← Change request: explanationFilled-in example Blank template
Day in the RoleChange requestRequest · impact · decision
Change no.CR-07
Raised byAmani (Clinical Lead)
DateWeek 22
TypeScope

1. What change?

Move two walls in the treatment area so a wheelchair and a trolley fit side by side.

2. Why?

Safe access for wheelchair users; the current layout fails the clinical team's walk-through.

3. Impact (L = low, M = medium, H = high)

AreaImpactDetail
ScopeLMHTwo walls and ventilation ducts moved
TimeLMH1 week on the critical path, recoverable by overlapping two finishing tasks
CostLMH€18,000 from contingency
QualityLMHImproves accessibility; ventilation re-inspection needed
RiskLMHSmall risk of rework in the overlap
Other workLMHEquipment layout drawing updated

4. Options

OptionCostTimeRisk
Do it now, overlap finishing tasks€18,0000 weeks netLow
Do it after opening€30,000Clinic closed 1 weekMedium
Don't do it€0NoneAccess problem remains

5. Decision

ApprovedApproved with conditionsRejectedDeferred
Decided by
Change board: Atticus (Sponsor), Amani (Clinical Lead), Arash (Contractor)

After approval: update the change log, plans, baselines and contracts, and tell everyone affected.

Letters and symbols: CR Change request (CR-07 = change request number 7)

Day in the Role · Change requestIllustrative example · not a real project or organisation · dayintherole.com