Day in the RoleCost baselineBudget, reserves and spending profile
Version
Date
Amounts in
Approved on

Cost per deliverable

WBSDelive­rableEstimate
Total work estimates

From estimates to funding

Work estimatesBottom-up, from the WBS
+ Contingency reserveFor identified risks · project manager
= Cost baselineApproved yardstick for spending
+ Management reserveFor the unknown · sponsor approves use
= Total fundingWhat the funder sets aside

Spending over time

M1M2M3M4M5M6M7

Bars: planned spend per month. Line: cumulative spend (the S-curve). Draw both by hand.

MonthM1M2M3M4M5M6M7

Letters and symbols: WBS Work breakdown structure · Wk · M1 Week and month numbers in schedules (Wk 26 = week 26, M3 = month 3)