Working out how much data is needed to estimate something precisely enough, or to give a test a good chance of detecting a difference that matters.
Common practice 5 steps Used by Process Improvement Specialist
What it is
Sample size is how much data you need. Power is the chance a test detects a real difference of a given size. Too little data gives low power: real effects get missed.
When to use it
Before collecting data for an estimate or a comparison, and when a test comes back “not significant”.
Why it works
It avoids both wasted effort (too much data) and false comfort (too little).
Do
Halving the difference you want to detect needs four times the data.
Don't
Guessing the spread.
Running a test with too little data, then reading “not significant” as “no difference”.
Filled in for: A team wants to know if a new layout cuts picking time by 1 minute; standard deviation about 2.5 minutes.
Input
Value
Copy this structure, or print the blank version and fill it in by hand. One average: n = (z × s ÷ E)² · Two groups: n = 2 × (zα + zβ)² × s² ÷ d² (zα = 1.96 for 95%, zβ = 0.84 for 80% power)
Before you use it: check these
Check
If it fails
A realistic estimate of the spread
Run a small pilot first
The smallest difference that matters, agreed in advance
Agree it with the process owner before calculating
How to do it with real data
The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
To estimate the average wait within ±2 days with 95% confidence, Augustin (Black Belt) shows the sample size formula. A pilot of 20 records gave a standard deviation of about 6.5 days.
Before comparing two groups, Amara wants an 80% chance of detecting a 3-day difference in waits, if it's real. The waits' standard deviation is about 6.5 days; alpha is 0.05.
Step by step
Formula (two groups)n per group = 2 × (z for alpha + z for power)² × s² ÷ difference²
Fill in2 × (1.96 + 0.84)² × 6.5² ÷ 3²= 73.7
Round up= 74 per group
What 30 per group would givepower = chance of detecting it: Φ(3 ÷ (6.5 × √(2/30)) − 1.96)= 43%