Building permits30 questions5 phases
Permitly: a Process Improvement Specialist case study
The council's building permit team receives 400 applications a month. More than half are sent back to applicants for errors, adding weeks of delay and a lot of rework. You're the Green Belt asked to get applications right the first time.
What this case study tests
DPMO and rolled yieldAttribute agreementChi-squareU chart
You're the Process Improvement Specialist. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.
Team
Akosua (Process Improvement Specialist)You: the Green Belt leading the project
Aidan (Systems Officer)The permit system and its data
Amelie (Permit Officer)Checks 20 applications a day
Stakeholders
Augustine (Head of Planning)Sponsor
Anneke (Permits Team Manager)Process owner
Aziz (Finance Officer)The money
Alejandro (Black Belt)Your mentor
Permitly
Define
Half the applications come back
Question 1 of 30
Choose 1Augustine (Head of Planning)
Builders complain permits take months. Half the applications come back to them with errors.
Question 2 of 30
Choose 1Anneke (Permits Team Manager)
Planning permission, building permits and tree works all use similar forms.
Question 3 of 30
Choose 1Amelie (Permit Officer)
Builders say: tell us once what you need, and don't send it back for small things.
Which critical-to-quality requirements follow?
Learn it on Day 9: What patients really needQuestion 4 of 30
Choose 1Aidan (Systems Officer)
400 applications last month, each with 6 sections that can be wrong; 528 errors found. Form first-time right 48%, council check first-time right 80%, consultation 92%.
Which baseline figures are right?
Learn it on Day 7: A problem, not a solutionQuestion 5 of 30
Choose 1Aziz (Finance Officer)
What do returned applications cost us?
52% of 400 applications a month are returned; each return costs €35 of officer time. What is the yearly cost to the council?
Learn it on Day 5: Which problem first?Question 6 of 30
Choose 1Anneke (Permits Team Manager)
Who's on the team?
Question 7 of 30
Choose 1Augustine (Head of Planning)
Sign now, with “new website” as the deliverable?
Permitly
Measure
Counting errors you can trust
Question 8 of 30
Choose 1Amelie (Permit Officer)
An application comes in, gets checked, goes back to the applicant, comes in again, sometimes three times.
Question 9 of 30
Choose 1Aidan (Systems Officer)
What counts as an error?
What does the data plan need?
Learn it on Day 17: What exactly do we count?Question 10 of 30
Choose 1Alejandro (Black Belt)
Three officers classify 25 errors into types. They match the lead officer 88%, 76% and 84% of the time; all three match on 16 of 25.
Question 11 of 30
Choose 1Aidan (Systems Officer)
Errors per application: 0 for many, 1 or 2 for most, up to 6 for a few.
How do you describe this data?
Learn it on Day 20: The baseline in numbersQuestion 12 of 30
Choose 1Anneke (Permits Team Manager)
48% of applications are complete first time.
Question 13 of 30
Choose 1Augustine (Head of Planning)
Ready?
Permitly
Analyse
Which errors, and why
Question 14 of 30
Choose 1Amelie (Permit Officer)
We've got 26 possible causes on the fishbone.
Question 15 of 30
Choose 1Aidan (Systems Officer)
Wrong fee: severity 5, occurrence 8, detection 2. Missing ownership certificate: severity 8, occurrence 4, detection 5.
Question 16 of 30
Choose 1Aidan (Systems Officer)
Download the data
Error types by channel (online or paper), 220 errors.
| Channel | Drawings missing | Fee wrong | Site plan unclear | Ownership certificate missing |
|---|---|---|---|---|
| Online | 38 | 22 | 9 | 11 |
| Paper | 30 | 54 | 31 | 25 |
Is the type of error linked to the channel?
Learn it on Day 35: The vicious circleQuestion 17 of 30
Choose 1Alejandro (Black Belt)
Which causes are proven?
Which list is right?
Learn it on Day 36: The Analyse reviewQuestion 18 of 30
Choose 1Augustine (Head of Planning)
What's ruled out?
Permitly
Improve
Forms that are hard to get wrong
Question 19 of 30
Choose 1Amelie (Permit Officer)
Ideas: a smart online form that asks for drawings by project type, a fee calculator, a new paper guidance sheet, a whole new website.
Question 20 of 30
Choose 1Aidan (Systems Officer)
Download the data
Groups of applicants: guidance pages read and average errors per application.
| Applicant | Guidance pages read | Errors per application (group average) |
|---|---|---|
| G01 | 7 | 0.63 |
| G02 | 5 | 0.83 |
| G03 | 4 | 1.16 |
| G04 | 2 | 1.67 |
| G05 | 2 | 1.08 |
| G06 | 0 | 1.95 |
| G07 | 0 | 1.69 |
| G08 | 0 | 1.82 |
| G09 | 1 | 1.69 |
| G10 | 7 | 0.73 |
| G11 | 5 | 1.25 |
| G12 | 8 | 0.9 |
| G13 | 4 | 1.29 |
| G14 | 5 | 1.49 |
| G15 | 8 | 0.47 |
| G16 | 6 | 1.07 |
What does it suggest?
Learn it on Day 37: Measuring the likely causeQuestion 21 of 30
Choose 1Anneke (Permits Team Manager)
Pilot for 6 weeks: 61 of 380 applications returned, against 208 of 400 before.
Question 22 of 30
Choose 1Anneke (Permits Team Manager)
How do we roll it out?
What's in the plan?
Learn it on Day 44: Rolling it outQuestion 23 of 30
Choose 1Augustine (Head of Planning)
Why approve?
Permitly
Control
Keeping errors down
Question 24 of 30
Choose 1Aidan (Systems Officer)
Download the data
After roll-out: errors found per day, with 15 to 25 applications a day. An application can have several errors.
| Day | Applications checked | Errors found | Errors per application |
|---|---|---|---|
| Day 1 | 24 | 14 | 0.58 |
| Day 2 | 22 | 8 | 0.36 |
| Day 3 | 20 | 13 | 0.65 |
| Day 4 | 17 | 11 | 0.65 |
| Day 5 | 18 | 7 | 0.39 |
| Day 6 | 15 | 4 | 0.27 |
| Day 7 | 15 | 5 | 0.33 |
| Day 8 | 15 | 8 | 0.53 |
| Day 9 | 16 | 13 | 0.81 |
| Day 10 | 23 | 19 | 0.83 |
| Day 11 | 22 | 15 | 0.68 |
| Day 12 | 25 | 14 | 0.56 |
| Day 13 | 20 | 5 | 0.25 |
| Day 14 | 21 | 7 | 0.33 |
| Day 15 | 25 | 8 | 0.32 |
| Day 16 | 23 | 8 | 0.35 |
| Day 17 | 21 | 15 | 0.71 |
| Day 18 | 20 | 5 | 0.25 |
| Day 19 | 21 | 9 | 0.43 |
| Day 20 | 25 | 9 | 0.36 |
Question 25 of 30
Choose 1Anneke (Permits Team Manager)
How do we keep this?
Question 26 of 30
Choose 1Amelie (Permit Officer)
Applicants can still skip uploading drawings.
Question 27 of 30
Choose 1Anneke (Permits Team Manager)
What am I taking on?
What's in the handover?
Learn it on Day 54: Handing overQuestion 28 of 30
Choose 1Aziz (Finance Officer)
After roll-out, 16% of applications are returned instead of 52%.
What's the yearly benefit in officer time?
Learn it on Day 54: Handing overQuestion 29 of 30
Choose 1Alejandro (Black Belt)
What goes in the final report?
Which is right?
Learn it on Day 55: Closing the projectQuestion 30 of 30
Choose 1Augustine (Head of Planning)
Close it?