| Version | 1.0 |
|---|---|
| Date | 15 March |
Two weeks behind on building works with a recovery plan; booking tests at 50%.
| Area | Status | Why |
|---|---|---|
| Scope | RAG | No unapproved changes |
| Time | RAG | Building works 2 weeks behind; recovery plan agreed |
| Cost | RAG | CPI 0.98; forecast inside baseline |
| Quality | RAG | Ventilation defect fixed; booking tests at 50% pass |
| Risk | RAG | Licence inspection not yet booked |
Green: on plan. Amber: off plan, recoverable within tolerance, with a plan. Red: beyond tolerance or needs a decision.
SPI or CPI below 1 means behind schedule or over cost.
None this week. A possible exception on the booking system next week.
Letters and symbols: AC Actual cost: what the work done so far really cost · CPI Cost performance index: earned value ÷ actual cost. Below 1 means over cost · EV Earned value: the budgeted cost of the work actually done · PV Planned value: the budgeted cost of the work planned by now · SPI Schedule performance index: earned value ÷ planned value. Below 1 means behind schedule · R · A · G Red, amber, green: status lights · ÷ × Divided by, multiplied by · €k Thousands of euros (€150k = €150,000)