Day 52 of 55Stage 5 · ControlTuesdayCUSUM and EWMA

A slow drift

Eight weeks in, waits are creeping up, but no single day breaks the limits. Amara uses charts that add up small differences over time.

Stage goal: Make the gains last and hand the process back.
Team
Astrid (Data Analyst)
Stakeholders
Aurelie (Practice Nurse Manager)
Documents today Control plan
How the day goes
  1. 09:00Look at the trend with Astrid (Data Analyst)
  2. 11:00EWMA and CUSUM
  3. 15:00Act with Aurelie (Practice Nurse Manager)

Situation 1 of 2

09:00 · Look at the trend with Astrid (Data Analyst)
Astrid (Data Analyst)
The I-MR chart shows nothing outside the limits, but my gut says waits are creeping up.

How do you check?

To catch small, sustained shifts early, use CUSUM or EWMA charts.

Situation 2 of 2

15:00 · Act with Aurelie (Practice Nurse Manager)
Aurelie (Practice Nurse Manager)process owner
The locum has been cancelling some sessions. I didn't know.

What happens now?

When a chart signals, follow the response plan and strengthen the control plan if a new risk appears.
Used here Control plan
Worked example 1

Catching a small drift: EWMA and CUSUM

After week 8 of roll-out, the locum covering two sessions starts cancelling some of them. The daily average wait creeps up by about half a day. Target 4.2 days, standard deviation 0.55.

Individuals chart: no point outside the limits02468CLUCLLCLDay 1: 4.3Day 2: 4.1Day 3: 4.6Day 4: 4.3Day 5: 3.9Day 6: 4.4Day 7: 4.9Day 8: 4.7Day 9: 3.8Day 10: 3.5Day 11: 3.9Day 12: 4.2Day 13: 2.9Day 14: 4.1Day 15: 3.5Day 16: 4.3Day 17: 4.5Day 18: 4.6Day 19: 5Day 20: 5.3Day 21: 4.7Day 22: 5.5Day 23: 4.4Day 24: 4.9Day 25: 5.2Day 26: 4.8Day 27: 4.3Day 28: 4.2Day 29: 4.5Day 30: 4.9Day 1Day 5Day 9Day 13Day 17Day 21Day 25Day 29Daily average waitEWMA chart: crosses its limit on day 2502468CLUCLDay 1: 4.22Day 2: 4.2Day 3: 4.28Day 4: 4.28Day 5: 4.21Day 6: 4.24Day 7: 4.38Day 8: 4.44Day 9: 4.31Day 10: 4.15Day 11: 4.1Day 12: 4.12Day 13: 3.88Day 14: 3.92Day 15: 3.84Day 16: 3.93Day 17: 4.04Day 18: 4.15Day 19: 4.32Day 20: 4.52Day 21: 4.56Day 22: 4.74Day 23: 4.68Day 24: 4.72Day 25: 4.82 (outside the limits)Day 26: 4.81 (outside the limits)Day 27: 4.71Day 28: 4.61Day 29: 4.59Day 30: 4.65Day 1Day 5Day 9Day 13Day 17Day 21Day 25Day 29EWMA
DayDaily average waitEWMAEWMA upper limitCUSUM
Day 14.34.224.530
Day 24.14.24.620
Day 34.64.284.670.12
Day 44.34.284.70
Day 53.94.214.720
Day 64.44.244.730
Day 74.94.384.740.43
Day 84.74.444.740.65
Day 93.84.314.750
Day 103.54.154.750
Day 113.94.14.750
Day 124.24.124.750
Day 132.93.884.750
Day 144.13.924.750
Day 153.53.844.750
Day 164.33.934.750
Day 174.54.044.750.02
Day 184.64.154.750.15
Day 1954.324.750.67
Day 205.34.524.751.5
Day 214.74.564.751.72
Day 225.54.744.752.75
Day 234.44.684.752.67
Day 244.94.724.753.1
Day 255.24.824.753.82
Day 264.84.814.754.15
Day 274.34.714.753.97
Day 284.24.614.753.7
Day 294.54.594.753.72
Day 304.94.654.754.15
Download the data (spreadsheet file)
  1. Individuals chartlimits 4.2 ± 3 × 0.55 = 2.55 to 5.85= no signal at all
  2. EWMAeach day: 0.2 × today + 0.8 × yesterday's EWMA, starting at 4.2
  3. EWMA limit4.2 + 3 × 0.55 × √(0.2 ÷ 1.8 × (1 − 0.8^(2 × day)))= 4.75 after a few days
  4. EWMA signalday 25: 4.82 above 4.75
  5. CUSUMeach day: add (today − 4.2 − 0.275) to the running total, never below 0= reference k = 0.5 × σ
  6. CUSUM signaltotal above h = 4 × 0.55 = 2.2= day 22
What it meansThe individuals chart never signals, because each day is still inside its limits. EWMA and CUSUM add up small differences over time and catch the drift within about 7 to 10 days of it starting.
What Amara decidesAurelie (Practice Nurse Manager) finds the cancelled locum sessions and books a second locum. Add a CUSUM on the daily average wait to the control plan.
Try it yourself in a spreadsheet
EWMA=0.2*B3+0.8*C2 (C2 starts at 4.2)
EWMA limit=4.2+3*0.55*SQRT(0.2/1.8*(1-0.8^(2*ROW()-2)))
CUSUM=MAX(0,E2+B3-4.2-0.275)

Why not just use a more sensitive individuals chart with limits at 2 standard deviations?

Show the answer

Tighter limits give many more false alarms on normal days. EWMA and CUSUM detect small sustained shifts without that cost.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

CUSUM

  • Adds up each value's distance from the target, minus an allowance k (often half a standard deviation). Signals when the sum passes h (often 4 or 5 standard deviations).

Where you will meet this: Cumulative sum (CUSUM) chart

Common practice

EWMA

  • A weighted average: λ × today + (1 − λ) × yesterday's EWMA, with λ often 0.2. Smooths noise and shows small shifts.

Where you will meet this: Exponentially weighted moving average (EWMA) chart

Concept

Use them together

  • Standard charts catch big sudden changes quickly; CUSUM and EWMA catch small sustained ones. Many control plans use both.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 52 complete

2 situations today.

Your responsibility todayDetecting small changes early
Technique you usedCUSUM, EWMA
Key points to remember
  • To catch small, sustained shifts early, use CUSUM or EWMA charts.
  • When a chart signals, follow the response plan and strengthen the control plan if a new risk appears.
Documents today Control plan