Day in the RoleCost baselineBudget, reserves and spending profile
Amounts in€ thousands
Approved onTuesday, month 1
Cost per deliverable
| WBS | Deliverable | Estimate |
|---|
| 1 | Building | 3,000 |
| 2 | Equipment | 650 |
| 3 | Booking system | 200 |
| 4 | People | 120 |
| 5 | Licence and opening | 30 |
| 6 | Project management | 50 |
Total work estimates4,050
From estimates to funding
Work estimates4,050Bottom-up, from the WBS
+ Contingency reserve150For identified risks · project manager
= Cost baseline4,200Approved yardstick for spending
+ Management reserve300For the unknown · sponsor approves use
= Total funding4,500What the funder sets aside
Spending over time
Bars: planned spend per month. Line: cumulative spend (the S-curve).
| Month | M1 | M2 | M3 | M4 | M5 | M6 | M7 |
|---|
| Planned | 150 | 350 | 900 | 1,000 | 900 | 600 | 300 |
| Cumulative | 150 | 500 | 1,400 | 2,400 | 3,300 | 3,900 | 4,200 |
Letters and symbols: WBS Work breakdown structure · €k Thousands of euros (€150k = €150,000) · Wk · M1 Week and month numbers in schedules (Wk 26 = week 26, M3 = month 3)