| Version | 1.0 |
|---|---|
| Date | 15 March |
| No. | Date | Change | Raised by | Cost € | Days | Decision | Decided by | Contingency left € |
|---|---|---|---|---|---|---|---|---|
| Opening contingency | 150,000 | |||||||
| CR-05 | Week 17 | Extra drying work, north wall damp | Arash (Contractor) | 20,000 | 0 | Approved | Annelise (Project Manager) | 130,000 |
| CR-07 | Week 22 | Move two walls in the treatment area | Amani (Clinical Lead) | 18,000 | 0 | Approved | Change board | 112,000 |
| CR-08 | Week 24 | Oak panelling in reception (unrequested) | Arash (Contractor) | 0 | 0 | Rejected: replaced with specified surface | Annelise (Project Manager) | 112,000 |
| CR-09 | Week 24 | One extra receptionist for Saturdays | Azadeh (Community Council) | 2,000 | 0 | Approved | Atticus (Sponsor) | 110,000 |
Only approved changes reduce the balance. Record rejected and deferred changes too.
Letters and symbols: CR Change request (CR-07 = change request number 7)