← Status report: explanationFilled-in example Blank template
Day in the RoleStatus reportWhere we are against the baselines
Version1.0
Date15 March
Reporting periodMonth 4 (weeks 14 to 17)
OverallRAG
Why

Two weeks behind on building works with a recovery plan; booking tests at 50%.

Status by area

AreaStatusWhy
ScopeRAGNo unapproved changes
TimeRAGBuilding works 2 weeks behind; recovery plan agreed
CostRAGCPI 0.98; forecast inside baseline
QualityRAGVentilation defect fixed; booking tests at 50% pass
RiskRAGLicence inspection not yet booked

Green: on plan. Amber: off plan, recoverable within tolerance, with a plan. Red: beyond tolerance or needs a decision.

Performance (€ thousands)

PVPlanned value2,400
EVEarned value2,200
ACActual cost2,250
SPIEV ÷ PV0.92
CPIEV ÷ AC0.98

SPI or CPI below 1 means behind schedule or over cost.

Done this period

  • Asbestos removed and certified
  • Structure repaired
  • 9 clinical staff hired

Next period

  • Treatment room fit-out
  • Booking system test cycle 2
  • Book licence inspection

Top risks and issues

  • Booking system tests failing (recovery plan Friday)
  • Building works recovery
  • Licence inspection backlog
Decisions needed from you

None this week. A possible exception on the booking system next week.

Letters and symbols: AC Actual cost: what the work done so far really cost · CPI Cost performance index: earned value ÷ actual cost. Below 1 means over cost · EV Earned value: the budgeted cost of the work actually done · PV Planned value: the budgeted cost of the work planned by now · SPI Schedule performance index: earned value ÷ planned value. Below 1 means behind schedule · R · A · G Red, amber, green: status lights · ÷ × Divided by, multiplied by · €k Thousands of euros (€150k = €150,000)

Day in the Role · Status reportIllustrative example · not a real project or organisation · dayintherole.com