A pull system where using up stock triggers its replacement: a card or empty bin signals the order, sized to cover the supplier's lead time plus a safety margin.
Common practice 5 steps Used by Process Improvement Specialist
What it is
Kanban replenishment uses a visual signal, such as an empty bin or a card, to trigger reordering only what has been used.
When to use it
For supplies used regularly, to stop both shortages and overstocking without counting stock.
Why it works
It prevents both shortages and overstock without anyone counting stock.
Do
Put the card where nobody can miss it when the bin empties.
Ayumi (Healthcare Assistant) sets up a two-bin kanban for blood tubes: when the first bin is empty, its card goes to the supplier and the second bin is used.
Step by step
Use during lead time40 × 3= 120 tubes
Safety stock40 × 1= 40 tubes
Bin size120 + 40= 160 tubes
Round to boxes160 ÷ 50 = 3.2= 4 boxes (200 tubes) per bin
Stock held at mosttwo bins= 400 tubes, down from about 1,100