Data and statistics · cheat sheet P chart A control chart for the share of items that fail a check, when the number checked can change from one period to the next.
Common practice 5 steps Used by Process Improvement Specialist
What it is A P chart plots the share of items failing a check each period, with limits that depend on how many were checked.
When to use it For yes-or-no outcomes with varying sample sizes: share late, share defective, share not offered in time.
Why it works It shows whether a yes-or-no process is stable, and flags unusual periods, even when volumes change.
Do Make sure the definition of failing doesn't change. Don't Using one fixed limit when n changes a lot. Very small n with rare defects, where limits are meaningless. Step by step Record n and failures
Shares
Centre p̄
Limits per period
Investigate
What the letters mean
X̄ · X̿ · R̄ · s̄ · p̄ · ū · c̄ A bar over a letter means an average: X̄ a subgroup average, X̿ the average of the averages, R̄ the average range, s̄ the average standard deviation, p̄ the average share, ū and c̄ the average defect rate and count
± Plus or minus: the allowed range either side
÷ × Divided by, multiplied by Worked example The situation. Late deliveries, about 200 a day.
p̄ = 0.04. The result. A day with 9% late (above 8.2%) triggered a check: a van broke down.
Line Calculation Value Upper limit (n = 200) 0.04 + 3 × √(0.04 × 0.96 ÷ 200) 0.082 Lower limit 0.04 − 0.042 0 (none)
Filled in for: Late deliveries, about 200 a day.
Period Number checked (n) Number failing Share Upper limit Lower limit
Copy this structure, or print the blank version and fill it in by hand.
Before you use it: check these Check If it fails Each item is defective or not Use a U or C chart when items can have several defects Sample size known each period Record it every time
How to do it with real data The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Worked example with real dataP chart: share not offered an appointment within 7 days
From Day 50: Counting yes or no of the Process Improvement Specialist story
Every request is checked: was an appointment offered within 7 days? The number of requests changes each day, so the limits change too.
P chart, with limits that depend on each day's number of requests 0 0.1 0.2 0.3 0.4 CL UCL Day 1: 0.105 Day 2: 0 Day 3: 0.12 Day 4: 0.022 Day 5: 0.109 Day 6: 0.05 Day 7: 0.122 Day 8: 0.075 Day 9: 0.302 (outside the limits) Day 10: 0.07 Day 11: 0.019 Day 12: 0.034 Day 13: 0.1 Day 14: 0.096 Day 15: 0.083 Day 16: 0.073 Day 17: 0.208 Day 18: 0.157 Day 19: 0.098 Day 20: 0.085 Day 1 Day 4 Day 7 Day 10 Day 13 Day 16 Day 19 Share not within 7 days
Step by step Average share total not within 7 ÷ total requests = 0.095 Upper limit for each day 0.095 + 3 × √(0.095 × 0.905 ÷ n); day 1, n = 57 = 0.211 Lower limit below zero for these sample sizes = none Read day 9: 0.302 against its limit of 0.228 = a signal Find the cause day 9: the booking system was down for 3 hours = special cause Recalculate without day 9 = 0.085
Day Requests Not within 7 days Share Upper limit Day 1 57 6 0.105 0.211 Day 2 53 0 0 0.215 Day 3 50 6 0.12 0.219 Day 4 45 1 0.022 0.225 Day 5 46 5 0.109 0.224 Day 6 40 2 0.05 0.233 Day 7 41 5 0.122 0.232 Day 8 40 3 0.075 0.233 Day 9 43 13 0.302 0.228 Day 10 57 4 0.07 0.211 Day 11 53 1 0.019 0.215 Day 12 59 2 0.034 0.209 Day 13 50 5 0.1 0.219 Day 14 52 5 0.096 0.216 Day 15 60 5 0.083 0.208 Day 16 55 4 0.073 0.213 Day 17 53 11 0.208 0.215 Day 18 51 8 0.157 0.218 Day 19 51 5 0.098 0.218 Day 20 59 5 0.085 0.209
How to read the result About 9% of requests now miss the 7-day standard on a normal day (the goal is under 10%). Day 9 was an unusual day with a clear cause, not a sign the process has slipped.
What it led to Add a booking-system outage to the response plan: paper booking sheets at the desk, entered when the system returns.
Do it in a spreadsheet Share =C2/B2Average share =SUM(C2:C21)/SUM(B2:B21)Upper limit =$G$1+3*SQRT($G$1*(1-$G$1)/B2) (G1 = average share)
Try it yourself: Why do the limits get closer together on days with more requests? The more items in a day, the less the share varies by chance: the limit width shrinks with the square root of n.
In the roles How a Process Improvement Specialist uses itShare not offered within 7 days: centre 0.095; day 9 (system down) above its limit.
Questions people ask Why do limits vary? Bigger samples vary less by chance, so their limits are tighter.