Day 25 of 55Stage 3 · AnalyseFridayFMEA

What could go wrong?

Amara and the team go step by step through the booking process, asking how each step could fail, how badly, how often, and whether anyone would notice.

Stage goal: Find and prove the root causes.
Team
Ayumi (Healthcare Assistant) Alma (Reception Team Lead)
Techniques today FMEA
Documents today FMEA worksheet
How the day goes
  1. 09:00List failure modes with the team
  2. 11:00Score them with the team
  3. 15:00Decide which to prove

Situation 1 of 2

09:00 · List failure modes with the team
Ayumi (Healthcare Assistant)
Do we list every possible failure, or just the ones we know about?

How do you build the list?

Build an FMEA step by step along the process map: failure, effect, cause, current control.

Situation 2 of 2

11:00 · Score them with the team
Alma (Reception Team Lead)
Urgent cases in routine slots: severity 6, it happens often (6), and nobody tracks it (7). That's 252. Higher than anything else.

What does the high detection score tell you?

Risk priority = severity × occurrence × detection. A failure nobody notices is a risk in itself.
Worked example 1

Ranking failure modes by risk

The team lists how the booking process can fail, then scores each failure for severity, how often it happens (occurrence) and how likely it is to go unnoticed (detection), each from 1 to 10.

Risk priority number for each failure mode0100200300400Urgent in / routine: 252252Urgent inroutineCan't get / through: 168168Can't getthroughMissed / appt: 168168MissedapptRota / late: 168168RotalateWrong / type: 6060WrongtypeSession / cancelled: 4848Sessioncancelled
Failure modeEffect on the patientSeverityOccurrenceDetectionRisk priority number
Urgent case booked into a routine slotRoutine capacity lost; others wait longer667252
Patient can't get through at 8 amTold to call back; wait grows783168
Patient misses the appointmentSlot wasted; patient rebooks674168
Rota released lateFewer slots to offer746168
Wrong appointment type bookedPatient rebooked43560
Session cancelled at short noticePatients rebooked83248
Download the data (spreadsheet file)
  1. Severityhow bad the effect is for the patient: 1 none, 10 dangerous
  2. Occurrencehow often the cause happens: 1 almost never, 10 constantly
  3. Detectionhow likely it goes unnoticed before harm: 1 always caught, 10 never
  4. Risk priority numberseverity × occurrence × detection: 6 × 6 × 7= 252
  5. Sort and acthighest first, and anything with severity 9 or 10 regardless= urgent cases in routine slots first
What it meansUrgent cases quietly taking routine slots is the biggest risk: frequent, and nobody tracks it. Three other failure modes tie at 168.
What Amara decidesAdd “urgent use of routine slots” to the root causes to prove with data, and plan actions for every failure mode above 150.
Try it yourself in a spreadsheet
Risk priority number=C2*D2*E2
Sort by risk=SORT(A2:F7,6,FALSE)

If a simple daily count made urgent use of routine slots easy to spot (detection 2), what would its risk priority number become?

Show the answer

6 × 6 × 2 = 72. Better detection alone moves it from first to near the bottom, though the failure still happens.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

Failure modes and effects

  • For each step: how could it fail, what would the effect be, why would it happen, and how is it caught today?
  • Built step by step along the process map, with the people who do the work.

Where you will meet this: FMEA

Common practice

Three scores

  • Severity (how bad), occurrence (how often) and detection (how likely it goes unnoticed), each 1 to 10. Multiplied, they give the risk priority number.
  • Very severe failures need action whatever their total.

Where you will meet this: Risk priority number (RPN)

Concept

Invisible failures

  • A failure nobody notices keeps happening. Making it visible, by counting or checking it, is often the cheapest first fix.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 25 complete

2 situations today.

Your responsibility todayRanking risks in the process
Technique you usedFailure modes and effects analysis
Key points to remember
  • Build an FMEA step by step along the process map: failure, effect, cause, current control.
  • Risk priority = severity × occurrence × detection. A failure nobody notices is a risk in itself.
Techniques today FMEA
Documents today FMEA worksheet