Plan-do-study-act

A small, planned test of a change: plan it with a prediction, do it, study the results against the prediction, then act: adopt, adapt or drop it.

Common practice
4 steps
Used by Process Improvement Specialist

What it is

Plan-do-study-act is a short cycle for testing a change: plan with a prediction, do it on a small scale, study the results against the prediction, then act.

When to use it

Before rolling out any change that affects customers or staff.

Why it works

Small tests find problems early and cheaply, and build confidence and evidence before a full roll-out.

Do

  • Write the prediction before the test.
  • Keep cycles short: days or weeks.

Don't

  • Pilots without a success measure.
  • Changing the measure between baseline and pilot.
  • Declaring success before studying the data.

Step by step

  1. Plan Change, scope, measures, prediction.
  2. Do Run it; note problems.
  3. Study Compare with baseline and prediction.
  4. Act Adopt, adapt or drop.
Also called: PDSA, PDCA, pilotPrint the blank template ↗

Worked example

The situation. A school office tests a new way to handle absence calls.

  1. Prediction: calls answered within a minute rise from 60% to 85%.

The result. Rolled out to the whole school a month later.

PDSA record Print blank
StageWhat happened
PlanTwo weeks, one year group, same definition of “answered within a minute”
DoRun; a script problem found on day 2 and fixed
Study82% within a minute against 60% before
ActAdopt for all year groups

Filled in for: A school office tests a new way to handle absence calls.

StageNotes

Copy this structure, or print the blank version and fill it in by hand.

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

Did the pilot work?

From Day 43: The pilot of the Process Improvement Specialist story

For four weeks, the package runs: book up to 2 weeks ahead, reminders for every booking, protected urgent slots, two extra Monday sessions. Astrid (Data Analyst) takes 60 random requests from the pilot, by the same definition as the baseline.

Waits before the project and during the pilot010203040Before: median 10, quartiles 5 and 14.25, n = 6010BeforePilot: median 4, quartiles 3 and 5, n = 604Pilot

Step by step

  1. Median waitbaseline 10 days; pilot= 4 days
  2. Within 7 daysbaseline 27 of 60 (45%); pilot 53 of 60= 88%
  3. Two-proportion testz = (0.883 − 0.45) ÷ √(0.667 × 0.333 × 2/60)= z = 5.03, p below 0.0001
  4. Mann-Whitneywaits before generally longer than in the pilot= p below 0.0001
  5. Missed appointments15.7% (220 of 1,400) to 8.5% (117 of 1,380); two-proportion z = 5.84= p below 0.0001
  6. Against the goalmedian 5 or less: met; 90% within 7 days: 88%= close
RequestPeriodWait (days)
R01Before12
R02Before13
R03Before12
R04Before28
R05Before11
R06Before12
R07Before16
R08Before7
R09Before3
R10Before4
R11Before4
R12Before10
R13Before4
R14Before17
R15Before5
R16Before8
R17Before5
R18Before5
R19Before5
R20Before20
R21Before3
R22Before15
R23Before5
R24Before9
R25Before5
R26Before5
R27Before15
R28Before15
R29Before14
R30Before13
R31Before18
R32Before16
R33Before3
R34Before5
R35Before10
R36Before7
R37Before6
R38Before10
R39Before10
R40Before5
R41Before5
R42Before4
R43Before5
R44Before6
R45Before7
R46Before11
R47Before11
R48Before3
R49Before13
R50Before26
R51Before12
R52Before22
R53Before27
R54Before18
R55Before4
R56Before14
R57Before20
R58Before3
R59Before6
R60Before19
P01Pilot8
P02Pilot5
P03Pilot2
P04Pilot4
P05Pilot3
P06Pilot4
P07Pilot5
P08Pilot2
P09Pilot6
P10Pilot2
P11Pilot4
P12Pilot6
P13Pilot6
P14Pilot3
P15Pilot10
P16Pilot5
P17Pilot2
P18Pilot4
P19Pilot3
P20Pilot5
P21Pilot2
P22Pilot5
P23Pilot2
P24Pilot7
P25Pilot5
P26Pilot8
P27Pilot3
P28Pilot1
P29Pilot2
P30Pilot4
P31Pilot11
P32Pilot5
P33Pilot8
P34Pilot3
P35Pilot3
P36Pilot3
P37Pilot7
P38Pilot3
P39Pilot3
P40Pilot9
P41Pilot3
P42Pilot4
P43Pilot2
P44Pilot4
P45Pilot6
P46Pilot7
P47Pilot2
P48Pilot1
P49Pilot5
P50Pilot9
P51Pilot3
P52Pilot5
P53Pilot4
P54Pilot1
P55Pilot1
P56Pilot4
P57Pilot5
P58Pilot2
P59Pilot3
P60Pilot3

How to read the result

The pilot cut the median wait from 10 days to 4 and missed appointments almost in half. 88% of patients were offered an appointment within 7 days, just short of the 90% goal, before the lost sessions are covered.

What it led to

Roll out the package, adding cover for the two lost sessions, which the regression says should close the gap. Watch the Thursday sessions that moved to Monday for side effects.

Do it in a spreadsheet

Within 7 days=COUNTIFS(B2:B121,"Pilot",C2:C121,"<=7")/60
Median=MEDIAN(IF(B2:B121="Pilot",C2:C121))
Two-proportion z=(0.883-0.45)/SQRT(0.667*0.333*(2/60))
Try it yourself: Thursday lost two sessions to Monday. What would you check to make sure the problem didn't just move?

Waits for requests made on Thursday and Friday, before and during the pilot. If they grew a lot, rebalance.

In the roles

How a Process Improvement Specialist uses it

Four weeks: median wait 10 to 4 days, 88% within 7 days, missed appointments 15.7% to 8.5%.

Questions people ask

PDSA or PDCA?

The same idea. “Study” stresses learning from the data rather than just checking.