Checking how much of the variation in your data comes from the measuring itself (the tool, the method, the people), before trusting the data.
Common practice 6 steps Used by Process Improvement Specialist
What it is
Every measurement contains some error. Measurement system analysis finds out how much, and where it comes from: the method itself (repeatability) or differences between people (reproducibility).
It also covers accuracy: whether measurements are right on average (bias), whether that holds across the range (linearity) and over time (stability).
When to use it
Before using data to make decisions, especially when people measure or judge by hand.
Variations
Attribute agreement analysis The same idea for categories, such as pass or fail.
Bias study Measuring a known standard many times to see whether results are right on average.
Why it works
If the measuring adds a lot of variation, you can chase causes that are really measurement errors, or miss real changes.
Do
Choose items that differ as much as real ones do.
Hide the item labels so people can't remember their first result.
Don't
Skipping it because the tool is new or digital.
Testing items that are all alike, which hides the error.
Letting people see their earlier results.
Step by step
Pick itemsCovering the normal range, often 10.
Measure repeatedly2 or 3 people, 2 or 3 times each, blind, in random order.
RepeatabilitySpread within each person.
ReproducibilityDifferences between people.
Compare with total variationGauge share of total.
Judge against purposeUnder 10% good; 10 to 30% may be acceptable; over 30% fix it.
Filled in for: A café weighs coffee doses with a kitchen scale.
Item
Person A, 1
Person A, 2
Person B, 1
Person B, 2
Person C, 1
Person C, 2
Each person measures each item twice, without seeing earlier results. Repeatability = average range × 0.8862 · Reproducibility = √((difference in person averages × 0.5231)² − repeatability² ÷ (items × trials)) · Gauge share = gauge ÷ total
Before you use it: check these
Check
If it fails
Parts cover the real range of the process
Choose new parts; similar parts make the measurement look worse than it is
Repeats are blind and in random order
Repeat the study with hidden labels
How to do it with real data
The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Worked example with real data
Linearity: is the stopwatch equally accurate for short and long calls?
Recordings of known length (2, 4, 6, 8 and 10 minutes, timed by the phone system) are each timed 3 times with the stopwatch. Bias = stopwatch time − true time.
Step by step
Average biasaverage of all 15 biases= +0.155 minutes (about 9 seconds)
Does bias change with size?regress bias on the true length= bias = 0.009 + 0.0243 × length
Is the slope real?p-value of the slope= 0.0005: yes
Bias at each endat 2 minutes: 0.009 + 0.0243 × 2; at 10: 0.009 + 0.0243 × 10= 0.06 and 0.25 minutes
The stopwatch reads long, and more so for longer calls: about 4 seconds on a 2-minute call, 15 seconds on a 10-minute call. That's a linearity problem as well as a bias.
What it led to
Small against call lengths used for staffing, but it adds up: the team corrects stopwatch times by the fitted line, and moves to the phone system's own timer when it's available.
Do it in a spreadsheet
Bias
=C2-B2
Slope and its p-value
=LINEST(D2:D16,B2:B16,TRUE,TRUE)
Average bias
=AVERAGE(D2:D16)
Try it yourself: If the slope had been 0.000 with an average bias of +0.15, what kind of problem would that be?
Pure bias: the same offset at every length. Correct it by subtracting 0.15 minutes; there's no linearity problem.
Alma, Anouk and Arturo time 10 recorded calls twice each (minutes). The average and range method separates the stopwatch method's error from the real differences between calls.
Step by step
Average rangefor each person and call, the difference between their two times; average all 30= 0.22 minutes
Repeatabilityaverage range × 0.8862 (for 2 trials)= 0.195
About 14% of the variation in the times comes from the timing method: acceptable for planning staffing (10 to 30% may be acceptable). The method can tell about 10 groups of call length apart, well above the minimum of 5.
What it led to
Use the call times for capacity planning. Write a start-and-stop rule (start at “hello”, stop when the booking is saved) to reduce the repeatability error further.
Do it in a spreadsheet
Range for one person and call
=ABS(B2-C2)
Average range
=AVERAGE(H2:J11) (ranges in H to J)
Repeatability
=K12*0.8862
Gauge share
=SQRT(EV^2+AV^2)/SQRT(EV^2+AV^2+PV^2)
Try it yourself: If the gauge error stayed at 0.226 but the calls varied much less (real variation 0.6), what would the gauge share be?
√(0.226² + 0.6²) = 0.641; 0.226 ÷ 0.641 = 35%. The same stopwatch would no longer be good enough: acceptability depends on what you're measuring.
In the roles
How a Process Improvement Specialist uses it
Three people time 10 recorded calls twice: 13.8% of the variation comes from timing, acceptable for capacity planning.