Machine breakdowns30 questions5 phases
Steadyline: a Process Improvement Specialist case study
Steadyline packs food on 12 machines running two shifts. Unplanned breakdowns cost about 14 hours of production a week, and orders are going out late. You're the Green Belt asked to cut downtime.
What this case study tests
Measurement of stopsCurve fitPaired t-testI-MR chart and kanban
You're the Process Improvement Specialist. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.
Team
Ashton (Process Improvement Specialist)You: the Green Belt leading the project
Amina (Reliability Engineer)Breakdown records
Aldo (Line Technician)Fixes the machines
Stakeholders
Aria (Operations Director)Sponsor
Ayden (Maintenance Manager)Process owner
Agneta (Finance Controller)The money
Ariel (Black Belt)Your mentor
Steadyline
Define
Lines that keep stopping
Question 1 of 30
Choose 1Aria (Operations Director)
Our packing lines keep breaking down. We lose orders.
Question 2 of 30
Choose 1Ayden (Maintenance Manager)
Planned maintenance, changeovers and breakdowns all stop the lines.
Question 3 of 30
Choose 1Aldo (Line Technician)
Production planners want lines that run when scheduled, and fast repair when they don't.
Question 4 of 30
Choose 1Amina (Reliability Engineer)
25 of the last 26 weeks had more than 6 hours of unplanned downtime.
How would you describe baseline performance?
Learn it on Day 22: How capable is the process?Question 5 of 30
Choose 1Agneta (Finance Controller)
What do breakdowns cost?
Lost production costs about €1,800 an hour; downtime averages 13.9 hours a week over 50 weeks. Yearly cost?
Learn it on Day 5: Which problem first?Question 6 of 30
Choose 1Ayden (Maintenance Manager)
Who's on it?
Question 7 of 30
Choose 1Aria (Operations Director)
Sign with “replace the four oldest machines”?
Steadyline
Measure
Counting every stop
Question 8 of 30
Choose 1Aldo (Line Technician)
Machine stops, operator calls, technician walks over, diagnoses, fetches parts, repairs, restarts.
What does the value stream show?
Learn it on Day 15: Where does the time go?Question 9 of 30
Choose 1Amina (Reliability Engineer)
Operators log stops differently: some log a 5-minute jam, some don't.
Question 10 of 30
Choose 1Ariel (Black Belt)
The controller says 61 stops last week; the operators' log says 38.
What's this?
Learn it on Day 18: Do we agree what's urgent?Question 11 of 30
Choose 1Amina (Reliability Engineer)
Download the data
26 weeks of unplanned downtime hours.
| Week | Unplanned downtime (hours) |
|---|---|
| Week 1 | 10 |
| Week 2 | 12.1 |
| Week 3 | 25.3 |
| Week 4 | 16.9 |
| Week 5 | 6.7 |
| Week 6 | 13 |
| Week 7 | 10.1 |
| Week 8 | 13.8 |
| Week 9 | 6.8 |
| Week 10 | 14.3 |
| Week 11 | 14.3 |
| Week 12 | 24.4 |
| Week 13 | 14.8 |
| Week 14 | 15.9 |
| Week 15 | 7.2 |
| Week 16 | 32 |
| Week 17 | 6 |
| Week 18 | 20.2 |
| Week 19 | 11.4 |
| Week 20 | 9.1 |
| Week 21 | 10 |
| Week 22 | 9.9 |
| Week 23 | 15.1 |
| Week 24 | 12.4 |
| Week 25 | 23.5 |
| Week 26 | 6.3 |
Which description is right?
Learn it on Day 20: The baseline in numbersQuestion 12 of 30
Choose 1Aria (Operations Director)
Download the data
How capable are we against 6 hours?
| Week | Unplanned downtime (hours) |
|---|---|
| Week 1 | 10 |
| Week 2 | 12.1 |
| Week 3 | 25.3 |
| Week 4 | 16.9 |
| Week 5 | 6.7 |
| Week 6 | 13 |
| Week 7 | 10.1 |
| Week 8 | 13.8 |
| Week 9 | 6.8 |
| Week 10 | 14.3 |
| Week 11 | 14.3 |
| Week 12 | 24.4 |
| Week 13 | 14.8 |
| Week 14 | 15.9 |
| Week 15 | 7.2 |
| Week 16 | 32 |
| Week 17 | 6 |
| Week 18 | 20.2 |
| Week 19 | 11.4 |
| Week 20 | 9.1 |
| Week 21 | 10 |
| Week 22 | 9.9 |
| Week 23 | 15.1 |
| Week 24 | 12.4 |
| Week 25 | 23.5 |
| Week 26 | 6.3 |
Question 13 of 30
Choose 1Aria (Operations Director)
Ready?
Steadyline
Analyse
Missing maintenance and ageing machines
Question 14 of 30
Choose 1Aldo (Line Technician)
Why did the sealer stop? A bearing failed. Why? It wasn't greased. Why? Greasing is on a paper list nobody owns. Why? The planned maintenance system was never set up for the new lines.
Question 15 of 30
Choose 1Amina (Reliability Engineer)
No greasing: severity 7, occurrence 7, detection 6. Electrical fault: severity 8, occurrence 2, detection 5.
Question 16 of 30
Choose 1Amina (Reliability Engineer)
Download the data
Failures per month against machine age, 14 machines.
| Machine | Age (years) | Failures per month |
|---|---|---|
| M01 | 9.9 | 2.12 |
| M02 | 4.8 | 0.8 |
| M03 | 1.6 | 0.46 |
| M04 | 1.2 | 0.52 |
| M05 | 12.4 | 3.82 |
| M06 | 13.8 | 4.77 |
| M07 | 9.5 | 2.36 |
| M08 | 11.2 | 3.59 |
| M09 | 8.6 | 1.85 |
| M10 | 14.1 | 4.7 |
| M11 | 12.4 | 3.99 |
| M12 | 1 | 0.65 |
| M13 | 13 | 3.72 |
| M14 | 1.5 | 0.32 |
Is the relationship a straight line?
Learn it on Day 40: When the line bendsQuestion 17 of 30
Choose 1Ariel (Black Belt)
Which causes are proven?
Which list is right?
Learn it on Day 36: The Analyse reviewQuestion 18 of 30
Choose 1Aria (Operations Director)
Ruled out?
Steadyline
Improve
Planned care, not repairs
Question 19 of 30
Choose 1Aldo (Line Technician)
Ideas: a planned maintenance schedule in the system, overhaul the four oldest machines, a spares point next to the lines, replace the four oldest.
Question 20 of 30
Choose 1Amina (Reliability Engineer)
Download the data
The curve predicts failures by age.
| Machine | Age (years) | Failures per month |
|---|---|---|
| M01 | 9.9 | 2.12 |
| M02 | 4.8 | 0.8 |
| M03 | 1.6 | 0.46 |
| M04 | 1.2 | 0.52 |
| M05 | 12.4 | 3.82 |
| M06 | 13.8 | 4.77 |
| M07 | 9.5 | 2.36 |
| M08 | 11.2 | 3.59 |
| M09 | 8.6 | 1.85 |
| M10 | 14.1 | 4.7 |
| M11 | 12.4 | 3.99 |
| M12 | 1 | 0.65 |
| M13 | 13 | 3.72 |
| M14 | 1.5 | 0.32 |
How do you use it to check the plan?
Learn it on Day 40: When the line bendsQuestion 21 of 30
Choose 1Ayden (Maintenance Manager)
Download the data
Pilot on 10 machines for 3 months: monthly downtime per machine, before and after.
| Machine | Downtime per month before (hours) | After | Difference |
|---|---|---|---|
| M01 | 16.2 | 11 | 5.2 |
| M02 | 10.3 | 3.6 | 6.7 |
| M03 | 6.7 | 4.6 | 2.1 |
| M04 | 6.3 | 2.3 | 4 |
| M05 | 19 | 12.2 | 6.8 |
| M06 | 20.6 | 8.7 | 11.9 |
| M07 | 15.7 | 10.9 | 4.8 |
| M08 | 17.7 | 10 | 7.7 |
| M09 | 14.7 | 6.9 | 7.8 |
| M10 | 21 | 10.9 | 10.1 |
Question 22 of 30
Choose 1Ayden (Maintenance Manager)
Roll it out.
What's in the plan?
Learn it on Day 44: Rolling it outQuestion 23 of 30
Choose 1Aria (Operations Director)
Why approve?
Steadyline
Control
Keeping the lines running
Question 24 of 30
Choose 1Amina (Reliability Engineer)
Download the data
After roll-out: unplanned downtime hours each week, 20 weeks.
| Week | Unplanned downtime (hours) |
|---|---|
| Week 1 | 5.3 |
| Week 2 | 5.1 |
| Week 3 | 5.9 |
| Week 4 | 5.3 |
| Week 5 | 4.6 |
| Week 6 | 5.6 |
| Week 7 | 6.6 |
| Week 8 | 6.2 |
| Week 9 | 4.4 |
| Week 10 | 3.8 |
| Week 11 | 4.5 |
| Week 12 | 5.2 |
| Week 13 | 2.6 |
| Week 14 | 5 |
| Week 15 | 3.8 |
| Week 16 | 4.4 |
| Week 17 | 4.6 |
| Week 18 | 4.9 |
| Week 19 | 5.7 |
| Week 20 | 6.3 |
Question 25 of 30
Choose 1Ayden (Maintenance Manager)
How do we keep it?
Question 26 of 30
Choose 1Aldo (Line Technician)
Spare bearings: we use about 6 a month, and the supplier takes 3 weeks.
How many should the line-side kanban hold?
Learn it on Day 53: Lean controlsQuestion 27 of 30
Choose 1Ayden (Maintenance Manager)
What am I taking on?
What's in the handover?
Learn it on Day 54: Handing overQuestion 28 of 30
Choose 1Agneta (Finance Controller)
Downtime fell from 13.9 to 5.0 hours a week. The new planned maintenance costs about €60,000 a year.
Question 29 of 30
Choose 1Ariel (Black Belt)
Final report?
What's in it?
Learn it on Day 55: Closing the projectQuestion 30 of 30
Choose 1Aria (Operations Director)
Close it?