Clearline: a Process Improvement Specialist case study
Clearline supplies gas and electricity to 400,000 homes. Its helpline answers 2,400 calls a day, but customers wait too long: only about half are answered within 2 minutes, and 14% hang up. Complaints have doubled. You're the Green Belt asked to fix it, from the first problem statement to gains that last.
What this case study tests
Value streamKruskal-WallisMultiple regressionI-MR and EWMA charts
You're the Process Improvement Specialist. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.
Team
Ama (Process Improvement Specialist)You: the Green Belt leading the project
Ari (Workforce Planner)Rotas and call data
Agnes (Team Leader)Runs a team of 12 agents
Stakeholders
Arthur (Head of Customer Service)Sponsor
Aisling (Contact Centre Manager)Process owner
Amos (Finance Analyst)The money
Adaeze (Black Belt)Your mentor
Clearline
Define
A helpline that keeps people waiting
Question 1 of 32
Choose 1Arthur (Head of Customer Service)
Customers wait far too long on hold. Complaints doubled this year. Just hire more agents.
Question 2 of 32
Choose 1Ama (Process Improvement Specialist)
Draft: “Last quarter, only 53% of calls were answered within 2 minutes, against a target of 80%; 14% of callers hung up.” Goal?
Which goal statement is best?
Learn it on Day 7: A problem, not a solutionQuestion 3 of 32
Choose 1Aisling (Contact Centre Manager)
Should the project cover email, web chat and the complaints line too?
Question 4 of 32
Choose 1Agnes (Team Leader)
Customers say lots of things on the survey. What really matters to them?
Which critical-to-quality requirements fit the voice of the customer best?
Learn it on Day 9: What patients really needQuestion 5 of 32
Choose 1Ari (Workforce Planner)
53% of calls answered within 2 minutes. What sigma level is that, on the usual scale?
Question 6 of 32
Choose 1Amos (Finance Analyst)
What does all this waiting actually cost us?
Callers who hang up: 336 a day; 60% call back (€1.80 per call handled); 2% of those who hang up leave for another supplier (€180 margin a year). Over 250 working days, what is the yearly cost of poor quality?
Learn it on Day 5: Which problem first?Question 7 of 32
Choose 1Aisling (Contact Centre Manager)
Who should be on the project team? My agents are flat out.
Question 8 of 32
Choose 1Arthur (Head of Customer Service)
Here's your charter. Can I sign it now and add “move to a new phone system” as the solution?
Clearline
Measure
Where the time goes, and data you can trust
Question 9 of 32
Choose 1Ari (Workforce Planner)
The menu takes 75 seconds, 18% of calls go to the wrong team and wait again, talk is 6 minutes, wrap-up 1 minute. The wait for an agent varies.
What does a value stream show here?
Learn it on Day 15: Where does the time go?Question 10 of 32
Choose 1Ari (Workforce Planner)
Hold time: from dialling? From the end of the menu? Until the agent says hello?
What's the best operational definition?
Learn it on Day 17: What exactly do we count?Question 11 of 32
Choose 1Agnes (Team Leader)
Three agents coded the reason for the same 20 recorded calls. They matched the expert coder 70%, 75% and 85% of the time; all three matched on only 11 calls.
What do you conclude?
Learn it on Day 18: Do we agree what's urgent?Question 12 of 32
Choose 1Ari (Workforce Planner)
Download the data
Here are 36 hold times from last week, 12 per shift.
| Call | Shift | Hold (seconds) |
|---|---|---|
| C01 | Early | 86 |
| C02 | Early | 115 |
| C03 | Early | 85 |
| C04 | Early | 32 |
| C05 | Early | 121 |
| C06 | Early | 91 |
| C07 | Early | 51 |
| C08 | Early | 99 |
| C09 | Early | 87 |
| C10 | Early | 84 |
| C11 | Early | 71 |
| C12 | Early | 97 |
| C13 | Mid-morning | 131 |
| C14 | Mid-morning | 175 |
| C15 | Mid-morning | 149 |
| C16 | Mid-morning | 256 |
| C17 | Mid-morning | 194 |
| C18 | Mid-morning | 164 |
| C19 | Mid-morning | 129 |
| C20 | Mid-morning | 167 |
| C21 | Mid-morning | 191 |
| C22 | Mid-morning | 166 |
| C23 | Mid-morning | 363 |
| C24 | Mid-morning | 314 |
| C25 | Late | 21 |
| C26 | Late | 34 |
| C27 | Late | 86 |
| C28 | Late | 75 |
| C29 | Late | 107 |
| C30 | Late | 107 |
| C31 | Late | 305 |
| C32 | Late | 52 |
| C33 | Late | 77 |
| C34 | Late | 292 |
| C35 | Late | 136 |
| C36 | Late | 137 |
Which description is right?
Learn it on Day 20: The baseline in numbersQuestion 13 of 32
Choose 1Ari (Workforce Planner)
Download the data
17 of the 36 calls waited more than 120 seconds.
| Call | Shift | Hold (seconds) |
|---|---|---|
| C01 | Early | 86 |
| C02 | Early | 115 |
| C03 | Early | 85 |
| C04 | Early | 32 |
| C05 | Early | 121 |
| C06 | Early | 91 |
| C07 | Early | 51 |
| C08 | Early | 99 |
| C09 | Early | 87 |
| C10 | Early | 84 |
| C11 | Early | 71 |
| C12 | Early | 97 |
| C13 | Mid-morning | 131 |
| C14 | Mid-morning | 175 |
| C15 | Mid-morning | 149 |
| C16 | Mid-morning | 256 |
| C17 | Mid-morning | 194 |
| C18 | Mid-morning | 164 |
| C19 | Mid-morning | 129 |
| C20 | Mid-morning | 167 |
| C21 | Mid-morning | 191 |
| C22 | Mid-morning | 166 |
| C23 | Mid-morning | 363 |
| C24 | Mid-morning | 314 |
| C25 | Late | 21 |
| C26 | Late | 34 |
| C27 | Late | 86 |
| C28 | Late | 75 |
| C29 | Late | 107 |
| C30 | Late | 107 |
| C31 | Late | 305 |
| C32 | Late | 52 |
| C33 | Late | 77 |
| C34 | Late | 292 |
| C35 | Late | 136 |
| C36 | Late | 137 |
How do you report capability against the 2-minute requirement?
Learn it on Day 22: How capable is the process?Question 14 of 32
Choose 1Arthur (Head of Customer Service)
So, are you ready to look for causes?
Clearline
Analyse
Proving the causes
Question 15 of 32
Choose 1Agnes (Team Leader)
We brainstormed 19 possible causes. We can't study them all.
How do you choose which to study first?
Learn it on Day 16: What could be causing it?Question 16 of 32
Choose 1Ari (Workforce Planner)
Menu misroute: severity 6, occurrence 7, detection 6. Agents logged off without cover: severity 7, occurrence 4, detection 3.
Which has the higher risk priority number, and why does it matter?
Learn it on Day 25: What could go wrong?Question 17 of 32
Choose 1Ari (Workforce Planner)
Download the data
Hold times by shift: early median 86.5 seconds, mid-morning 171, late 96.5. The data is skewed.
| Call | Shift | Hold (seconds) |
|---|---|---|
| C01 | Early | 86 |
| C02 | Early | 115 |
| C03 | Early | 85 |
| C04 | Early | 32 |
| C05 | Early | 121 |
| C06 | Early | 91 |
| C07 | Early | 51 |
| C08 | Early | 99 |
| C09 | Early | 87 |
| C10 | Early | 84 |
| C11 | Early | 71 |
| C12 | Early | 97 |
| C13 | Mid-morning | 131 |
| C14 | Mid-morning | 175 |
| C15 | Mid-morning | 149 |
| C16 | Mid-morning | 256 |
| C17 | Mid-morning | 194 |
| C18 | Mid-morning | 164 |
| C19 | Mid-morning | 129 |
| C20 | Mid-morning | 167 |
| C21 | Mid-morning | 191 |
| C22 | Mid-morning | 166 |
| C23 | Mid-morning | 363 |
| C24 | Mid-morning | 314 |
| C25 | Late | 21 |
| C26 | Late | 34 |
| C27 | Late | 86 |
| C28 | Late | 75 |
| C29 | Late | 107 |
| C30 | Late | 107 |
| C31 | Late | 305 |
| C32 | Late | 52 |
| C33 | Late | 77 |
| C34 | Late | 292 |
| C35 | Late | 136 |
| C36 | Late | 137 |
Which test, and what does it show?
Learn it on Day 32: Checking with ranks and mediansQuestion 18 of 32
Choose 1Adaeze (Black Belt)
Which causes can you now call proven?
Which list is right?
Learn it on Day 36: The Analyse reviewQuestion 19 of 32
Choose 1Arthur (Head of Customer Service)
Good. Can we move on?
Clearline
Improve
Testing what works
Question 20 of 32
Choose 1Agnes (Team Leader)
Ideas: re-roster to the call pattern, a shorter menu with 4 options, a call-back offer, a new phone system, 15 extra agents.
Question 21 of 32
Choose 1Ari (Workforce Planner)
Download the data
16 half-hours: agents on phones, calls per hour and average hold time.
| Half hour | Agents on phones | Calls per hour | Average hold (seconds) |
|---|---|---|---|
| H1 | 22 | 267 | 44 |
| H2 | 14 | 274 | 130 |
| H3 | 15 | 155 | 26 |
| H4 | 16 | 169 | 15 |
| H5 | 15 | 226 | 79 |
| H6 | 22 | 216 | 15 |
| H7 | 23 | 300 | 64 |
| H8 | 20 | 237 | 27 |
| H9 | 14 | 221 | 83 |
| H10 | 15 | 223 | 82 |
| H11 | 17 | 263 | 113 |
| H12 | 18 | 249 | 63 |
| H13 | 20 | 179 | 15 |
| H14 | 19 | 275 | 91 |
| H15 | 16 | 278 | 104 |
| H16 | 15 | 312 | 152 |
What does the regression tell you about re-rostering?
Learn it on Day 39: Two causes at onceQuestion 22 of 32
Choose 1Aisling (Contact Centre Manager)
Can we switch the new rota and menu on for everyone tomorrow?
Question 23 of 32
Choose 1Aisling (Contact Centre Manager)
The pilot worked. How do we roll it out?
What does the implementation plan need?
Learn it on Day 44: Rolling it outQuestion 24 of 32
Choose 1Arthur (Head of Customer Service)
Show me why I should approve the roll-out.
Clearline
Control
Making it last
Question 25 of 32
Choose 1Ari (Workforce Planner)
Download the data
After roll-out we record the average hold time each day: 20 days of data.
| Day | Average hold (seconds) |
|---|---|
| Day 1 | 63 |
| Day 2 | 61 |
| Day 3 | 66 |
| Day 4 | 63 |
| Day 5 | 58 |
| Day 6 | 65 |
| Day 7 | 71 |
| Day 8 | 69 |
| Day 9 | 57 |
| Day 10 | 53 |
| Day 11 | 58 |
| Day 12 | 62 |
| Day 13 | 46 |
| Day 14 | 60 |
| Day 15 | 53 |
| Day 16 | 57 |
| Day 17 | 58 |
| Day 18 | 60 |
| Day 19 | 65 |
| Day 20 | 69 |
Question 26 of 32
Choose 1Adaeze (Black Belt)
Hold times could creep up slowly if agents drift back to the old breaks. Will the I-MR chart catch a 5-second creep quickly?
Question 27 of 32
Choose 1Aisling (Contact Centre Manager)
How do I keep this going when you've gone?
Question 28 of 32
Choose 1Agnes (Team Leader)
Agents still sometimes pick the wrong reason code under pressure.
Question 29 of 32
Choose 1Aisling (Contact Centre Manager)
What exactly am I taking on?
What does a good handover include?
Learn it on Day 54: Handing overQuestion 30 of 32
Choose 1Amos (Finance Analyst)
Three months on: abandoned calls are down from 336 a day to 110, using the same method as the cost of poor quality.
Question 31 of 32
Choose 1Adaeze (Black Belt)
How will the next team learn from this?
What goes into the final report?
Learn it on Day 55: Closing the projectQuestion 32 of 32
Choose 1Arthur (Head of Customer Service)
Anything else before we close?