Handing over
The process belongs to Aurelie (Practice Nurse Manager) now. And finance needs to confirm the money.
- 09:00Handover with Aurelie (Practice Nurse Manager)
- 11:00Benefits with Abigail (Finance Business Partner)
- 15:00Sign-off
Situation 1 of 2
09:00 · Handover with Aurelie (Practice Nurse Manager)What does a good handover include?
Situation 2 of 2
11:00 · Benefits with Abigail (Finance Business Partner)How do you confirm the benefits?
Confirming the benefits with finance
Three months after roll-out, Abigail (Finance Business Partner) and Amara compare the actual figures with the estimate in the charter.
| Line | Before | After | Benefit a year (€) |
|---|---|---|---|
| Missed appointments | 15.7% | 8.3% | 14100 |
| Repeat calls | 11,250 a year | 2,810 a year | 10125 |
| Emergency visits for routine care | 208 a year | 104 a year | 12480 |
- Missed appointments
12,700 × (15.7% − 8.3%) = 940 fewer × €15= €14,100 - Repeat calls
75% fewer: 8,437 × €1.20= €10,125 - Emergency visits
104 fewer × €120 (avoided cost for the health system)= €12,480 - Total
€14,100 + €10,125 + €12,480= €36,705 a year - One-off project costs
team time €14,000 + system changes €3,000 + training €1,500= €18,500 - Payback on the clinic's own savings
€18,500 ÷ (€14,100 + €10,125) × 12 months= about 9 months
Try it yourself in a spreadsheet
| Missed appointments | =12700*(0.157-0.083)*15 |
| Total | =SUM(D2:D4) |
| Payback in months | =18500/(D2+D3)*12 |
If missed appointments had only fallen to 10%, what would the payback be?
Show the answer
12,700 × 5.7% × €15 = €10,859; with €10,125 that's €20,984 a year of clinic savings; €18,500 ÷ €20,984 × 12 = about 10.6 months.
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Handover to the process owner
- The owner takes the control plan, charts, response plan, standard work and open actions, signs for them, and agrees a review date with the project leader.
Benefits confirmed
- Measure each benefit line with the method agreed in Define, subtract the project's costs, and let finance sign off. Check again later, often at 12 months.
Where you will meet this: Cost-benefit analysis · benefits realisation
Cash and avoided cost
- Separate savings the organisation can spend from avoided costs elsewhere (here, emergency visits). Both are real; they're reported differently.
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 54 complete
2 situations today.
- Hand over the process to its owner with the control plan, standard work, owners for each measure, and a review date.
- Confirm benefits with finance using actual data and the method agreed at the start, including the project's costs.