Quality · cheat sheetRun chart
A line chart of a measure in time order, with the median drawn across it, showing trends, shifts and patterns that a single number hides.
Common practice
6 steps
Used by Process Improvement Specialist
What it is
A line chart of one measure in time order, with a horizontal line at the median.
It shows how a process behaves over time: steady, drifting, shifting or repeating.
When to use it
Whenever you have repeated measurements over time and want to see how the process behaves before analysing it further.
Variations
- Control chart Adds limits calculated from the data, to tell everyday variation from unusual events.
Why it works
Averages and totals hide patterns. A run chart is the simplest way to see them before deciding what to do.
Do
- Note events on the chart: a new rule, a holiday, a staff change.
- Don't redraw the median after every point.
Don't
- Reacting to every single high or low point.
- Too few points to see a pattern; aim for at least 20.
- Changing how the measure is collected halfway through.
Step by step
Collect in time order Daily, weekly or per item.
Plot the points Joined by a line.
Draw the median Half the points above, half below.
Look for patterns A run of 6 or more on one side, 5 or more steadily up or down, a repeating cycle.
Ask what happened Before acting.
Keep plotting To see whether a change worked.
Worked example
The situation. A shop tracks delivery time over 20 days.
- Median 3 days. Days 13 to 20 are all above the median: a shift. A new courier started on day 12.
The result. The shop raised it with the new courier, and times returned to normal.
| Day | Delivery (days) | Above median? |
|---|
| 10 | 3 | No |
| 11 | 2 | No |
| 12 | 3 | No |
| 13 | 5 | Yes |
| 14 | 4 | Yes |
| 15 | 5 | Yes |
Filled in for: A shop tracks delivery time over 20 days.
| Date or number | Value | Notes (anything unusual) |
|---|
| | |
| | |
| | |
| | |
Record the values in time order, then plot them. Median: ______ Patterns seen: ______
How to do it with real data
The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Worked example with real dataReading a run chart
From Day 6: Averages hide the pain of the Process Improvement Specialist story
Astrid (Data Analyst) plots the median wait for each of the last 20 weeks and adds the median of all 20 as a centre line.
Step by step
- Centre lineSort the 20 values; the median is the middle (10th and 11th values)= 9 days
- Mark each pointAbove, below or on the median; ignore points on it= 16 useful points
- Look for a shift6 or more points in a row on one side is a signal= weeks 12 to 20: 9 in a row above
- Count the runsA run is a series on the same side of the median= 2 runs
- Check the number of runsWith 16 useful points, fewer than 5 runs is very unlikely by chance= 2 is a signal
| Week | Median wait (days) |
|---|
| Wk 1 | 8 |
| Wk 2 | 9 |
| Wk 3 | 8 |
| Wk 4 | 7 |
| Wk 5 | 9 |
| Wk 6 | 8 |
| Wk 7 | 9 |
| Wk 8 | 8 |
| Wk 9 | 8 |
| Wk 10 | 9 |
| Wk 11 | 8 |
| Wk 12 | 10 |
| Wk 13 | 10 |
| Wk 14 | 11 |
| Wk 15 | 11 |
| Wk 16 | 12 |
| Wk 17 | 12 |
| Wk 18 | 13 |
| Wk 19 | 12 |
| Wk 20 | 13 |
How to read the result
The waits didn't just have a few bad weeks: from week 12 the process shifted upwards and stayed there. Something changed around week 12.
What it led to
Ask what changed around week 12 and note it for the Analyse phase. Don't react to single bad days; react to signals like this one.
Do it in a spreadsheet
| Median | =MEDIAN(B2:B21) |
| Above or below | =IF(B2>$D$1,"Above",IF(B2<$D$1,"Below","On")) |
| Chart | Insert a line chart of column B, then add the median as a second series |
Try it yourself: How many points in a row on one side of the median count as a shift, and which weeks show one here?
6 or more. Weeks 12 to 20 are 9 points in a row above the median.
In the roles
How a Process Improvement Specialist uses it
Twenty weeks of daily waits: the line creeps up from week 12, and every Monday jumps. Neither shows in the 10-day average.
Questions people ask
How many points do I need?
About 20 for patterns to be reliable.
Median or mean?
The median isn't pulled by extreme values, so it suits run charts.