Where does the time go?
The map shows the steps. Now Amara adds the time: how long each step takes, and how long requests wait in between.
- 09:00Time each step with Astrid (Data Analyst)
- 11:00Draw the value stream
- 14:00The 8 o'clock rush with Alma (Reception Team Lead)
Situation 1 of 2
09:00 · Time each step with Astrid (Data Analyst)What do you add to the map?
Situation 2 of 2
14:00 · The 8 o'clock rush with Alma (Reception Team Lead)How do you check whether reception can keep up?
Lead time, value-added time and takt time
Astrid (Data Analyst) times each step of a routine request from the value stream, using the averages from the booking data.
| Step | Working time (min) | Waiting before next step (days) |
|---|---|---|
| Phone queue | 0 | 0.01 |
| Call and triage | 4 | 0 |
| Check the rota | 3 | 0 |
| Told to call back: the loop | 0 | 2.1 |
| Book the appointment | 2 | 0 |
| Wait for the appointment date | 0 | 8.3 |
| Consultation | 10 | 0 |
- Total working time
4 + 3 + 2 + 10 minutes= 19 minutes - Lead time
about 12 minutes in the queue + 2.1 days + 8.3 days= about 10.4 days - Value-added time
only the consultation changes something the patient cares about= 10 minutes - Process cycle efficiency
10 minutes ÷ (10.4 days × 1,440 minutes a day)= about 0.07% - Takt time at 8 o'clock
3 receptionists × 90 minutes = 270 minutes ÷ 48 requests= 5.6 minutes per request per receptionist - Compare with cycle time
each call takes 4 + 3 + 2 minutes= 9 minutes, slower than takt
Try it yourself in a spreadsheet
| Lead time in days | =0.01+2.1+8.3 |
| Efficiency | =10/(C9*1440) (C9 = lead time in days) |
| Takt time | =(3*90)/48 |
If a fourth receptionist joined for the 8 o'clock rush, what would the takt time per receptionist be, and could they keep up?
Show the answer
4 × 90 = 360 minutes ÷ 48 = 7.5 minutes per request. Still faster than the 9-minute call, so a queue would still build, just more slowly.
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Lead time and value-added time
- Lead time is everything the customer waits for, from request to result. Value-added time is the part that actually helps them.
- Process cycle efficiency = value-added time ÷ lead time. In services it is often below 1%.
Where you will meet this: Value stream map (VSM) · process cycle efficiency
Cycle time
- Cycle time is how long one step takes to handle one item. If a step's cycle time is longer than the pace demand needs, a queue builds in front of it.
Takt time
- Takt time = available working time ÷ customer demand. It's the pace the process must keep to meet demand.
- Comparing takt time with cycle time shows where capacity can't keep up.
Where you will meet this: Takt time (Lean)
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 15 complete
2 situations today.
- A value stream shows working time and waiting time step by step. The gap between them is the opportunity.
- Compare the pace customers demand (takt time) with the time the work takes. If the work is slower, queues are guaranteed.