Precision machining31 questions5 phases
Precitec: a Process Improvement Specialist case study
Precitec grinds 180,000 steel shafts a year for a pump maker, to 25.00 ± 0.05 mm. 2.1% are scrapped, and the customer has just rejected two batches. You're the Green Belt asked to make the process capable.
What this case study tests
Multi-variANOVA and LeveneCpkXbar-R and CUSUM
You're the Process Improvement Specialist. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.
Team
Aleksander (Process Improvement Specialist)You: the Green Belt leading the project
Aurelio (Quality Engineer)Measurement and quality data
Arnold (CNC Operator)Runs machines A to C
Stakeholders
Adriana (Plant Director)Sponsor
Ahmet (Machining Supervisor)Process owner
Andrea (Cost Accountant)The money
Avery (Black Belt)Your mentor
Precitec
Define
Shafts that don't fit
Question 1 of 31
Choose 1Adriana (Plant Director)
Our pump customer rejected two batches of shafts last month. 2.1% of shafts are scrapped.
Which problem statement is best?
Learn it on Day 7: A problem, not a solutionQuestion 2 of 31
Choose 1Ahmet (Machining Supervisor)
Shafts go through turning, heat treatment and grinding.
Question 3 of 31
Choose 1Aurelio (Quality Engineer)
The customer's drawing says 25.00 ± 0.05 mm, and they want Cpk of at least 1.33.
Question 4 of 31
Choose 1Aurelio (Quality Engineer)
2.1% scrapped.
What is the baseline sigma level?
Learn it on Day 22: How capable is the process?Question 5 of 31
Choose 1Andrea (Cost Accountant)
What does it cost?
180,000 shafts a year, 2.1% scrapped at €14 each, plus half a person sorting at €24,000. Yearly cost?
Learn it on Day 5: Which problem first?Question 6 of 31
Choose 1Ahmet (Machining Supervisor)
Who's on it?
Question 7 of 31
Choose 1Adriana (Plant Director)
Sign, with “replace machine C” as the deliverable?
Precitec
Measure
A micrometer you can trust
Question 8 of 31
Choose 1Arnold (CNC Operator)
Load, grind, measure with a hand micrometer, unload; settings adjusted by feel when parts drift.
Question 9 of 31
Choose 1Aurelio (Quality Engineer)
Diameter: where on the shaft? How many?
What's the data plan?
Learn it on Day 17: What exactly do we count?Question 10 of 31
Choose 1Avery (Black Belt)
Gauge study on the hand micrometer: 22% of total variation. On the digital micrometer in a stand: 7%.
Question 11 of 31
Choose 1Aurelio (Quality Engineer)
Download the data
45 shafts, 15 per machine.
| Shaft | Machine | Diameter (mm) |
|---|---|---|
| S01 | A | 25.003 |
| S02 | A | 25.001 |
| S03 | A | 25.008 |
| S04 | A | 25.003 |
| S05 | A | 24.997 |
| S06 | A | 25.006 |
| S07 | A | 25.015 |
| S08 | A | 25.011 |
| S09 | A | 24.995 |
| S10 | A | 24.989 |
| S11 | A | 24.996 |
| S12 | A | 25.002 |
| S13 | A | 24.979 |
| S14 | A | 25 |
| S15 | A | 24.99 |
| S16 | B | 25.016 |
| S17 | B | 25.018 |
| S18 | B | 25.021 |
| S19 | B | 25.029 |
| S20 | B | 25.035 |
| S21 | B | 25.023 |
| S22 | B | 25.039 |
| S23 | B | 25.017 |
| S24 | B | 25.028 |
| S25 | B | 25.034 |
| S26 | B | 25.025 |
| S27 | B | 25.016 |
| S28 | B | 25.014 |
| S29 | B | 25.019 |
| S30 | B | 25.026 |
| S31 | C | 24.976 |
| S32 | C | 24.993 |
| S33 | C | 24.994 |
| S34 | C | 25.01 |
| S35 | C | 25.003 |
| S36 | C | 25.006 |
| S37 | C | 24.984 |
| S38 | C | 24.995 |
| S39 | C | 25.015 |
| S40 | C | 25.031 |
| S41 | C | 24.97 |
| S42 | C | 25.031 |
| S43 | C | 25.028 |
| S44 | C | 25.015 |
| S45 | C | 25.004 |
How do you describe them?
Learn it on Day 20: The baseline in numbersQuestion 12 of 31
Choose 1Aurelio (Quality Engineer)
Download the data
Limits 24.95 to 25.05; mean 25.009, standard deviation 0.0166.
| Shaft | Machine | Diameter (mm) |
|---|---|---|
| S01 | A | 25.003 |
| S02 | A | 25.001 |
| S03 | A | 25.008 |
| S04 | A | 25.003 |
| S05 | A | 24.997 |
| S06 | A | 25.006 |
| S07 | A | 25.015 |
| S08 | A | 25.011 |
| S09 | A | 24.995 |
| S10 | A | 24.989 |
| S11 | A | 24.996 |
| S12 | A | 25.002 |
| S13 | A | 24.979 |
| S14 | A | 25 |
| S15 | A | 24.99 |
| S16 | B | 25.016 |
| S17 | B | 25.018 |
| S18 | B | 25.021 |
| S19 | B | 25.029 |
| S20 | B | 25.035 |
| S21 | B | 25.023 |
| S22 | B | 25.039 |
| S23 | B | 25.017 |
| S24 | B | 25.028 |
| S25 | B | 25.034 |
| S26 | B | 25.025 |
| S27 | B | 25.016 |
| S28 | B | 25.014 |
| S29 | B | 25.019 |
| S30 | B | 25.026 |
| S31 | C | 24.976 |
| S32 | C | 24.993 |
| S33 | C | 24.994 |
| S34 | C | 25.01 |
| S35 | C | 25.003 |
| S36 | C | 25.006 |
| S37 | C | 24.984 |
| S38 | C | 24.995 |
| S39 | C | 25.015 |
| S40 | C | 25.031 |
| S41 | C | 24.97 |
| S42 | C | 25.031 |
| S43 | C | 25.028 |
| S44 | C | 25.015 |
| S45 | C | 25.004 |
Question 13 of 31
Choose 1Adriana (Plant Director)
Ready?
Precitec
Analyse
Three machines, two problems
Question 14 of 31
Choose 1Aurelio (Quality Engineer)
Download the data
Where does the variation come from: within a shaft, shaft to shaft, between machines, over time?
| Family | Size of variation (mm) |
|---|---|
| Within one shaft (taper, end to end) | 0.004 |
| Shaft to shaft on one machine (standard deviation) | 0.008 to 0.019 |
| Between machines (range of averages) | 0.024 |
| Hour to hour (drift) | 0.006 |
What does the multi-vari show?
Learn it on Day 26: Where does the variation come from?Question 15 of 31
Choose 1Aurelio (Quality Engineer)
Machine running hot: severity 7, occurrence 6, detection 5. Worn wheel: severity 6, occurrence 3, detection 4.
Question 16 of 31
Choose 1Aurelio (Quality Engineer)
Download the data
Diameters by machine: A 24.9997, B 25.0240, C 25.0037 mm (standard deviations 0.009, 0.008, 0.019).
| Shaft | Machine | Diameter (mm) |
|---|---|---|
| S01 | A | 25.003 |
| S02 | A | 25.001 |
| S03 | A | 25.008 |
| S04 | A | 25.003 |
| S05 | A | 24.997 |
| S06 | A | 25.006 |
| S07 | A | 25.015 |
| S08 | A | 25.011 |
| S09 | A | 24.995 |
| S10 | A | 24.989 |
| S11 | A | 24.996 |
| S12 | A | 25.002 |
| S13 | A | 24.979 |
| S14 | A | 25 |
| S15 | A | 24.99 |
| S16 | B | 25.016 |
| S17 | B | 25.018 |
| S18 | B | 25.021 |
| S19 | B | 25.029 |
| S20 | B | 25.035 |
| S21 | B | 25.023 |
| S22 | B | 25.039 |
| S23 | B | 25.017 |
| S24 | B | 25.028 |
| S25 | B | 25.034 |
| S26 | B | 25.025 |
| S27 | B | 25.016 |
| S28 | B | 25.014 |
| S29 | B | 25.019 |
| S30 | B | 25.026 |
| S31 | C | 24.976 |
| S32 | C | 24.993 |
| S33 | C | 24.994 |
| S34 | C | 25.01 |
| S35 | C | 25.003 |
| S36 | C | 25.006 |
| S37 | C | 24.984 |
| S38 | C | 24.995 |
| S39 | C | 25.015 |
| S40 | C | 25.031 |
| S41 | C | 24.97 |
| S42 | C | 25.031 |
| S43 | C | 25.028 |
| S44 | C | 25.015 |
| S45 | C | 25.004 |
Question 17 of 31
Choose 1Avery (Black Belt)
Which causes are proven?
Which list is right?
Learn it on Day 36: The Analyse reviewQuestion 18 of 31
Choose 1Adriana (Plant Director)
Ruled out?
Precitec
Improve
Cool, steady and centred
Question 19 of 31
Choose 1Arnold (CNC Operator)
Ideas: a chiller on machine B, new spindle bearings on C, an offset rule instead of adjusting by feel, a new grinder.
Question 20 of 31
Choose 1Aurelio (Quality Engineer)
Download the data
Machine B: coolant temperature and diameter over 14 runs.
| Run | Coolant temperature (°C) | Diameter (mm) |
|---|---|---|
| Run 1 | 26.9 | 25.005 |
| Run 2 | 21.8 | 24.995 |
| Run 3 | 18.6 | 24.989 |
| Run 4 | 18.2 | 24.989 |
| Run 5 | 29.4 | 25.017 |
| Run 6 | 30.8 | 25.022 |
| Run 7 | 26.5 | 25.008 |
| Run 8 | 28.2 | 25.018 |
| Run 9 | 25.6 | 25.004 |
| Run 10 | 31.1 | 25.02 |
| Run 11 | 29.4 | 25.019 |
| Run 12 | 18 | 24.99 |
| Run 13 | 30 | 25.013 |
| Run 14 | 18.5 | 24.987 |
How much would a chiller help?
Learn it on Day 38: How much difference would it make?Question 21 of 31
Choose 1Ahmet (Machining Supervisor)
Pilot: chiller on B, new bearings on C, offset rule; then 20 hours of 5 shafts.
Question 22 of 31
Choose 1Ahmet (Machining Supervisor)
Roll it out.
What's in the plan?
Learn it on Day 44: Rolling it outQuestion 23 of 31
Choose 1Adriana (Plant Director)
Why approve?
Precitec
Control
Catching wear before it costs
Question 24 of 31
Choose 1Aurelio (Quality Engineer)
Download the data
After roll-out: 5 shafts measured each hour for 20 hours.
| Hour | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| Hour 1 | 25.001 | 24.999 | 25.005 | 25.001 | 24.996 |
| Hour 2 | 25.003 | 25.01 | 25.008 | 24.994 | 24.99 |
| Hour 3 | 24.995 | 25 | 24.981 | 24.998 | 24.99 |
| Hour 4 | 24.994 | 24.996 | 24.997 | 25.003 | 25.008 |
| Hour 5 | 24.999 | 25.011 | 24.995 | 25.003 | 25.007 |
| Hour 6 | 25.001 | 24.994 | 24.993 | 24.996 | 25.002 |
| Hour 7 | 24.992 | 24.998 | 24.999 | 25.004 | 25.002 |
| Hour 8 | 25.003 | 24.995 | 24.999 | 25.006 | 25.012 |
| Hour 9 | 24.99 | 25.012 | 25.011 | 25.006 | 25.002 |
| Hour 10 | 24.997 | 25.012 | 25.016 | 25.014 | 25.011 |
| Hour 11 | 25.003 | 24.99 | 25 | 25.005 | 24.99 |
| Hour 12 | 25.003 | 25.003 | 25.006 | 24.991 | 24.995 |
| Hour 13 | 24.997 | 24.991 | 25.014 | 24.996 | 25.003 |
| Hour 14 | 24.998 | 25.013 | 25.011 | 25.005 | 24.982 |
| Hour 15 | 25 | 25.005 | 25.008 | 24.995 | 25.015 |
| Hour 16 | 24.989 | 24.995 | 25.007 | 25 | 25.016 |
| Hour 17 | 25.002 | 24.995 | 24.997 | 24.991 | 24.99 |
| Hour 18 | 25.005 | 25.005 | 25.01 | 24.994 | 25.014 |
| Hour 19 | 24.998 | 25.013 | 24.997 | 24.994 | 25.002 |
| Hour 20 | 25.008 | 25.001 | 24.995 | 24.989 | 24.989 |
Question 25 of 31
Choose 1Avery (Black Belt)
Download the data
The wheel wears slowly, pushing diameters up a few micrometres a day. Daily averages stay inside the Xbar chart's limits.
| Day | Daily average (mm) | Upper CUSUM |
|---|---|---|
| Day 1 | 25.0008 | 0 |
| Day 2 | 24.9979 | 0 |
| Day 3 | 24.9983 | 0 |
| Day 4 | 24.9902 | 0 |
| Day 5 | 25.0072 | 0.0052 |
| Day 6 | 25.0046 | 0.0078 |
| Day 7 | 24.9987 | 0.0045 |
| Day 8 | 25.0031 | 0.0056 |
| Day 9 | 25.0011 | 0.0047 |
| Day 10 | 24.9978 | 0.0005 |
| Day 11 | 25.0079 | 0.0064 |
| Day 12 | 25.0028 | 0.0072 |
| Day 13 | 25.0027 | 0.0079 |
| Day 14 | 25.0008 | 0.0067 |
| Day 15 | 25.0058 | 0.0105 |
| Day 16 | 25.0036 | 0.0121 |
| Day 17 | 25.0062 | 0.0163 |
| Day 18 | 25.0016 | 0.0159 |
| Day 19 | 25.0045 | 0.0184 |
| Day 20 | 25.0004 | 0.0168 |
Question 26 of 31
Choose 1Ahmet (Machining Supervisor)
How do we keep it?
Question 27 of 31
Choose 1Arnold (CNC Operator)
Operators could still adjust offsets by feel.
Question 28 of 31
Choose 1Ahmet (Machining Supervisor)
What am I taking on?
What's in the handover?
Learn it on Day 54: Handing overQuestion 29 of 31
Choose 1Andrea (Cost Accountant)
Scrap fell from 2.1% to 0.1%, and sorting was replaced by the charts.
Question 30 of 31
Choose 1Avery (Black Belt)
Final report?
What's in it?
Learn it on Day 55: Closing the projectQuestion 31 of 31
Choose 1Adriana (Plant Director)
Close it?