Day in the RoleStatus reportWhere we are against the baselines
Version
Date
Reporting period
OverallRAG
Why

Status by area

AreaStatusWhy
ScopeRAG
TimeRAG
CostRAG
QualityRAG
RiskRAG

Green: on plan. Amber: off plan, recoverable within tolerance, with a plan. Red: beyond tolerance or needs a decision.

Performance (€ thousands)

PVPlanned value
EVEarned value
ACActual cost
SPIEV ÷ PV
CPIEV ÷ AC

SPI or CPI below 1 means behind schedule or over cost.

Done this period

Next period

Top risks and issues

Decisions needed from you

Letters and symbols: AC Actual cost: what the work done so far really cost · CPI Cost performance index: earned value ÷ actual cost. Below 1 means over cost · EV Earned value: the budgeted cost of the work actually done · PV Planned value: the budgeted cost of the work planned by now · SPI Schedule performance index: earned value ÷ planned value. Below 1 means behind schedule · R · A · G Red, amber, green: status lights · ÷ × Divided by, multiplied by · €k Thousands of euros (€150k = €150,000)