Commercial printing30 questions5 phases
Inkwell: a Process Improvement Specialist case study
Inkwell prints brochures and packaging on two large presses: 40 million sheets a year. 4.2% are rejected for smudges, colour and other defects, and customers are complaining. You're the Green Belt asked to cut the waste.
What this case study tests
F-test and unequal-variances t-testMultiple regressionConfidence intervalU chart
You're the Process Improvement Specialist. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.
Team
Athena (Process Improvement Specialist)You: the Green Belt leading the project
Alvin (Colour Technician)Measures colour and defects
Abram (Press Operator)Runs press 2
Stakeholders
Archibald (Managing Director)Sponsor
Alisha (Print Production Manager)Process owner
Antoine (Finance Manager)The money
Aubrey (Black Belt)Your mentor
Inkwell
Define
Too many sheets in the bin
Question 1 of 30
Choose 1Archibald (Managing Director)
We reprint too much. Customers complain about smudges and colour.
Which problem statement is best?
Learn it on Day 7: A problem, not a solutionQuestion 2 of 30
Choose 1Alisha (Print Production Manager)
Prepress, printing, finishing and packing all touch the job.
Question 3 of 30
Choose 1Alvin (Colour Technician)
Customers want clean sheets and colour that matches the proof.
Question 4 of 30
Choose 1Alvin (Colour Technician)
0.042 defects per sheet; each sheet has 4 opportunities (smudge, colour, registration, crease).
What are the baseline metrics?
Learn it on Day 7: A problem, not a solutionQuestion 5 of 30
Choose 1Antoine (Finance Manager)
What do rejects cost?
40 million sheets a year; 4.2% rejected; each rejected sheet costs €0.09 in paper, ink and press time. Yearly cost?
Learn it on Day 5: Which problem first?Question 6 of 30
Choose 1Alisha (Print Production Manager)
Who's on it?
Question 7 of 30
Choose 1Archibald (Managing Director)
Sign with “replace press 2”?
Inkwell
Measure
Sampling, inspection and two presses
Question 8 of 30
Choose 1Abram (Press Operator)
Make-ready, colour set, run, inspect at the end, stack.
Question 9 of 30
Choose 1Aubrey (Black Belt)
You'll inspect 8,000 sheets; 336 are rejected. How precise is the 4.2%?
What's the 95% confidence interval?
Learn it on Day 27: What can a sample tell us?Question 10 of 30
Choose 1Alvin (Colour Technician)
Inspectors judge “smudged or not” by eye. Three inspectors agree with the colour lab on 70%, 80% and 85% of 30 sheets.
Question 11 of 30
Choose 1Alvin (Colour Technician)
Download the data
Colour error on 20 sheets from each press.
| Sheet | Press | Colour error (units) |
|---|---|---|
| S01 | Press 1 | 2.19 |
| S02 | Press 1 | 1.84 |
| S03 | Press 1 | 1.89 |
| S04 | Press 1 | 0.88 |
| S05 | Press 1 | 3 |
| S06 | Press 1 | 2.67 |
| S07 | Press 1 | 1.94 |
| S08 | Press 1 | 2.49 |
| S09 | Press 1 | 2.24 |
| S10 | Press 1 | 1.82 |
| S11 | Press 1 | 2.59 |
| S12 | Press 1 | 1.94 |
| S13 | Press 1 | 1.94 |
| S14 | Press 1 | 1.7 |
| S15 | Press 1 | 2.33 |
| S16 | Press 1 | 2.05 |
| S17 | Press 1 | 2.37 |
| S18 | Press 1 | 1.8 |
| S19 | Press 1 | 2.16 |
| S20 | Press 1 | 1.65 |
| S21 | Press 2 | 3.66 |
| S22 | Press 2 | 3.07 |
| S23 | Press 2 | 3.2 |
| S24 | Press 2 | 3.27 |
| S25 | Press 2 | 1.99 |
| S26 | Press 2 | 3.6 |
| S27 | Press 2 | 4.75 |
| S28 | Press 2 | 1.43 |
| S29 | Press 2 | 1.34 |
| S30 | Press 2 | 1.55 |
| S31 | Press 2 | 3.66 |
| S32 | Press 2 | 3.02 |
| S33 | Press 2 | 3.87 |
| S34 | Press 2 | 3.55 |
| S35 | Press 2 | 3.09 |
| S36 | Press 2 | 3.16 |
| S37 | Press 2 | 2.75 |
| S38 | Press 2 | 3.68 |
| S39 | Press 2 | 1.88 |
| S40 | Press 2 | 2.52 |
How do you describe it?
Learn it on Day 20: The baseline in numbersQuestion 12 of 30
Choose 1Alisha (Print Production Manager)
4.2% rejected.
Question 13 of 30
Choose 1Archibald (Managing Director)
Ready?
Inkwell
Analyse
Damp paper, speed and worn keys
Question 14 of 30
Choose 1Abram (Press Operator)
Download the data
Defect types from a month of inspections.
| Defect | Share of defects |
|---|---|
| Smudging | 48% |
| Colour off | 27% |
| Misregistration | 15% |
| Creases | 10% |
What does the Pareto show, and what next?
Learn it on Day 3: Eight kinds of wasteQuestion 15 of 30
Choose 1Alvin (Colour Technician)
Smudging from damp paper: severity 6, occurrence 7, detection 7. Wrong plate: severity 8, occurrence 1, detection 2.
Question 16 of 30
Choose 1Alvin (Colour Technician)
Download the data
Colour error: press 1 against press 2, 20 sheets each.
| Sheet | Press | Colour error (units) |
|---|---|---|
| S01 | Press 1 | 2.19 |
| S02 | Press 1 | 1.84 |
| S03 | Press 1 | 1.89 |
| S04 | Press 1 | 0.88 |
| S05 | Press 1 | 3 |
| S06 | Press 1 | 2.67 |
| S07 | Press 1 | 1.94 |
| S08 | Press 1 | 2.49 |
| S09 | Press 1 | 2.24 |
| S10 | Press 1 | 1.82 |
| S11 | Press 1 | 2.59 |
| S12 | Press 1 | 1.94 |
| S13 | Press 1 | 1.94 |
| S14 | Press 1 | 1.7 |
| S15 | Press 1 | 2.33 |
| S16 | Press 1 | 2.05 |
| S17 | Press 1 | 2.37 |
| S18 | Press 1 | 1.8 |
| S19 | Press 1 | 2.16 |
| S20 | Press 1 | 1.65 |
| S21 | Press 2 | 3.66 |
| S22 | Press 2 | 3.07 |
| S23 | Press 2 | 3.2 |
| S24 | Press 2 | 3.27 |
| S25 | Press 2 | 1.99 |
| S26 | Press 2 | 3.6 |
| S27 | Press 2 | 4.75 |
| S28 | Press 2 | 1.43 |
| S29 | Press 2 | 1.34 |
| S30 | Press 2 | 1.55 |
| S31 | Press 2 | 3.66 |
| S32 | Press 2 | 3.02 |
| S33 | Press 2 | 3.87 |
| S34 | Press 2 | 3.55 |
| S35 | Press 2 | 3.09 |
| S36 | Press 2 | 3.16 |
| S37 | Press 2 | 2.75 |
| S38 | Press 2 | 3.68 |
| S39 | Press 2 | 1.88 |
| S40 | Press 2 | 2.52 |
What do the tests show?
Learn it on Day 30: What happened in week 12?Question 17 of 30
Choose 1Aubrey (Black Belt)
Which causes are proven?
Which list is right?
Learn it on Day 36: The Analyse reviewQuestion 18 of 30
Choose 1Archibald (Managing Director)
Ruled out?
Inkwell
Improve
Dry paper, steady speed, good keys
Question 19 of 30
Choose 1Abram (Press Operator)
Ideas: a dehumidified paper store, speed limits by paper weight, new ink keys on press 2, in-run camera inspection, a new press.
Question 20 of 30
Choose 1Alvin (Colour Technician)
Download the data
18 runs: humidity, speed and smudge defects per 1,000 sheets.
| Run | Humidity (%) | Speed (thousand sheets an hour) | Smudge defects per 1,000 sheets |
|---|---|---|---|
| Run 1 | 65 | 13.6 | 27.6 |
| Run 2 | 57 | 12.9 | 25.9 |
| Run 3 | 53 | 8 | 20.6 |
| Run 4 | 44 | 13.1 | 23.1 |
| Run 5 | 46 | 8.2 | 19 |
| Run 6 | 36 | 12.4 | 21.9 |
| Run 7 | 37 | 9.1 | 19.3 |
| Run 8 | 35 | 13.2 | 23.1 |
| Run 9 | 41 | 11.2 | 22.1 |
| Run 10 | 64 | 9.8 | 23.5 |
| Run 11 | 58 | 10.5 | 23.8 |
| Run 12 | 67 | 8.2 | 24 |
| Run 13 | 53 | 8.7 | 22.9 |
| Run 14 | 56 | 12 | 23.8 |
| Run 15 | 69 | 11.9 | 29.3 |
| Run 16 | 61 | 11.7 | 27.5 |
| Run 17 | 57 | 10.3 | 24.5 |
| Run 18 | 54 | 14 | 27.4 |
What do humidity and speed limits buy?
Learn it on Day 39: Two causes at onceQuestion 21 of 30
Choose 1Alisha (Print Production Manager)
Pilot for 4 weeks with all changes.
Question 22 of 30
Choose 1Alisha (Print Production Manager)
Roll it out.
What's in the plan?
Learn it on Day 44: Rolling it outQuestion 23 of 30
Choose 1Archibald (Managing Director)
Why approve?
Inkwell
Control
Keeping sheets clean
Question 24 of 30
Choose 1Alvin (Colour Technician)
Download the data
After roll-out: defects found per day in 200 to 300 inspected sheets.
| Day | Sheets inspected | Defects found | Defects per sheet |
|---|---|---|---|
| Day 1 | 285 | 1 | 0.0035 |
| Day 2 | 264 | 1 | 0.0038 |
| Day 3 | 251 | 4 | 0.0159 |
| Day 4 | 227 | 1 | 0.0044 |
| Day 5 | 231 | 2 | 0.0087 |
| Day 6 | 204 | 6 | 0.0294 |
| Day 7 | 207 | 1 | 0.0048 |
| Day 8 | 201 | 3 | 0.0149 |
| Day 9 | 217 | 4 | 0.0184 |
| Day 10 | 282 | 4 | 0.0142 |
| Day 11 | 265 | 3 | 0.0113 |
| Day 12 | 292 | 2 | 0.0068 |
| Day 13 | 250 | 2 | 0.008 |
| Day 14 | 261 | 2 | 0.0077 |
| Day 15 | 298 | 2 | 0.0067 |
| Day 16 | 273 | 3 | 0.011 |
| Day 17 | 263 | 2 | 0.0076 |
| Day 18 | 254 | 6 | 0.0236 |
| Day 19 | 256 | 7 | 0.0273 |
| Day 20 | 294 | 7 | 0.0238 |
Question 25 of 30
Choose 1Alisha (Print Production Manager)
How do we keep it?
Question 26 of 30
Choose 1Abram (Press Operator)
Operators might run heavy paper too fast when a job is late.
Question 27 of 30
Choose 1Alisha (Print Production Manager)
What am I taking on?
What's in the handover?
Learn it on Day 54: Handing overQuestion 28 of 30
Choose 1Antoine (Finance Manager)
Rejects fell from 4.2% to 1.24%.
Question 29 of 30
Choose 1Aubrey (Black Belt)
Final report?
What's in it?
Learn it on Day 55: Closing the projectQuestion 30 of 30
Choose 1Archibald (Managing Director)
Close it?