← Cost baseline: explanationFilled-in example Blank template
Day in the RoleCost baselineBudget, reserves and spending profile
Version1.0
Date15 March
Amounts in€ thousands
Approved onTuesday, month 1

Cost per deliverable

WBSDelive­rableEstimate
1Building3,000
2Equipment650
3Booking system200
4People120
5Licence and opening30
6Project management50
Total work estimates4,050

From estimates to funding

Work estimates4,050Bottom-up, from the WBS
+ Contingency reserve150For identified risks · project manager
= Cost baseline4,200Approved yardstick for spending
+ Management reserve300For the unknown · sponsor approves use
= Total funding4,500What the funder sets aside

Spending over time

01,0502,1003,1504,200M1M2M3M4M5M6M7

Bars: planned spend per month. Line: cumulative spend (the S-curve).

MonthM1M2M3M4M5M6M7
Planned1503509001,000900600300
Cumulative1505001,4002,4003,3003,9004,200

Letters and symbols: WBS Work breakdown structure · €k Thousands of euros (€150k = €150,000) · Wk · M1 Week and month numbers in schedules (Wk 26 = week 26, M3 = month 3)

Day in the Role · Cost baselineIllustrative example · not a real project or organisation · dayintherole.com