Data and statistics · cheat sheet

I-MR chart

A pair of control charts for single measurements over time: one for the values, one for the change from each value to the next.

Common practice
6 steps
Used by Process Improvement Specialist

What it is

An I-MR chart plots single values and the moving range (the change from one value to the next). The moving range estimates the normal short-term variation.

When to use it

When there is one value per period: daily averages, weekly totals, monthly figures, or slow or costly measurements.

Why it works

Many measures come one at a time: daily, weekly, monthly. This chart tells normal ups and downs from real change.

Do

  • Rules: a point outside, 8 in a row on one side, 6 rising or falling.

Don't

  • Reacting to points inside the limits.
  • Very skewed data: transform it or use other charts.

Step by step

  1. 20+ values
  2. Moving ranges
  3. Centre lines
  4. Limits Average ± 2.66 × MR̄.
  5. MR limit 3.267 × MR̄.
  6. Read with rules
Also called: Individuals and moving range chart, XmR chartPrint the blank template ↗

Worked example

The situation. Monthly customer complaints at a shop.

  1. Average 12, average moving range 3.

The result. A month with 15 complaints is normal; 21 would be a signal.

I-MR data sheet Print blank
LineCal­culationValue
Upper limit12 + 2.66 × 320.0
Lower limit12 − 2.66 × 34.0
Moving range limit3.267 × 39.8

Filled in for: Monthly customer complaints at a shop.

PeriodValueMoving range

Copy this structure, or print the blank version and fill it in by hand. Average ______ MR̄ ______ limits ± 2.66 × MR̄ · MR limit 3.267 × MR̄

Before you use it: check these

CheckIf it fails
One value per periodUse subgroup charts when several values are taken together
Roughly normal valuesTransform, or rely on the run rules with care

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

I-MR chart of the daily average wait

From Day 48: One number a day of the Process Improvement Specialist story

The weekly report to the council shows one number a day: the average wait for all routine requests booked that day. One value per day calls for an individuals chart.

I chart: daily average wait02468CLUCLLCLDay 1: 4.3Day 2: 4.1Day 3: 4.6Day 4: 4.3Day 5: 3.9Day 6: 4.4Day 7: 4.9Day 8: 4.7Day 9: 3.8Day 10: 3.5Day 11: 3.9Day 12: 4.2Day 13: 2.9Day 14: 4.1Day 15: 3.5Day 16: 3.8Day 17: 3.9Day 18: 4Day 19: 4.4Day 20: 4.8Day 21: 4.1Day 22: 5Day 23: 3.8Day 24: 4.4Day 25: 4.7Day 1Day 4Day 7Day 10Day 13Day 16Day 19Day 22Day 25Average wait (days)MR chart: change from the day before00.511.52CLUCLDay 2: 0.2Day 3: 0.5Day 4: 0.3Day 5: 0.4Day 6: 0.5Day 7: 0.5Day 8: 0.2Day 9: 0.9Day 10: 0.3Day 11: 0.4Day 12: 0.3Day 13: 1.3Day 14: 1.2Day 15: 0.6Day 16: 0.3Day 17: 0.1Day 18: 0.1Day 19: 0.4Day 20: 0.4Day 21: 0.7Day 22: 0.9Day 23: 1.2Day 24: 0.6Day 25: 0.3Day 2Day 5Day 8Day 11Day 14Day 17Day 20Day 23Moving range

Step by step

  1. Moving rangesdifference between each day and the day before (24 of them)
  2. Centre linesaverage of the 25 values; average moving range= 4.16; 0.525
  3. I limits4.16 ± 2.66 × 0.525= 2.76 to 5.56
  4. MR upper limit3.267 × 0.525= 1.72
  5. Readall points inside, no runs of 8 on one side, no trends of 6= stable
DayAverage wait (days)Moving range
Day 14.3
Day 24.10.2
Day 34.60.5
Day 44.30.3
Day 53.90.4
Day 64.40.5
Day 74.90.5
Day 84.70.2
Day 93.80.9
Day 103.50.3
Day 113.90.4
Day 124.20.3
Day 132.91.3
Day 144.11.2
Day 153.50.6
Day 163.80.3
Day 173.90.1
Day 1840.1
Day 194.40.4
Day 204.80.4
Day 214.10.7
Day 2250.9
Day 233.81.2
Day 244.40.6
Day 254.70.3

How to read the result

The daily average wait is stable around 4.2 days, and any day between 2.8 and 5.6 is normal variation. No reason to react to an individual day inside those limits.

What it led to

Give the council the chart, not just the number, so nobody reacts to normal daily ups and downs.

Do it in a spreadsheet

Moving range=ABS(B3-B2)
Limits=AVERAGE(B2:B26)+2.66*AVERAGE(C3:C26)
MR upper limit=3.267*AVERAGE(C3:C26)
Try it yourself: Tomorrow the daily average is 5.4 days. Do you react?

No: 5.4 is inside the limits (up to 5.56). It's normal variation. React to points outside the limits or to patterns such as 8 in a row above the centre line.

In the roles

How a Process Improvement Specialist uses it

Daily average wait: centre 4.16 days, limits 2.76 to 5.56.

Questions people ask

Is it sensitive?

Less than subgroup charts; add CUSUM or EWMA for small shifts.