Lean and improvement · cheat sheet

Value stream map

A map of a process that adds the working time and waiting time of each step, showing the total lead time and how little of it adds value.

Common practice
6 steps
Used by Process Improvement Specialist

What it is

A value stream map adds time to a process map: working time per step, waiting time between steps, and totals for lead time and value-added time.

It often includes takt time: the pace customers demand.

When to use it

When customers wait much longer than the work takes, and you need to see where the time goes.

Why it works

It shows, in one picture, that most of the time customers wait is not work at all.

Do

  • Use real averages from data, not what people think.
  • Show the timeline as a ladder under the map: work up, waits down.

Don't

  • Using best-case times instead of real averages.
  • Leaving out waits because nobody owns them.
  • Drawing it once and never using it.

Step by step

  1. Pick 5 to 10 steps
  2. Record times Working time and the wait before the next step.
  3. Add the totals Lead time and value-added time.
  4. Efficiency Value-added ÷ lead time.
  5. Takt time Available time ÷ demand; compare with cycle times.
  6. Mark the biggest waits
Also called: VSM, current-state mapPrint the blank template ↗

Worked example

The situation. A print shop's business card orders.

  1. Work takes 45 minutes; the customer waits 6 days.

The result. Proofs sent within an hour and printing every afternoon cut lead time to 2 days.

Value stream timeline Print blank
StepWork (min)Wait before next
Order checked51 day
Proof sent and approved102 days
Printed and cut252 days
Packed and sent51 day

Filled in for: A print shop's business card orders.

StepWorking timeWaiting time before next stepValue-adding? (yes or no)

Copy this structure, or print the blank version and fill it in by hand. Lead time = ______ Value-added time = ______ Efficiency = ______ % Takt time = available time ÷ demand = ______

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

Lead time, value-added time and takt time

From Day 15: Where does the time go? of the Process Improvement Specialist story

Astrid (Data Analyst) times each step of a routine request from the value stream, using the averages from the booking data.

Where the waiting days are0246810Phone / queue: 0.00.0PhonequeueCall / back loop: 0.00.0Callback loopWait for / the date: 0.00.0Wait forthe date

Step by step

  1. Total working time4 + 3 + 2 + 10 minutes= 19 minutes
  2. Lead timeabout 12 minutes in the queue + 2.1 days + 8.3 days= about 10.4 days
  3. Value-added timeonly the consultation changes something the patient cares about= 10 minutes
  4. Process cycle efficiency10 minutes ÷ (10.4 days × 1,440 minutes a day)= about 0.07%
  5. Takt time at 8 o'clock3 receptionists × 90 minutes = 270 minutes ÷ 48 requests= 5.6 minutes per request per receptionist
  6. Compare with cycle timeeach call takes 4 + 3 + 2 minutes= 9 minutes, slower than takt
StepWorking time (min)Waiting before next step (days)
Phone queue00.01
Call and triage40
Check the rota30
Told to call back: the loop02.1
Book the appointment20
Wait for the appointment date08.3
Consultation100

How to read the result

Almost all of the 10.4 days is waiting, mostly before the appointment date and in the call-back loop. And at 8 o'clock, calls take longer than the pace demand needs, so the queue is built into the process.

What it led to

Two places to analyse first: why appointment dates are so far away, and why patients are sent round the call-back loop.

Do it in a spreadsheet

Lead time in days=0.01+2.1+8.3
Efficiency=10/(C9*1440) (C9 = lead time in days)
Takt time=(3*90)/48
Try it yourself: If a fourth receptionist joined for the 8 o'clock rush, what would the takt time per receptionist be, and could they keep up?

4 × 90 = 360 minutes ÷ 48 = 7.5 minutes per request. Still faster than the 9-minute call, so a queue would still build, just more slowly.

In the roles

How a Process Improvement Specialist uses it

19 minutes of work inside 10.4 days of waiting; at 8 o'clock calls take 9 minutes against a takt of 5.6.

Questions people ask

What's the difference between cycle time and lead time?

Cycle time is how long one step takes to process an item. Lead time is the whole time from request to delivery, waits included.