Fairlend: a Process Improvement Specialist case study
Fairlend is a regional bank. Personal loan applicants wait too long for a decision: only 38% hear within 5 working days, and 9% give up and borrow elsewhere. You're the Green Belt asked to find out why and fix it.
What this case study tests
Sample size and confidenceMood's median and Mann-WhitneyRegressionP chart
You're the Process Improvement Specialist. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.
Team
Abena (Process Improvement Specialist)You: the Green Belt leading the project
Anton (Data Analyst)Loan system data
Alicia (Loan Officer)Processes 30 applications a week
Stakeholders
Alistair (Head of Lending)Sponsor
Annika (Lending Operations Manager)Process owner
Ahmed (Finance Manager)The money
Adele (Black Belt)Your mentor
Fairlend
Define
Slow decisions, lost customers
Question 1 of 31
Choose 1Alistair (Head of Lending)
Customers say our loan decisions are slow. Competitors decide in two days.
Which problem statement is best?
Learn it on Day 7: A problem, not a solutionQuestion 2 of 31
Choose 1Annika (Lending Operations Manager)
Mortgages and business loans have the same problem. Include them?
Question 3 of 31
Choose 1Alicia (Loan Officer)
Applicants tell us they want a quick answer. Some also say they hate being asked for the same document twice.
Which critical-to-quality requirements follow?
Learn it on Day 9: What patients really needQuestion 4 of 31
Choose 1Anton (Data Analyst)
38% decided within 5 days. On the usual scale?
What is the baseline sigma level?
Learn it on Day 22: How capable is the process?Question 5 of 31
Choose 1Ahmed (Finance Manager)
What does slowness cost?
1,200 applications a month; 9% withdraw (each worth €900 margin over the loan's life); each application also gets 1.6 chasing calls at €4.50. What is the yearly cost of poor quality?
Learn it on Day 5: Which problem first?Question 6 of 31
Choose 1Annika (Lending Operations Manager)
Who do you need?
Question 7 of 31
Choose 1Alistair (Head of Lending)
Sign the charter now, and add “launch an automatic decision engine” as the goal?
Fairlend
Measure
Mapping hand-offs and trusting the dates
Question 8 of 31
Choose 1Alicia (Loan Officer)
An application goes from branch to scanning to operations to underwriting and back if anything's missing.
Question 9 of 31
Choose 1Adele (Black Belt)
You want to estimate the average days to decision within ±1 day. A pilot shows a standard deviation of about 4.5 days.
How many applications do you need?
Learn it on Day 27: What can a sample tell us?Question 10 of 31
Choose 1Anton (Data Analyst)
The loan system stamps “received” when the scan arrives, and the branch writes the date on paper. They don't always match.
What do you do?
Learn it on Day 18: Do we agree what's urgent?Question 11 of 31
Choose 1Anton (Data Analyst)
Download the data
40 applications, days to decision.
| Application | Channel | Days to decision |
|---|---|---|
| L01 | Online | 11 |
| L02 | Online | 1 |
| L03 | Online | 7 |
| L04 | Online | 5 |
| L05 | Online | 9 |
| L06 | Online | 5 |
| L07 | Online | 11 |
| L08 | Online | 5 |
| L09 | Online | 3 |
| L10 | Online | 6 |
| L11 | Online | 6 |
| L12 | Online | 4 |
| L13 | Online | 4 |
| L14 | Online | 6 |
| L15 | Online | 6 |
| L16 | Online | 4 |
| L17 | Online | 4 |
| L18 | Online | 2 |
| L19 | Online | 10 |
| L20 | Online | 4 |
| L21 | Branch | 15 |
| L22 | Branch | 9 |
| L23 | Branch | 20 |
| L24 | Branch | 16 |
| L25 | Branch | 9 |
| L26 | Branch | 16 |
| L27 | Branch | 5 |
| L28 | Branch | 14 |
| L29 | Branch | 4 |
| L30 | Branch | 9 |
| L31 | Branch | 13 |
| L32 | Branch | 8 |
| L33 | Branch | 6 |
| L34 | Branch | 5 |
| L35 | Branch | 6 |
| L36 | Branch | 13 |
| L37 | Branch | 12 |
| L38 | Branch | 7 |
| L39 | Branch | 4 |
| L40 | Branch | 11 |
Which description is right?
Learn it on Day 20: The baseline in numbersQuestion 12 of 31
Choose 1Annika (Lending Operations Manager)
Download the data
15 of the 40 were decided within 5 days.
| Application | Channel | Days to decision |
|---|---|---|
| L01 | Online | 11 |
| L02 | Online | 1 |
| L03 | Online | 7 |
| L04 | Online | 5 |
| L05 | Online | 9 |
| L06 | Online | 5 |
| L07 | Online | 11 |
| L08 | Online | 5 |
| L09 | Online | 3 |
| L10 | Online | 6 |
| L11 | Online | 6 |
| L12 | Online | 4 |
| L13 | Online | 4 |
| L14 | Online | 6 |
| L15 | Online | 6 |
| L16 | Online | 4 |
| L17 | Online | 4 |
| L18 | Online | 2 |
| L19 | Online | 10 |
| L20 | Online | 4 |
| L21 | Branch | 15 |
| L22 | Branch | 9 |
| L23 | Branch | 20 |
| L24 | Branch | 16 |
| L25 | Branch | 9 |
| L26 | Branch | 16 |
| L27 | Branch | 5 |
| L28 | Branch | 14 |
| L29 | Branch | 4 |
| L30 | Branch | 9 |
| L31 | Branch | 13 |
| L32 | Branch | 8 |
| L33 | Branch | 6 |
| L34 | Branch | 5 |
| L35 | Branch | 6 |
| L36 | Branch | 13 |
| L37 | Branch | 12 |
| L38 | Branch | 7 |
| L39 | Branch | 4 |
| L40 | Branch | 11 |
How capable is the process?
Learn it on Day 22: How capable is the process?Question 13 of 31
Choose 1Alistair (Head of Lending)
Ready for Analyse?
Fairlend
Analyse
What really delays a decision
Question 14 of 31
Choose 1Alicia (Loan Officer)
Download the data
Why are applications delayed? We noted the reason on 100 late ones.
| Reason for delay | Applications |
|---|---|
| Missing payslip or bank statement | 46 |
| Identity check repeated | 21 |
| Waiting for underwriter | 14 |
| Valuation of security | 12 |
| Other | 7 |
Question 15 of 31
Choose 1Annika (Lending Operations Manager)
Why are documents missing? Because the branch doesn't know which ones. Why? The checklist is from 2015. Why…
Question 16 of 31
Choose 1Anton (Data Analyst)
Missing documents: severity 7, occurrence 8, detection 3. Underwriter queue: severity 5, occurrence 4, detection 4.
Question 17 of 31
Choose 1Anton (Data Analyst)
Download the data
Online applications: median 5 days. Branch applications: median 9. 20 of each, skewed data.
| Application | Channel | Days to decision |
|---|---|---|
| L01 | Online | 11 |
| L02 | Online | 1 |
| L03 | Online | 7 |
| L04 | Online | 5 |
| L05 | Online | 9 |
| L06 | Online | 5 |
| L07 | Online | 11 |
| L08 | Online | 5 |
| L09 | Online | 3 |
| L10 | Online | 6 |
| L11 | Online | 6 |
| L12 | Online | 4 |
| L13 | Online | 4 |
| L14 | Online | 6 |
| L15 | Online | 6 |
| L16 | Online | 4 |
| L17 | Online | 4 |
| L18 | Online | 2 |
| L19 | Online | 10 |
| L20 | Online | 4 |
| L21 | Branch | 15 |
| L22 | Branch | 9 |
| L23 | Branch | 20 |
| L24 | Branch | 16 |
| L25 | Branch | 9 |
| L26 | Branch | 16 |
| L27 | Branch | 5 |
| L28 | Branch | 14 |
| L29 | Branch | 4 |
| L30 | Branch | 9 |
| L31 | Branch | 13 |
| L32 | Branch | 8 |
| L33 | Branch | 6 |
| L34 | Branch | 5 |
| L35 | Branch | 6 |
| L36 | Branch | 13 |
| L37 | Branch | 12 |
| L38 | Branch | 7 |
| L39 | Branch | 4 |
| L40 | Branch | 11 |
Which tests fit, and what do they show?
Learn it on Day 32: Checking with ranks and mediansQuestion 18 of 31
Choose 1Adele (Black Belt)
Which causes are proven?
Which list is right?
Learn it on Day 36: The Analyse reviewQuestion 19 of 31
Choose 1Alistair (Head of Lending)
Anything ruled out?
Why does the Analyse review list ruled-out causes?
Learn it on Day 36: The Analyse reviewFairlend
Improve
Fewer hand-offs, complete applications
Question 20 of 31
Choose 1Alicia (Loan Officer)
Ideas: a new checklist by loan type, one identity check shared by all teams, applications going straight to operations, a decision engine.
Question 21 of 31
Choose 1Anton (Data Analyst)
Download the data
15 applications: number of hand-offs and days to decision.
| Application | Hand-offs between teams | Days to decision |
|---|---|---|
| A01 | 7 | 9.5 |
| A02 | 5 | 6 |
| A03 | 5 | 6.8 |
| A04 | 3 | 4.7 |
| A05 | 3 | 1.9 |
| A06 | 2 | 3 |
| A07 | 2 | 1.8 |
| A08 | 2 | 2.4 |
| A09 | 3 | 4 |
| A10 | 6 | 8.5 |
| A11 | 5 | 8 |
| A12 | 7 | 11.6 |
| A13 | 5 | 7.3 |
| A14 | 5 | 9.1 |
| A15 | 7 | 9.5 |
How much would cutting hand-offs help?
Learn it on Day 38: How much difference would it make?Question 22 of 31
Choose 1Annika (Lending Operations Manager)
Pilot in two branches for four weeks: 207 of 280 decided within 5 days, against 114 of 300 before.
Question 23 of 31
Choose 1Annika (Lending Operations Manager)
Rolling out to 40 branches. What matters most?
Which plan is right?
Learn it on Day 44: Rolling it outQuestion 24 of 31
Choose 1Alistair (Head of Lending)
Why should I approve the roll-out?
Fairlend
Control
Keeping decisions fast
Question 25 of 31
Choose 1Anton (Data Analyst)
Download the data
After roll-out: the daily share of decisions taking more than 5 days, with 50 to 70 decisions a day.
| Day | Decisions | Over 5 days | Share |
|---|---|---|---|
| Day 1 | 67 | 19 | 0.284 |
| Day 2 | 63 | 6 | 0.095 |
| Day 3 | 60 | 18 | 0.3 |
| Day 4 | 55 | 8 | 0.145 |
| Day 5 | 56 | 15 | 0.268 |
| Day 6 | 50 | 9 | 0.18 |
| Day 7 | 51 | 16 | 0.314 |
| Day 8 | 50 | 12 | 0.24 |
| Day 9 | 53 | 11 | 0.208 |
| Day 10 | 67 | 15 | 0.224 |
| Day 11 | 63 | 9 | 0.143 |
| Day 12 | 69 | 13 | 0.188 |
| Day 13 | 60 | 16 | 0.267 |
| Day 14 | 62 | 16 | 0.258 |
| Day 15 | 70 | 18 | 0.257 |
| Day 16 | 65 | 15 | 0.231 |
| Day 17 | 63 | 25 | 0.397 |
| Day 18 | 61 | 22 | 0.361 |
| Day 19 | 61 | 16 | 0.262 |
| Day 20 | 69 | 18 | 0.261 |
Question 26 of 31
Choose 1Annika (Lending Operations Manager)
How do we keep this up?
Question 27 of 31
Choose 1Alicia (Loan Officer)
Branch staff sometimes skip the checklist when busy.
Question 28 of 31
Choose 1Annika (Lending Operations Manager)
What am I taking over?
What's in the handover?
Learn it on Day 54: Handing overQuestion 29 of 31
Choose 1Ahmed (Finance Manager)
Three months on: withdrawals fell from 9% to 4%, and chasing calls from 1.6 to 0.6 per application.
Question 30 of 31
Choose 1Adele (Black Belt)
How will other teams learn from it?
What's in the final report?
Learn it on Day 55: Closing the projectQuestion 31 of 31
Choose 1Alistair (Head of Lending)
Can we close?