Day 54 of 55Stage 5 · ControlThursdayHandover and benefits

Handing over

The process belongs to Aurelie (Practice Nurse Manager) now. And finance needs to confirm the money.

Stage goal: Make the gains last and hand the process back.
Stakeholders
Aurelie (Practice Nurse Manager) Abigail (Finance Business Partner)
How the day goes
  1. 09:00Handover with Aurelie (Practice Nurse Manager)
  2. 11:00Benefits with Abigail (Finance Business Partner)
  3. 15:00Sign-off

Situation 1 of 2

09:00 · Handover with Aurelie (Practice Nurse Manager)
Aurelie (Practice Nurse Manager)process owner
What exactly am I taking on?

What does a good handover include?

Hand over the process to its owner with the control plan, standard work, owners for each measure, and a review date.
Used here Control plan

Situation 2 of 2

11:00 · Benefits with Abigail (Finance Business Partner)
Abigail (Finance Business Partner)
Your charter promised about €35,000 a year. What did you actually achieve?

How do you confirm the benefits?

Confirm benefits with finance using actual data and the method agreed at the start, including the project's costs.
Worked example 1

Confirming the benefits with finance

Three months after roll-out, Abigail (Finance Business Partner) and Amara compare the actual figures with the estimate in the charter.

Confirmed benefit a year, by source05,00010,00015,00020,000Missed / appts: €14,100€14,100MissedapptsRepeat / calls: €10,125€10,125RepeatcallsEmergency / visits: €12,480€12,480Emergencyvisits
LineBeforeAfterBenefit a year (€)
Missed appointments15.7%8.3%14100
Repeat calls11,250 a year2,810 a year10125
Emergency visits for routine care208 a year104 a year12480
Download the data (spreadsheet file)
  1. Missed appointments12,700 × (15.7% − 8.3%) = 940 fewer × €15= €14,100
  2. Repeat calls75% fewer: 8,437 × €1.20= €10,125
  3. Emergency visits104 fewer × €120 (avoided cost for the health system)= €12,480
  4. Total€14,100 + €10,125 + €12,480= €36,705 a year
  5. One-off project coststeam time €14,000 + system changes €3,000 + training €1,500= €18,500
  6. Payback on the clinic's own savings€18,500 ÷ (€14,100 + €10,125) × 12 months= about 9 months
What it meansThe project is worth about €36,700 a year, slightly more than the €35,300 estimated. On the clinic's own savings alone, it pays back in about 9 months. Covering the lost sessions costs nothing extra: they were already in the budget.
What Amara decidesAbigail (Finance Business Partner) signs off the benefits. They will be checked again at 12 months.
Try it yourself in a spreadsheet
Missed appointments=12700*(0.157-0.083)*15
Total=SUM(D2:D4)
Payback in months=18500/(D2+D3)*12

If missed appointments had only fallen to 10%, what would the payback be?

Show the answer

12,700 × 5.7% × €15 = €10,859; with €10,125 that's €20,984 a year of clinic savings; €18,500 ÷ €20,984 × 12 = about 10.6 months.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

Handover to the process owner

  • The owner takes the control plan, charts, response plan, standard work and open actions, signs for them, and agrees a review date with the project leader.
Common practice

Benefits confirmed

  • Measure each benefit line with the method agreed in Define, subtract the project's costs, and let finance sign off. Check again later, often at 12 months.

Where you will meet this: Cost-benefit analysis · benefits realisation

Concept

Cash and avoided cost

  • Separate savings the organisation can spend from avoided costs elsewhere (here, emergency visits). Both are real; they're reported differently.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 54 complete

2 situations today.

Your responsibility todayHanding over and confirming benefits
Technique you usedHandover, cost-benefit analysis
Key points to remember
  • Hand over the process to its owner with the control plan, standard work, owners for each measure, and a review date.
  • Confirm benefits with finance using actual data and the method agreed at the start, including the project's costs.