← Project schedule: explanationFilled-in example Blank template
Day in the RoleProject scheduleGantt chart · weeks 1 to 30
Version1.0
Date15 March
ActivityCritical path (no slack)◆ MilestoneShade the weeks for each activity; mark critical bars darker.
IDActivityDur.AfterMonth 1Month 2Month 3Month 4Month 5Month 6Month 7
123456789101112131415161718192021222324252627282930
A1Survey and design7 wk
A2Purchase completes1 wkA1
A3Asbestos removal3 wkA2
A4Building works14 wkA3
A5Equipment order and delivery14 wkA1
A6Booking system setup10 wkA2
A7Hiring12 wkA2
A8Training5 wkA6, A7
A9Equipment installation2 wkA4, A5
A10Inspection1 wkA9
A11Licence2 wkA10
A12Opening–A8, A11◆

Critical path and slack

Critical path: A1 → A2 → A3 → A4 → A9 → A10 → A11 → A12, no slack. Hiring (A7) and training (A8) have 5 weeks of slack.

Letters and symbols: ID Identifier: a reference number or code · ◆ A milestone or decision point

Day in the Role · Project scheduleIllustrative example · not a real project or organisation · dayintherole.com