Biscuit packing30 questions5 phases

Crumbly: a Process Improvement Specialist case study

Crumbly makes 6 million packs of biscuits a year on line 2. The packs say 200 g, but the line fills them far heavier, giving away tonnes of biscuits, while now and then a pack fails the weight check. You're the Green Belt asked to fix the fill.

What this case study tests
Gauge studyCp and CpkOne-sample varianceXbar-S chart

You're the Process Improvement Specialist. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Team
Ayo (Process Improvement Specialist)You: the Green Belt leading the project
Anika (Quality Technician)Weights and lab checks
Abdul (Line Operator)Runs the depositor on line 2
Stakeholders
Agatha (Plant Manager)Sponsor
Alvaro (Production Manager)Process owner
Arabella (Finance Controller)The money
Ansel (Black Belt)Your mentor
Crumbly

Define

Too much in every pack

Question 1 of 30

Choose 1
Agatha (Plant Manager)
We're giving away biscuits. Packs say 200 g, but we fill far more. And now and then one fails the legal check.

Which problem statement is best?

Learn it on Day 7: A problem, not a solution

Technique: Problem statement

Question 2 of 30

Choose 1
Alvaro (Production Manager)
Lines 1 and 3 have similar problems.

How do you scope it?

Learn it on Day 8: Drawing the boundaries

Technique: SIPOC

Question 3 of 30

Choose 1
Anika (Quality Technician)
The customer (and the law) need packs at least the declared weight. The business needs as little giveaway as possible.

Which requirements follow?

Learn it on Day 9: What patients really need

Technique: CTQ tree

Question 4 of 30

Choose 1
Anika (Quality Technician)
Limits 195 to 209 g; mean 206.3 g, standard deviation 2.95 g, normal data.

What are Cp and Cpk?

Learn it on Day 22: How capable is the process?

Technique: Process capability

Question 5 of 30

Choose 1
Arabella (Finance Controller)
What does the overfill cost?

6 million packs a year; average 206.33 g against a 202 g target; biscuits cost €3.20 a kilo. What's the yearly giveaway?

Learn it on Day 5: Which problem first?

Technique: Cost of quality

Question 6 of 30

Choose 1
Alvaro (Production Manager)
Who's needed?

Which team?

Learn it on Day 11: Building the team

Technique: RACI

Question 7 of 30

Choose 1
Agatha (Plant Manager)
Sign, with “new depositor” as the deliverable?

How do you answer?

Learn it on Day 13: The Define review

Technique: Stage gate

Crumbly

Measure

Trusting the scales, describing the weights

Question 8 of 30

Choose 1
Abdul (Line Operator)
Mixer, sheeter, cutter, oven, cooler, depositor fills the tray, sealer, checkweigher.

What does the process map add?

Learn it on Day 14: How the work really flows

Technique: Process map

Question 9 of 30

Choose 1
Anika (Quality Technician)
Weigh 5 packs from every hour? Or 50 at once?

What's the data plan?

Learn it on Day 27: What can a sample tell us?

Technique: Sampling methods

Question 10 of 30

Choose 1
Ansel (Black Belt)
Before trusting the checkweigher, check it: 10 packs, 3 operators, 2 weighings each.

The gauge study gives 8% of total variation from the measurement and 14 distinct groups. Verdict?

Learn it on Day 19: Can we trust the stopwatch?

Technique: Measurement system analysis

Question 11 of 30

Choose 1
Anika (Quality Technician)
50 packs, in grams.
PackWeight (g)
P01205.1
P02212
P03207
P04201.3
P05205.8
P06208.8
P07204.3
P08204.2
P09210.2
P10204.2
P11203.7
P12207.1
P13205.9
P14206.8
P15208.1
P16202.2
P17211.9
P18203.1
P19205.8
P20208.4
P21208.4
P22209
P23209.2
P24199.8
P25207.6
P26204.2
P27204.5
P28210.6
P29209.3
P30204.3
P31208.4
P32210.8
P33208.3
P34205.9
P35200.5
P36206.2
P37204.8
P38209.6
P39206.9
P40207.3
P41205.2
P42208.5
P43201.9
P44204.5
P45207.2
P46202.1
P47207.2
P48203.6
P49204.2
P50210.6
Download the data

Which description is right?

Learn it on Day 20: The baseline in numbers

Technique: Descriptive statistics

Question 12 of 30

Choose 1
Anika (Quality Technician)
Is the process stable before we trust Cpk?
PackWeight (g)
P01205.1
P02212
P03207
P04201.3
P05205.8
P06208.8
P07204.3
P08204.2
P09210.2
P10204.2
P11203.7
P12207.1
P13205.9
P14206.8
P15208.1
P16202.2
P17211.9
P18203.1
P19205.8
P20208.4
P21208.4
P22209
P23209.2
P24199.8
P25207.6
P26204.2
P27204.5
P28210.6
P29209.3
P30204.3
P31208.4
P32210.8
P33208.3
P34205.9
P35200.5
P36206.2
P37204.8
P38209.6
P39206.9
P40207.3
P41205.2
P42208.5
P43201.9
P44204.5
P45207.2
P46202.1
P47207.2
P48203.6
P49204.2
P50210.6
Download the data

What do you check?

Learn it on Day 22: How capable is the process?

Technique: Process capability

Question 13 of 30

Choose 1
Agatha (Plant Manager)
Ready?

What must Measure confirm?

Learn it on Day 23: The Measure review

Technique: Stage gate

Crumbly

Analyse

Moisture, settings and spread

Question 14 of 30

Choose 1
Abdul (Line Operator)
Why so heavy? Operators turn the depositor up. Why? To avoid underweight rejects. Why? Weights swing with the dough. Why? Dough moisture varies between batches.

What has 5 whys found?

Learn it on Day 24: Why, why, why?

Technique: 5 Whys

Question 15 of 30

Choose 1
Anika (Quality Technician)
Depositor set too high: severity 4, occurrence 9, detection 3. Seal failure: severity 8, occurrence 2, detection 4.

Which ranks higher?

Learn it on Day 25: What could go wrong?

Technique: FMEA

Question 16 of 30

Choose 1
Anika (Quality Technician)
Is the average really above the 202 g target, and is the spread really wider than the 1.5 g the line should manage?
PackWeight (g)
P01205.1
P02212
P03207
P04201.3
P05205.8
P06208.8
P07204.3
P08204.2
P09210.2
P10204.2
P11203.7
P12207.1
P13205.9
P14206.8
P15208.1
P16202.2
P17211.9
P18203.1
P19205.8
P20208.4
P21208.4
P22209
P23209.2
P24199.8
P25207.6
P26204.2
P27204.5
P28210.6
P29209.3
P30204.3
P31208.4
P32210.8
P33208.3
P34205.9
P35200.5
P36206.2
P37204.8
P38209.6
P39206.9
P40207.3
P41205.2
P42208.5
P43201.9
P44204.5
P45207.2
P46202.1
P47207.2
P48203.6
P49204.2
P50210.6
Download the data

What do the tests show?

Learn it on Day 28: Real, or just chance?

Technique: t-test

Question 17 of 30

Choose 1
Ansel (Black Belt)
Which causes are proven?

Which list is right?

Learn it on Day 36: The Analyse review

Question 18 of 30

Choose 1
Agatha (Plant Manager)
Ruled out?

What does the Analyse review include?

Learn it on Day 36: The Analyse review

Technique: Stage gate

Crumbly

Improve

Filling to target

Question 19 of 30

Choose 1
Abdul (Line Operator)
Ideas: control dough moisture at mixing, a weight feedback loop from the checkweigher to the depositor, a fixed setting card, a new depositor.

How do you choose?

Learn it on Day 41: Ideas worth testing

Technique: Solution selection matrix

Question 20 of 30

Choose 1
Anika (Quality Technician)
14 runs: depositor setting and average pack weight.
RunDepositor settingAverage pack weight (g)
Run 166206.7
Run 259204.5
Run 355203.6
Run 448203.3
Run 549203.9
Run 641201.1
Run 742202.9
Run 840201.8
Run 945202.8
Run 1065205.4
Run 1160204.9
Run 1268206.5
Run 1355205.4
Run 1458204.9
Download the data

What setting gives 202 g?

Learn it on Day 38: How much difference would it make?

Technique: Simple linear regression

Question 21 of 30

Choose 1
Alvaro (Production Manager)
Two-week pilot: moisture control, feedback loop, setting card. 50 packs weighed.
PackPeriodWeight (g)
P01Before205.1
P02Before212
P03Before207
P04Before201.3
P05Before205.8
P06Before208.8
P07Before204.3
P08Before204.2
P09Before210.2
P10Before204.2
P11Before203.7
P12Before207.1
P13Before205.9
P14Before206.8
P15Before208.1
P16Before202.2
P17Before211.9
P18Before203.1
P19Before205.8
P20Before208.4
P21Before208.4
P22Before209
P23Before209.2
P24Before199.8
P25Before207.6
P26Before204.2
P27Before204.5
P28Before210.6
P29Before209.3
P30Before204.3
P31Before208.4
P32Before210.8
P33Before208.3
P34Before205.9
P35Before200.5
P36Before206.2
P37Before204.8
P38Before209.6
P39Before206.9
P40Before207.3
P41Before205.2
P42Before208.5
P43Before201.9
P44Before204.5
P45Before207.2
P46Before202.1
P47Before207.2
P48Before203.6
P49Before204.2
P50Before210.6
N01Pilot202.7
N02Pilot201.7
N03Pilot201.8
N04Pilot199
N05Pilot204.9
N06Pilot204
N07Pilot201.9
N08Pilot203.5
N09Pilot202.8
N10Pilot201.6
N11Pilot203.8
N12Pilot202
N13Pilot201.9
N14Pilot201.3
N15Pilot203
N16Pilot202.3
N17Pilot203.2
N18Pilot201.5
N19Pilot202.6
N20Pilot201.2
N21Pilot203.6
N22Pilot202.7
N23Pilot202.9
N24Pilot203
N25Pilot201
N26Pilot203.5
N27Pilot205.3
N28Pilot200.1
N29Pilot200
N30Pilot200.3
N31Pilot203.6
N32Pilot202.6
N33Pilot203.9
N34Pilot203.4
N35Pilot202.7
N36Pilot202.8
N37Pilot202.2
N38Pilot203.6
N39Pilot200.8
N40Pilot201.8
N41Pilot202.7
N42Pilot204.9
N43Pilot201.3
N44Pilot200.9
N45Pilot201.6
N46Pilot203.8
N47Pilot202.1
N48Pilot204.3
N49Pilot199.8
N50Pilot204
Download the data

Did it work?

Learn it on Day 43: The pilot

Technique: Plan-do-study-act

Question 22 of 30

Choose 1
Alvaro (Production Manager)
Rolling out on line 2.

What's in the plan?

Learn it on Day 44: Rolling it out

Question 23 of 30

Choose 1
Agatha (Plant Manager)
Why approve?

What does the Improve review show?

Learn it on Day 45: The Improve review

Technique: Stage gate

Crumbly

Control

Keeping the fill right

Question 24 of 30

Choose 1
Anika (Quality Technician)
After roll-out, 12 packs are weighed every hour for 15 hours.
HourPack 1Pack 2Pack 3Pack 4Pack 5Pack 6Pack 7Pack 8Pack 9Pack 10Pack 11Pack 12
Hour 1202.6202.2203.3202.5201.7202.9204.2203.7201.4200.6201.5202.5
Hour 2199.1202.1200.7201.4201.6202203203.9202.2204.3201.5202.9
Hour 3203.7202.5201.4201.1201.8202.7201202.1202.2203.2202.7202.9
Hour 4201.5202.2203.5204.5200.6204.5204.3203.5202.8202204.4205.1
Hour 5204.9204.2202.9200.7202.4203.3200.6203203203.4200.7201.5
Hour 6201.8200.8204.8201.7202.9202204.6204.2203.3199.3202.5203.4
Hour 7203.8201.5205200.6201.5203.7202.5205.2202.7201.5201.9200.9
Hour 8200.6203.3203.2204.2201.3204.8202204.6201.8201.4202.7203.8
Hour 9202.6201.6200.5200.4203.1203.8202.2200.9203.6200.6201.4203.3
Hour 10199.2202.9201.6202.6202.3202.7203.4201.3204.4203.4203.6204
Hour 11203.5203.6202.5200.4202.2201.3200.4202.8201.6201200.9202.8
Hour 12202.9204.3202.4203.9204.4204199.1204.1202.9203202.9202.9
Hour 13202.8201.9199.7202.2201.3203.9202202.5201.2201.7202.4200.3
Hour 14202.8202.3200.7199203.1202201.7202.1204.9202.3202.5200.3
Hour 15204.7203.7203.9202.5203.7202.9203.3202.2200.3203.8199.7202.1
Download the data

Which chart and limits?

Learn it on Day 49: Bigger samples

Technique: Xbar-S chart

Question 25 of 30

Choose 1
Alvaro (Production Manager)
How do we keep it?

What's in the control plan?

Learn it on Day 46: Making it stick

Technique: Control plan

Question 26 of 30

Choose 1
Abdul (Line Operator)
Operators could still override the depositor setting.

How do you prevent it?

Learn it on Day 42: Designing it right

Technique: Mistake-proofing

Question 27 of 30

Choose 1
Alvaro (Production Manager)
What am I taking on?

What's in the handover?

Learn it on Day 54: Handing over

Question 28 of 30

Choose 1
Arabella (Finance Controller)
Average weight fell from 206.33 g to 202.44 g.

What's the yearly saving?

Learn it on Day 54: Handing over

Technique: Cost of quality

Question 29 of 30

Choose 1
Ansel (Black Belt)
Final report?

What's in it?

Learn it on Day 55: Closing the project

Question 30 of 30

Choose 1
Agatha (Plant Manager)
Close it?

What closes it?

Learn it on Day 55: Closing the project

Technique: Stage gate