46
Day 2434243.42
Day 3485524.86
Day 41026334.88
Day 5335474.44
Day 6243623.44
Day 7342643.84
Day 8663344.43
Day 95633343
Day 10344934.66
Day 11453343.82
Day 12627344.45
Day 136564452
Day 14879757.24
Day 15942935.47
Day 16634223.44
Day 173461135.48
Day 18634223.44
Day 19324373.85
Day 20446544.62
Download the data (spreadsheet file)
  1. Subgroup averages and rangesfor each day: average of the 5 waits, and largest − smallest
  2. Centre linesaverage of the 20 averages; average of the 20 ranges= 4.42 days; 4.45 days
  3. Xbar limits4.42 ± A2 × R̄ = 4.42 ± 0.577 × 4.45 (A2 for subgroups of 5)= 1.85 to 6.99
  4. R limitsD3 × R̄ to D4 × R̄ = 0 to 2.114 × 4.45= 0 to 9.41
  5. Read the R chart firstall ranges inside: the spread within days is stable
  6. Read the Xbar chartday 14 (7.2) is above the upper limit= a signal
  7. After investigatingday 14: a doctor off sick, no cover; remove it and recalculate= centre 4.27, upper limit 6.86
What it meansThe new process is stable: apart from day 14, every day's average and range sits inside the limits. 91% of the 100 waits are 7 days or less: the 90% goal is met.
What Amara decidesDay 14 has a known special cause. The response plan adds: when a doctor is off at short notice, use the cover list the same day. The chart continues with the recalculated limits.
Try it yourself in a spreadsheet
Average and range=AVERAGE(B2:F2) and =MAX(B2:F2)-MIN(B2:F2)
Limits=AVERAGE(G2:G21)+0.577*AVERAGE(H2:H21), and minus for the lower
Chartline chart of the averages, with three extra series for the centre line and limits

Why read the R chart before the Xbar chart?

Show the answer

The Xbar limits are calculated from the average range. If the ranges aren't stable, the Xbar limits are wrong.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

What control charts do

  • They separate everyday (common-cause) variation from signals of real change (special causes), so people react only when something has changed.

Where you will meet this: Statistical process control (SPC)

Common practice

Rational subgroups

  • Take small samples under the same conditions at regular intervals. Variation inside a subgroup is everyday noise; differences between subgroups show change.

Where you will meet this: Data collection for SPC

Common practice

Choosing the chart

  • Measured data: one value a period, I-MR; subgroups of 2 to 9, Xbar-R; 10 or more, Xbar-S. Yes or no: P (varying n) or NP (fixed n). Defect counts: U (varying) or C (fixed). Small shifts: CUSUM or EWMA.

Where you will meet this: Control chart selection

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 47 complete

2 situations today.

Your responsibility todayMonitoring a process
Technique you usedRational subgroups, Xbar-R chart
Key points to remember
  • Collect data in rational subgroups: small samples taken under the same conditions, so differences between subgroups show real changes.
  • A point outside the limits is a special cause: investigate it, act on the cause, and don't change the process for normal variation.